Hartec Corp. v. GSE Associates, Inc.

91 So. 3d 375, 2010 La.App. 1 Cir. 1332, 2012 La. App. LEXIS 199, 2012 WL 600611
CourtLouisiana Court of Appeal
DecidedFebruary 24, 2012
DocketNo. 2010 CA 1332
StatusPublished
Cited by2 cases

This text of 91 So. 3d 375 (Hartec Corp. v. GSE Associates, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartec Corp. v. GSE Associates, Inc., 91 So. 3d 375, 2010 La.App. 1 Cir. 1332, 2012 La. App. LEXIS 199, 2012 WL 600611 (La. Ct. App. 2012).

Opinions

McDonald, j.

I «.This case involves a dispute between Hartec Corporation (Hartec), Consolidated Waterworks District No. 1 (Waterworks), and GSE Associates, Inc. (GSE) concern[378]*378ing the Terrebonne Parish Schriever Water Plant Expansion project (the project). Waterworks retained the services of GSE to provide professional architectural and engineering services for the project. Waterworks hired Hartec to construct the plant, for the sum of $4,950,000.00, according to the plans and specifications prepared by GSE.

On June 26, 2002, Hartec notified Waterworks by letter that it was terminating the contract, pursuant to section 15.5 of the general conditions of the contract, due to suspension of work in excess of 90 days on two critical areas of the project, namely the filter trough openings and the dismantled piping in the high service pits. On September 6, 2002, Hartec filed suit against Waterworks, GSE, and Continental Casualty Company, GSE’s insurer. Hartec asserted that Waterworks, upon the recommendation of GSE, had refused to pay for completed work in the form of labor and materials placed on the project, and that in addition to the sums due on the contract, Hartec had suffered substantial additional expenses as a result of the acts and omissions of the defendants. The alleged acts and omissions included negligent undertaking of the architectural and engineering services on the project, failure to adequately prepare the plans and specifications, failure to furnish additional instruction and clarifications, failure to timely and fairly process requests for payments, failure to timely and fairly process requests for extensions of time, and failure to timely and properly inspect areas of work.

In particular, Hartec asserted that it was damaged due to the following acts or omissions of defendants: the failure of Waterworks pumps which contributed to flooding of the project; failure to provide owner-furnished items; failure to provide the correct elevations on the raw water suction piping; failure to timely provide | ..¡electrical drawings; engaging in decision making which unjustly enriched Waterworks and GSE; engaging in speculative investigations that delayed, interfered with and finally caused loss of continuity of construction on the project; failure to make timely and reasonable decisions regarding necessary changes, which caused delays in completion of the project; failure to provide the correct elevations and proper drawings to avoid conflict of piping and concrete beams at corridor No. 1; failure to provide the correct elevations and proper drawings to avoid conflict of piping and electrical services and Pipe Pit C; failure to grant extensions of time, which accelerated the cost; failed to adequately provide for construction joints in the clearwell roof; failure to process change orders in a timely manner; failure to provide the correct elevations and proper drawings to avoid conflict of suction piping; and other acts of negligence and unjust enrichment to be shown at trial.

Hartec asserted that GSE breached its duty of care and skill owed to Hartec by failing to adequately prepare plans and specifications on behalf of Waterworks; failing to accept responsibility for design errors; and failing to objectively, timely and fairly make decisions regarding processing change orders, requests for payments and extensions of contract time. Further, Hartec asserted that as a result of GSE’s failure to perform its duties and obligations, Hartec was damaged and suffered costs and expenses to be shown at trial.

Waterworks filed a Third Party Demand against West American Insurance Company, the surety for Hartec, and a Reconven-tional Demand against Hartec and GSE, seeking damages for liquidated damages, excess completion costs, engineering fees and remediation costs.

[379]*379In accordance with La. R.S. 13:5105, a bifurcated trial was conducted with a jury deciding the issues concerning the nonpublic entities (Hartec’s claims against GSE) and a judge deciding the issues concerning the public entity (Hartec’s |4claims against Waterworks and Waterworks’ claims against Hartec and GSE). The statute prohibits a jury trial in suits against political subdivisions of the state, except where timely demand for a jury trial is made by the state, a state agency, or a plaintiff in a lawsuit against the state or state agency. La. R.S. 13:5105(A).

After a trial on the merits, the jury rendered a verdict in favor of Hartec and against GSE in the amount of $909,222.49, consisting of the unpaid contract balance, additional costs incurred, and delay damages. The jury also found that GSE was solely at fault and attributed no fault to Hartec. Having taken the Waterworks portion of the case under advisement, the trial judge issued a judgment on February 9, 2009, that is inconsistent with the jury verdict. He found in favor of Waterworks and against Hartec in the amount of $1,555,472.69, consisting of excess completion costs and nearly a half million dollars in liquidated damages, and dismissed Waterworks’ claims against GSE. The judgment, dated February 9, 2009, includes both verdicts. GSE filed a motion for new trial and judgment notwithstanding the verdict, which were denied. This situation points out the difficulty that can occur in bifurcated trials with a jury deciding part of the case and a judge deciding the rest. The judicial history of this situation is very well summarized and discussed by Benjamin David Jones in his excellent Loyola Law Review article.1

GSE and Continental appealed the portion of the judgment against them, but later requested that the appeal be dismissed because of a settlement with Har-tec. This appeal was dismissed on September 29, 2010. Hartec appealed the judgment against it, citing nine assignments of error:

1. The lower court erred in rejecting Hartec’s claims for the contract balance.
2. The lower court erred in rejecting Hartec’s claims for delay damages caused [5by the negligent action of CWWs2 engineer, GSE.
3. The lower court erred in assessing liquidated damages against Hartec in the amount of $479,500.00.
4. The lower court erred in rejecting Hartec’s claims for extra compensation.
5. The lower court erred in finding that the costs to complete the Project, $1,492,637.16 were reasonably incurred and supported by the record.
6. The lower court erred in concluding that the plans and specifications prepared by GSE were adequate.
7. The lower court erred in disregarding the factual findings of the jury.
8. The lower court erred in assessing legal interest from the date of judicial demand.
9. The lower court erred in rejecting the surety defenses of waiver and overpayment and holding West American Insurance Company liable [380]*380for amounts in excess of the unpaid portions of the contract balance.

Before considering the merits of Har-tec’s appeal, it is necessary to determine the standard of review in a bifurcated trial.

BIFURCATION

In assignment number 7, Hartec suggests that the lower court erred in disregarding the factual findings of the jury and questions whether the jury’s decision to hold GSE liable is binding on the judge.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kelly Doucet v. Hornet Service Company
Louisiana Court of Appeal, 2019
Sullivan v. City of Baton Rouge
170 So. 3d 186 (Louisiana Court of Appeal, 2015)
Gutierrez v. Louisiana Department of Transportation & Development
92 So. 3d 380 (Louisiana Court of Appeal, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
91 So. 3d 375, 2010 La.App. 1 Cir. 1332, 2012 La. App. LEXIS 199, 2012 WL 600611, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartec-corp-v-gse-associates-inc-lactapp-2012.