Hartford St. Boiler v. Murray Turbo M., No. Cv91-039 00 75 S (Mar. 28, 1995)

1995 Conn. Super. Ct. 2925
CourtConnecticut Superior Court
DecidedMarch 28, 1995
DocketNo. CV91-039 00 75 S
StatusUnpublished

This text of 1995 Conn. Super. Ct. 2925 (Hartford St. Boiler v. Murray Turbo M., No. Cv91-039 00 75 S (Mar. 28, 1995)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford St. Boiler v. Murray Turbo M., No. Cv91-039 00 75 S (Mar. 28, 1995), 1995 Conn. Super. Ct. 2925 (Colo. Ct. App. 1995).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION ON DEFENDANT'S MOTION FOR SUMMARY JUDGMENT In this case the plaintiff insurance company has brought an action in subrogation suing for breach of a contract CT Page 2926 between the defendant and the plaintiff's insureds.

The contract involved the sale of a steam turbine/generator set by the defendant to Process Construction Services, Inc. (PCS).

The plaintiff provides various types of insurance for steam turbines and related equipment. The plaintiff provided so-called "delay in start up" insurance coverage to the insureds. The insureds had entered into a so-called turnkey construction agreement whereby Process Construction Services, Inc. agreed to construct a co-generation facility to provide electricity to Hartford Hospital.

The equipment was manufactured by the defendant and delivered and during testing a malfunction occurred. Damage was done to the turbine unit and the plaintiff contends as the result of the equipment's malfunction the start up date of the co-generation facility was delayed.

The insureds allegedly sustained a loss of profits as a result of the delay in starting the co-generation facility and they made an insurance claim against the plaintiff insurance company which paid money on the claim. The plaintiff initiated this subrogation action against the defendant manufacturer to recoup what it paid for its insured's consequential damages.

The defendant has brought a motion for summary judgment. The defendant claims the plaintiff's insureds accepted the defendant's demand that it have no liability for consequential damages. By seeking to recoup what it paid out to its insureds the defendant maintains that the plaintiff in effect seeks to avoid the contract limitations to which its own insured had agreed.

In ruling on a motion for summary judgment the trial court must determine if an issue of fact exists but cannot try that issue if it does exist, McColl v. Pataky, 160 Conn. 457,459 (1971). The moving party must exclude any real doubt as to the existence of any genuine issue of material fact.Dougherty, v. Graham, 161 Conn. 248, 250 (1971). The test is whether the moving party would be entitled to a directed verdict, Batick v. Seymour, 180 Conn. 632 (1982). In deciding such a motion and the issues raised by it the evidence is to CT Page 2927 be viewed in the light most favorable to the non-moving party.Connell v. Connell, 214 Conn. 242 (1990).

The question before the court is whether the contract between the defendant and Process Construction Services, Inc. ("PCS") permit a claim for consequential damages.

The facts regarding contract formation between the defendant and PCS are of course determinative for the resolution of the motion before the court. The parties submitted various affidavits and documents which contain much that is undisputed, at least in factual terms, between the parties. In April of 1986 PCS sent the defendant an inquiry about the firm price bid it would place on a steam turbine/generator. On May 8, 1986, the defendant Murray forwarded a sales proposal. The proposal quoted prices for the work and stated any prices were firm only for orders placed before May 31, 1986. The May 8 proposal stated that "our terms and conditions of sale will apply to this offering" and this included a section on "Guarantees." In that portion of the May 8 proposal it states that if a part of the delivered equipment is found to be defective "then we will repair the defective part or furnish a similar part to replace it. . . . The guarantee specifically set forth above is our only guarantee and is made in lieu of all other warranties whether of merchantability or otherwise whether expressed or implied by law or trade usage and of all other obligations or liabilities on our part and will neither assume for us any other liability in connection with the sale of our apparatus. . . . In no event shall we be liable for any consequential damages or loss of anticipated profits."

It is undisputed that an order was not placed with the defendant within the time limit set forth in the May 8 proposal. Over a year later on April 23, 1987 representatives of the defendant and PCS met in order to negotiate terms for the sale of the equipment referred to in the May 8, 1986 proposal. On April 24, 1987 Mr. Perry of the defendant company sent a letter to Mr. Griffin the president of PCS. The letter contained twenty two issues which the defendant's representative said were discussed at the meeting of April 23, 1987. The letter states that it contains notes of what was discussed at the meeting. It does not mention the May 8, 1986 letter but does state "our standard warranty will apply . . ." The letter acknowledges that the insureds will issue a CT Page 2928 purchase order at some point in the future. The letter at no point states it was being sent in confirmation of a contract.

On April 24, 1987 the insured also sent a letter to the defendant Murray corporation. This letter said the insured PCS intends to issue a purchase order for a steam turbine generator "per the agreements reached in our meeting held April 23, 1987 at our office." Mr. Griffin of PCS also directed Murray to "proceed with any engineering required to meet the delivery date."

On May 6, 1987 Mr. Griffin sent another confirmatory letter to Murray which indicates there was agreement as to purchase price, terms of payment and delivery date. Neither the April 24, 1987 nor the May 6, 1987 Griffin letters make any reference to the May 8, 1986 letter.

On May 19, 1987 PCS sent Murray a "sample copy of our purchase order" and asked Murray specifically to review the draft purchase order and sought the defendant's concurrence on the final form of the purchase order. The sample purchase order does not specifically reference the May 8, 1986 proposal. However, the sample purchase order stated: "General Conditions of PCSI Purchase Order shall apply." Murray apparently obtained a copy of those conditions and condition number 4 stated: "Seller agrees to indemnify and save harmless purchaser from any loss, including consequential damages, resulting from the defective or non-conforming condition of material and equipment."

In its brief of 7/26/94 at page 6 defense counsel says Murray "noted" this language conflicted with the warranty limitations in Murray's May 8, 1986 proposal and thus with the agreements Murray claims were reached during the April 23, 1987 negotiations.

"Noticing the unacceptable proposed term with regard to consequential damages" the telefax messages flew and Murray requested that the offending language be removed from the purchase order. Murray sent the following telefax on June 3:

"Murray cannot accept liability for consequential damages. Since we do not know all of the aspects of the job, we cannot evaluate the risks involved with accepting liability for consequential damages. CT Page 2929 We request that the last sentence be removed from item 4." (Ex. 7)

In this response by Murray to the sample purchase order no actual reference is made to the May 8, 1986 proposal nor does the language used by Murray directly suggest or indirectly infer that Murray thought a previously arrived at April 23 agreement concerning consequential damages was being abrogated by the "unacceptable" language in the sample purchase order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dougherty v. Graham
287 A.2d 382 (Supreme Court of Connecticut, 1971)
McColl v. Pataky
280 A.2d 146 (Supreme Court of Connecticut, 1971)
Wade v. Yale University
30 A.2d 545 (Supreme Court of Connecticut, 1943)
State v. Gold
431 A.2d 501 (Supreme Court of Connecticut, 1980)
Russell v. Dean Witter Reynolds, Inc.
510 A.2d 972 (Supreme Court of Connecticut, 1986)
Connell v. Colwell
571 A.2d 116 (Supreme Court of Connecticut, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
1995 Conn. Super. Ct. 2925, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-st-boiler-v-murray-turbo-m-no-cv91-039-00-75-s-mar-28-connsuperct-1995.