Hartford Fire Ins. Co. v. DeBra-Kuempel Inc.

2024 Ohio 5830
CourtOhio Court of Appeals
DecidedDecember 13, 2024
DocketC-240100
StatusPublished
Cited by2 cases

This text of 2024 Ohio 5830 (Hartford Fire Ins. Co. v. DeBra-Kuempel Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Fire Ins. Co. v. DeBra-Kuempel Inc., 2024 Ohio 5830 (Ohio Ct. App. 2024).

Opinion

[Cite as Hartford Fire Ins. Co. v. DeBra-Kuempel Inc., 2024-Ohio-5830.]

IN THE COURT OF APPEALS FIRST APPELLATE DISTRICT OF OHIO HAMILTON COUNTY, OHIO

THE HARTFORD FIRE INSURANCE : APPEAL NO. C-240100 COMPANY, AS SUBROGEE OF BLUE TRIAL NO. A-2203885 ASH FUNDING COMPANY, LLC, :

Plaintiff-Appellant, : OPINION vs. :

DEBRA-KUEMPEL, INC., :

Defendant-Appellee/Third- : Party Plaintiff, : vs. : IMEG CONSULTANTS CORP., f.k.a PEDCO E&A SERVICES, INC., :

Third-Party Defendant- Appellee. :

Civil Appeal From: Hamilton County Court of Common Pleas

Judgment Appealed From Is: Affirmed in Part and Appeal Dismissed in Part

Date of Judgment Entry on Appeal: December 13, 2024

Rendigs, Fry, Kiely & Dennis LLP, Jonathan P. Saxton, James J. Englert, Whelan Ransel, LLC, and C. Zachary Ransel, for Plaintiff-Appellant,

Reminger Co., LPA, and Michael J. Caligaris, for Defendant-Appellee/Third-Party Plaintiff,

McNeal Schick Archibald & Biro Co., LPA, and Brian T. Winchester, for Third-Party Defendant-Appellee. OHIO FIRST DISTRICT COURT OF APPEALS

BOCK, Presiding Judge.

{¶1} After a heating coil malfunctioned in Blue Ash Funding Company,

LLC’s, newly-renovated office building (“the Property”), causing extensive damage,

Blue Ash made a claim with its insurer, plaintiff-appellant The Hartford Fire

Insurance Company. Hartford paid Blue Ash’s claim.

{¶2} Attempting to recoup those funds, Hartford filed a subrogation claim

against defendant-appellee/third-party-plaintiff DeBra-Kuempel, Inc., asserting that

the company had negligently engineered, designed, and/or installed the heating coil.

DeBra-Kuempel then sued third-party defendant-appellee IMEG Consultants Corp.,

f.k.a. PEDCO E&A Services, Inc., (“PEDCO”) seeking indemnification and

contribution. The trial court granted summary judgment in DeBra-Kuempel’s and

PEDCO’s favor. Hartford appeals.

{¶3} We hold that a contract provision in which Blue Ash and the renovation

project’s architect waived all rights to damages against the project’s subcontractors

bars Hartford’s claim against DeBra-Kuempel. And we further hold that Hartford

lacks standing to appeal the trial court’s summary judgment in PEDCO’s favor.

I. Facts and Procedure

A. Facts

{¶4} A malfunctioning HVAC unit caused extensive water damage to the

Property. Although factual disputes existed, because the trial court granted summary

judgment on a legal issue—the interpretation of the contracts’ subrogation-waiver

provisions—many facts underlying this case are not relevant.

2 OHIO FIRST DISTRICT COURT OF APPEALS

i. The parties’ contracts contained waiver provisions

{¶5} In 2018, Symphony Development Partners, LLC, Blue Ash’s

predecessor-in-interest, retained BHDP Architecture to renovate the Property. BHDP

and Symphony signed two separate documents comprising the agreement between

them (collectively “the Contract”): an AIA Document B101-2017, “Standard Form of

Agreement Between Owner and Architect Agreement” (“B101”) and an AIA Document

A201-2017, “General Conditions of the Contract for Construction” (“A201”).

