Harry J. Diebold v. Moore McCormack Bulk Transport Lines, Inc.

805 F.2d 55, 1987 A.M.C. 308, 1986 U.S. App. LEXIS 33346
CourtCourt of Appeals for the Second Circuit
DecidedNovember 6, 1986
Docket207, Docket 86-7399
StatusPublished
Cited by34 cases

This text of 805 F.2d 55 (Harry J. Diebold v. Moore McCormack Bulk Transport Lines, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harry J. Diebold v. Moore McCormack Bulk Transport Lines, Inc., 805 F.2d 55, 1987 A.M.C. 308, 1986 U.S. App. LEXIS 33346 (2d Cir. 1986).

Opinion

MANSFIELD, Circuit Judge:

Harry J. Diebold, a bosun, appeals from a judgment of the Southern District of New York, Charles M. Metzner, J., dismissing his action for damages for personal injuries sustained as the result of an accident which occurred while he was working as a member of the crew of the defendant’s *56 ship S.S. MORMACSUN. The action is based on negligence under the Jones Act, 46 U.S.C. § 688, and the law of unseaworthiness. The judgment was entered pursuant to the court’s order directing a verdict for the defendant at the close of the plaintiff’s case. We reverse.

The facts, as testified to by the plaintiff, whose testimony must be viewed most favorably to him upon our review of a directed verdict for the defendant, Mattivi v. South African Marine Corp., “Huguenot”, 618 F.2d 163, 168 (2d Cir.1980), were as follows. On the morning of January 13, 1984, the plaintiff, a bosun, acting pursuant to the orders of his immediate superior, Chief Mate William Smith, removed a metal step located inside a room called a “locker” and just below a watertight entrance door, aboard the MORMACSUN so that chipping and painting of the locker could proceed. The entrance door, located in the bulkhead, was approximate 5V2 feet high and 3 feet wide. At its bottom it was approximately 16-18 inches above the deck, with one metal step on each side. The inside step, located in the locker, was secured by four bolts attached to four legs which were secured to the deck by “padeyes”, or semi-circular 3V2 inch-high pieces of steel in the form of upside-down “U’s” welded to the deck, through which nuts and bolts were secured to hold the steps in place. Once the steps were removed, the four padeyes protruded approximately 3V2 inches up from the deck in the area below the inside door-opening.

As the chipping of paint in the locker was in progress after the step had been removed, the Chief Mate ordered the plaintiff and his men to start cleaning tanks. This task required the plaintiff and his crew to move certain heavy equipment from the locker through its door to the outside deck. The equipment included hoses (75 to 100 feet long), “saddles” (pieces of machinery about 3V2 to 4 feet high) and lines. When the plaintiff asked the Chief Mate whether the metal step should not be put back in place for this operation, the Chief Mate, replying that it was a rush job and that there was not enough time, ordered the plaintiff to get some pallets and place them inside at the point below the locker door where the metal step had been removed, stating “that is it.”

The pallets were wooden platforms about 4 by 4 feet in surface area and 4 or 5 inches high, consisting of 2- by 4-inch lumber as base pieces, covered by wooden slats about V2 inch in thickness and 3 to 4 inches in width. Ordinarily pallets, which are made of cheap wood and disposable, are not uniform in size and are used to keep cargo, such as drums or wire, above water that might be found in a ship’s hold.

In order to create a temporary step up to the locker door from the inside, the plaintiff placed two pallets, one on top of the other, against the metal wall below the sill of the door and a third in front of them to create a step up from the inside to the two. However, when he tried to put the pallets between the exposed metal padeyes, it “didn’t work”. In order to gain elevation he then placed the two pallets on top of the padeyes. Since the temporary step thus created was “wobbly” he sought to steady it by placing under the pallets some light 3-inch by 2-inch pieces of wood, scrap and dunnage. The result was a makeshift, jury-rigged step.

Thereafter, the Chief Mate entered or looked into the locker, directed the plaintiff regarding the tanks that were to be cleaned, and departed. While the plaintiff, and a crew member were carrying heavy equipment out of the locker for use in the tank cleaning operation, the plaintiff stepped onto the temporary pallet-step, which then rocked, causing him to fall off, drop his end of the load, and suffer injuries.

