Hartshorn v. Chaddock

16 N.Y.S. 714, 40 N.Y. St. Rep. 953, 61 Hun 623, 1891 N.Y. Misc. LEXIS 2202
New York Supreme Court·Decided October 23, 1891·Published·Cited by 1 cases

Opinion

Lewis, J.

The referee found as facts that Canacedea creek is a non-navigable stream of water, flowing in a north-easterly direction, and in nearly a. straight course, between Main and Genesee streets, in the city of Hornellsville, N. Y., and was so May 31, 1889, except as obstructed and dammed by the defendant’s piling in the rear of his lot; that the plaintiff was the owner .n fee, on May 31, 1889, of a lot of land lying upon the southerly side and adjacent to said creek, opposite the land of the defendant; that the average width of the channel of the creek was originally about 140 feet, with low and sloping banks between Main and West Genesee streets, and that in time of ordinary high water or freshets the waters of the creek were accustomed to-, overflow the banks thereof, and to cover the land generally north of the stream or adjacent to its left bank, some 100 feet from its present location and channel, and that at such times there was some overflow of the lands of the plaintiff; that the bed of the stream between the streets mentioned had been from time to time changed to the south by the filling in of the land upon the-northerly side thereof; that the plaintiff and his grantors had driven piles, along the bank of the creek adjacent to his lands, opposite and above and below the defendant’s lands, and covered the same with plank, and raised the-bank along the creek on his lands, to protect the same, and prevent the stream from further encroaching upon and washing away his land; that such planking did not impede, obstruct, or hinder the flow of the water in the-creek as it was originally accustomed to flow; that during the summer of 1888 the defendant drove, and caused to be driven, on the north-westerly side-of the creek, and opposite the plaintiff’s land, a number of piles, and caused and procured others to be driven along the bank of the creek above and below his premises, extending and projecting south-easterly into the channel of the-creek á distance of from 23 to 30 feet, the same being slightly curved, and that the piles were higher above the ground than the plaintiff’s land on the-opposite bank; they were sheeted with plank from the bottom to the top of " the pile-i, and that he filled in in the rear of the embankment with dirt, stone, and rubbish nearly to the height of the planking, and so constructed it as to-prevent the flowing of the water of the creek through the obstruction, and formed by the piling and embankment a solid dam or obstruction extending into-the channel of the creek as it then flowed, and obstructing the flow of the water for nearly one-third of its width as it existed before the embankment was-[715] constructed, and narrowed the channel at least 20 feet more than the average width of the stream at the points above and below the obstruction of the defendant, between Main and West Genesee streets; that the obstruction was maintained until the 1st of June, 1889; that it was an illegal obstruction to-the flow of water in the creek in times of high water or freshets, and dangerous to lands on the opposite bank of the stream; that on and previous to the 31sl of May, 1889, the plaintiff was the owner of the land opposite such piling and obstruction on the southerly bank of the creek, and extending down the stream south-easterly below the same; that on the lands of the plaintiff was stored and located a large amount of personal property, consisting of wood, lumber, shingles, wagon, and other property belonging to-the plaintiff; that on the night of May 81, 1889, and morning of June 1st, there was a long, heavy rain, and the water of the creek was raised several feet in height, and was largely increased in volume and velocity; that during such rise and freshet the waters were dammed and obstructed by defendant’s piling, and displaced and forced to the southerly bank upon the lands of the plaintiff, and against the plaintiff’s piling, breaking down the piling and embankment of the plaintiff, overflowing his land opposite to and below the defendant’s obstruction, and injuring and destroying said personal property; that defendant’s obstruction prevented the water from passing down the stream as it would had the planking and embankment not bqen placed there; that 1,600 yards of the earth on plaintiff’s lot were thereby washed away, and he suffered damages in all to the amount of $866.25; that the freshet was not usual or frequent in the creek, but was of the kind or volume of water and velocity of current that has periodically occurred in the past, and is liable to occur in the future, from heavy rains or melting snows, and that when such freshets occur the waters must be forced out of the channel over upon the lands of the plaintiff by the obstruction so constructed by the defendant. He found as a conclusion of law that the plaintiff was entitled to judginentagainst the defendant for the sum of $866.25, with costs. There was evidence tending to show that while the defendant was engaged in constructing the embankment he was remonstrated with, and admonished of the probable consequences which followed. While the proof shows that others had also encroached upon the bed of the stream by driving piles on the northerly side, there would have been left a space of 90 feet in width, which would have been sufficient to pass the waters of the stream, had it not been for the obstruction constructed by the defendant. -

Free access — add to your briefcase to read the full text and ask questions with AI

Hartshorn v. Chaddock, 16 N.Y.S. 714, 40 N.Y. St. Rep. 953, 61 Hun 623, 1891 N.Y. Misc. LEXIS 2202 (N.Y. Super. Ct. 1891).

16 N.Y.S. 714 (Hartshorn v. Chaddock) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ordway v. Village of Canisteo
21 N.Y.S. 835 (New York Supreme Court, 1893)