Symphony assigned its rights under the Contract to Blue Ash in April 2020. The

Contract contained three subrogation-waiver provisions.

{¶6} Section 8.1.2 of the B101 (“Section 8.1.2”) provides:

To the extent damages are covered by property insurance, the

Owner and Architect waive all rights against each other and against the

contractors, consultants, agents, and employees of the other for

damages, except such rights as they may have to the proceeds of such

insurance as set forth in AIA Document A201-2017, General Conditions

of the Contract for Construction.

{¶7} Section 11.3.1 of the A201 (“Section 11.3.1”) provides:

The Owner and Contractor waive all rights against (1) each other

and any of their subcontractors, sub-subcontractors, agents, and

employees, each of the other; (2) the Architect and Architect’s

consultants; and (3) Separate Contractors, if any, and any of their

subcontractors, sub-subcontractors, agents, and employees, for

damages caused by fire, or other causes of loss, to the extent those losses

are covered by property insurance required by the Agreement or other

3 OHIO FIRST DISTRICT COURT OF APPEALS

property insurance applicable to the Project, except such rights as they

have to proceeds of such insurance. However, the scope of this waiver

shall be limited to damages to the Work itself, and this waiver shall not

apply to property insurance purchased by the Owner after completion

of the Work or final payment, whichever comes first.

{¶8} Finally, Section 11.3.2 of the A201 (“Section 11.3.2”) provides:

If during the Project construction period the Owner insures properties,

real or personal or both, at or adjacent to the site by property insurance

under policies separate from those insuring the Project, or if after final

payment property insurance is to be provided on the completed Project

through a policy or policies other than those insuring the Project during

the construction period, to the extent permissible by such policies, the

Owner waives all rights in accordance with the terms of Section 11.3.1

for damages caused by fire or other causes of loss covered by this

separate property insurance.

ii. DeBra-Kuempel and PEDCO completed work on the Project

{¶9} Renovations to the Property started in 2019. BDHP retained PEDCO as

the mechanical, electrical, and plumbing engineering consultant for the Project.

Symphony retained Danis Building Construction Company as the general contractor

for the Project. Danis, in turn, subcontracted with DeBra-Kuempel to perform HVAC

installation work at the Project.

iii. The HVAC system failed and Hartford paid Blue Ash’s claim

{¶10} In December 2020, shortly after construction was completed, an HVAC

unit failed, resulting in substantial water damage to the Property. The property

4 OHIO FIRST DISTRICT COURT OF APPEALS

manager stated that the leak caused flooding in “a new section that had just been

renovated.”

{¶11} After Blue Ash filed an insurance claim, Hartford paid Blue Ash, its

insured, $1,905,222.21 to cover the loss. In opposing summary judgment below,

Hartford asserted that the policy under which Hartford paid Blue Ash (“the Policy”)

was neither a “builder’s risk policy” nor a policy insuring the work on the Project or

the Project itself. Rather, Hartford argued, the Policy was separate from any policies

insuring the Project. The Policy covered the cost to return the Property to “pre-loss

condition,” but covered damages for “direct physical loss” only. There were no other

insurance policies in place that might have covered the loss.

{¶12} The policy permitted Blue Ash to waive its rights to collect damages

against another “prior to a covered loss or damage.” But it included an exception: “For

their interest in building repair or construction, you may not waive your rights to

recover damages from architects or engineers except as agreed to in writing by us.”

B. Procedural history

{¶13} Hartford, as subrogee of Blue Ash, sued DeBra-Kuempel, alleging a

single count of negligence. DeBra-Kuempel filed a third-party complaint against

PEDCO, seeking indemnification and contribution from PEDCO if DeBra-Kuempel

were found liable to Hartford.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maccarone v. Mark Mandell-Brown, M.D., Inc.
2025 Ohio 5071 (Ohio Court of Appeals, 2025)
Branson v. Fifth Third Bank, N.A.
2025 Ohio 4396 (Ohio Court of Appeals, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2024 Ohio 5830, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-fire-ins-co-v-debra-kuempel-inc-ohioctapp-2024.