On July 10, 1984, plaintiff commenced the present action, alleging, among other things, negligence based on the work order of the Chief Mate, failure to provide a reasonably safe place to work, and the existence of improper equipment. Defendant answered with a general denial and an affirmative defense to the effect that plaintiff’s injuries were caused by his own negligence.

*57 At trial the plaintiff introduced his own testimony as summarized above and that of a maritime expert, former Chief Officer James E. Byrnes, who had also served on merchant ships as a Chief Mate, and of a doctor. Byrnes testified that in the chain of command of a U.S. merchant vessel such as the MORMACSUN a bosun is obligated to obey the orders of the Chief Mate, even if those orders result in an unsafe condition. According to Byrnes, the bosun could change such an alleged unsafe condition only with the permission of the Chief Mate, and the Chief Mate in the present case should have ordered Diebold to put the metal step back in place rather than direct that pallets be used in its stead. Byrnes further testified that, once the Chief Mate ordered the plaintiff to use the pallets because of the need for speed and the plaintiff found that the pallets were unsafe, the plaintiff might have the “option” to advise the Chief Mate of the unsafe condition but that the plaintiff did not have the right to change the condition.

At the conclusion of the plaintiffs case the trial judge, without a written opinion, granted the defendant’s motion to dismiss the complaint on the ground that the plaintiff had failed to establish a prima facie case. In a sometimes unclear exchange with plaintiffs counsel, the judge took the view that, although the plaintiff was bound to follow the Chief Mate’s order to use the pallets rather than replace the step as the plaintiff had suggested, the Chief Mate had not instructed the plaintiff regarding how to set up the pallete, which might be arranged so that “they wouldn’t be wobbly” and the plaintiff, once he discovered that the makeshift pallet substitute was wobbly and therefore unsafe, owed a duty to advise the Chief Mate of the unsafe condition, which the plaintiff did not do. This appeal followed.

DISCUSSION

The controlling issue on this appeal is whether the trial judge erred in granting a directed verdict dismissing the complaint on the ground that the plaintiff was solely negligent and therefore barred as a matter of law from any recovery for injuries caused by negligence in assembling and using an unsafe step consisting of stacked pallets, as directed by his superior, the Chief Mate. The answer requires a brief review of applicable legal principles.

A directed verdict, like a judgment n.o.v., may be granted only when, viewing the evidence most favorably to the party other than the movant, “there can be but one conclusion, as to the verdict that reasonable men could have reached.” Mattivi, supra, 618 F.2d at 167 (quoting Simblest v. Maynard, 427 F.2d 1, 4 (2d Cir.1970)). See in accord Haskell v. Kaman Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
N.D. New York, 2026
Martinez v. City of New York
684 F. App'x 90 (Second Circuit, 2017)
Soliman v. Maersk Line Ltd.
235 F. Supp. 3d 410 (E.D. New York, 2017)
Seemann v. Coastal Environmental Group, Inc.
219 F. Supp. 3d 362 (E.D. New York, 2016)
In re Bridge Construction Services of Florida, Inc.
39 F. Supp. 3d 373 (S.D. New York, 2014)
Quiles v. City of New York
978 F. Supp. 2d 374 (S.D. New York, 2013)
Kennedy v. Adamo
323 F. App'x 34 (Second Circuit, 2009)
Bailey v. SEABOARD BARGE CORP.
385 F. Supp. 2d 310 (S.D. New York, 2005)
Wills v. Amerada Hess Corp.
379 F.3d 32 (Second Circuit, 2004)
Nasser v. CSX LINES, LLC.
191 F. Supp. 2d 307 (E.D. New York, 2002)
Yurman Design, Inc. v. Paj, Inc.
93 F. Supp. 2d 449 (S.D. New York, 2000)
Lombas v. Moran Towing & Transportation Co.
899 F. Supp. 1089 (S.D. New York, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
805 F.2d 55, 1987 A.M.C. 308, 1986 U.S. App. LEXIS 33346, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harry-j-diebold-v-moore-mccormack-bulk-transport-lines-inc-ca2-1986.