Hartford Accident & Indemnity Company v. Michael P. W. Stone, Secretary of the Army

996 F.2d 317, 1993 WL 96874
CourtCourt of Appeals for the Federal Circuit
DecidedApril 5, 1993
Docket91-1383
StatusUnpublished
Cited by1 cases

This text of 996 F.2d 317 (Hartford Accident & Indemnity Company v. Michael P. W. Stone, Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Accident & Indemnity Company v. Michael P. W. Stone, Secretary of the Army, 996 F.2d 317, 1993 WL 96874 (Fed. Cir. 1993).

Opinion

996 F.2d 317

NOTICE: Federal Circuit Local Rule 47.8(b) states that opinions and orders which are designated as not citable as precedent shall not be employed or cited as precedent. This does not preclude assertion of issues of claim preclusion, issue preclusion, judicial estoppel, law of the case or the like based on a decision of the Court rendered in a nonprecedential opinion or order.
HARTFORD ACCIDENT & INDEMNITY COMPANY, Appellant,
v.
Michael P. W. STONE, Secretary of the Army, Appellee.

No. 91-1383.

United States Court of Appeals, Federal Circuit.

April 5, 1993.

Before NIES, Chief Judge, and PLAGER and ALARCON,* Circuit Judges.

PLAGER, Circuit Judge.

Hartford Accident & Indemnity Company (Hartford) appeals from a decision of the Armed Services Board of Contract Appeals (ASBCA or Board).1 Hartford, a surety who had taken over for a defaulting principal contractor, had appealed two claims to the ASBCA, after receiving no satisfaction from the contracting officer. The Board dismissed Hartford's appeal. The first claim, alleging overpayment to the defaulting contractor, was dismissed for lack of proper certification. The second claim, regarding replacement of a lost check, was dismissed on the ground that Hartford did not even purport to have "submitted" the claim pursuant to the Contract Disputes Act. We reverse-in-part, vacate-in-part and remand for further consideration.

BACKGROUND

In September 1980, the New York District, Army Corps of Engineers (Army or Government) awarded a construction contract to Juno Construction Corporation and Main Power & Electric Wiring Corporation, A Joint Venture (Juno). The contract dealt with construction of an Armed Forces Reserve Center in Middletown, New Jersey. Hartford was Juno's surety on the performance bond for the contract.

Juno later defaulted on the contract, and its right to proceed under the contract was terminated by the Government on October 28, 1982. On December 2, 1982, Hartford, as surety, assumed the remaining rights and obligations of Juno pursuant to a takeover agreement executed in the form of a Change Order. The agreement was signed on behalf of Hartford by Stephen G. Pazar (Pazar), a regional bond claims manager. Pazar then supervised the performance of the work done pursuant to the agreement.

Substantial completion of the construction project was accomplished on April 5, 1984. On November 12, 1984, Hartford sent a letter to the Army requesting issuance of replacements for two checks, in the amounts of $20,633 and $42,200, which were lost in the mail or otherwise misplaced. The Army's response notified Hartford that an effort was being made to trace the two checks.

On May 13, 1985, Hartford submitted a claim to the contracting officer for $235,896, an amount allegedly overpaid to Juno by the Government. Pazar certified and submitted the claim for Hartford.

The contracting officer denied the overpayment claim on September 9, 1988. In the meantime, having heard nothing about the tracing of the checks, Hartford again inquired about replacement checks, via letters to the Army District Counsel dated June 23 and August 11, 1988. On November 4, 1988, Hartford requested a "final decision" from the contracting officer on the replacement check issue, for the check written for $42,200.2

On November 28, 1988, Hartford appealed to the ASBCA the denial of its claim for the overpaid funds. Hartford also attempted to appeal its lost check claim, despite the fact that the contracting officer had not rendered a decision on the issue.

The ASBCA issued an order on January 16, 1991, which sua sponte questioned the certification of Hartford's overpayment claim. The order directed Hartford to show that Pazar was qualified to certify the claim, as required by 48 C.F.R. § 33.207(c)(2). Pursuant to the regulation, Hartford was told to demonstrate that Pazar was "a senior company official in charge at the contractor's plant or location involved," or "an officer ... of the contractor having overall responsibility for the conduct of the contractor's affairs."

Hartford referenced Pazar's deposition testimony that had been part of his certification that he had signed the takeover agreement on Hartford's behalf. The ASBCA then ordered the Government to address the jurisdictional question, and gave Hartford a chance to respond. Hartford again merely referred to Pazar's deposition testimony, pointing in particular to the sections referring to Pazar's sole responsibility at Hartford for the takeover contract and for completion of the construction project.

The ASBCA found Hartford's responses to be inadequate, and on February 19, 1991, ordered Hartford to file any further response to the jurisdictional issue. On February 25, Hartford submitted the certification of a Hartford assistant vice president, Robert J. Mathieu, who attested that Pazar was in charge of the completion and that no one in Hartford's home office had any personal knowledge which could form the basis of certification of the claim.

The ASBCA remained dissatisfied, and on February 28, 1991, found Hartford to be nonresponsive on the issue of jurisdiction. Both parties were given thirty days to file any additional documents in the proceeding.

On March 21, 1991, Hartford sent a letter alleging in detail that Pazar "is a 'senior company official in charge at the ...... location involved' and, therefore, his certification satisfies the requirements of [48 C.F.R. 33.207(c)(2)(i) ]." Hartford argued that Pazar had actual authority to certify the claim on behalf of Hartford, and that he satisfies the regulatory requirements.

On May 31, 1991, the Board dismissed Hartford's appeal for lack of jurisdiction, on the ground that Hartford failed to prove that Pazar qualifies to certify claims. The Board held that "[t]he record does not reflect where Mr. Pazar's job falls within the overall hierarchy of the company, or how extensive his responsibilities are compared to others."

The Board stated that, under 48 C.F.R. 33.207(c)(2)(i), "the certifying official must be both '[a] senior company official' and 'in charge at the contractor's plant or location involved.' United States v. Grumman Aerospace Corp., 927 F.2d 575, 580 (Fed.Cir.1991). In determining whether a certifying official is a senior company official, we look to his or her rank and managerial responsibilities within [Hartford]'s organization." The Board concluded that "[n]either Mr. Mathieu's certification ... [n]or Mr. Pazar's deposition contain an unqualified statement that Mr. Pazar is a senior company official."

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boston Edison Co. v. United States
106 Fed. Cl. 330 (Federal Claims, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
996 F.2d 317, 1993 WL 96874, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-accident-indemnity-company-v-michael-p-w-stone-secretary-of-cafc-1993.