Harrison v. Louisiana Power & Light Co.

274 So. 2d 785, 1973 La. App. LEXIS 6075
CourtLouisiana Court of Appeal
DecidedMarch 13, 1973
DocketNo. 5259
StatusPublished
Cited by3 cases

This text of 274 So. 2d 785 (Harrison v. Louisiana Power & Light Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harrison v. Louisiana Power & Light Co., 274 So. 2d 785, 1973 La. App. LEXIS 6075 (La. Ct. App. 1973).

Opinion

BOUTALL, Judge.

The owners of a certain tract of real estate brought suit against Louisiana Power and Light Company alleging that defendant constructed a power line across the front of their property without permission. The suit seeks damage for trespass, reimbursement for physical damages to the real estate, and also seeks removal of the power line. The trial court awarded plaintiffs $2,000.00 damages, but refused to order the removal of the power line. From this judgment the defendant power company has appealed, and plaintiffs have answered the appeal seeking an increase in damages and the removal of the power line.

The undisputed facts show that plaintiffs are the owners of a tract of ground fronting 900 feet on U.S. Highway 90 in St. Charles Parish near Boutte, Louisiana. Beginning in November, 1966, the defendant’s agents contacted the plaintiffs seeking permission to relocate an existing power line along the front of plaintiffs’ property with the utility poles to be located one foot inside the property line. Defendant’s purpose was to replace an existing power line which ran within the highway right-of-way with a line capable of carrying more power, and to relocate this line back out of the right-of-way for 2 reasons: one, to avoid possible conflict with relocation of the highway itself, and two, because the present line was located in a ditch or borrow pit containing water. The plaintiffs refused to permit the construction inside of the property line, but did agree to permit the construction with the poles located one foot outside their property line in the highway right-of-way. In the erection of this line, the defendant utilized the front portion of plaintiffs’ property, creating a clearing or roadway for access to the site leaving a rutted dirt road and a certain amount of debris upon plaintiffs’ property. There was also damage to a fence in this area. The parties disagree on some of the terms of the agreement and the extent of the damages.

[787]*787We shall consider first the agreement between the parties.

The evidence presented clearly shows that the land owners gave permission for the erection of the poles one foot outside of the property line, and that they understood that there would be an overhang by the crossarms on the utility poles over their property. Plaintiffs admitted that permission was granted to trim the trees within the boundary fence which interfered with the new power line.

The trial court found this to be the extent of the agreement, but defendant contends the agreement extended to complete use of the land for construction purposes. However, the testimony of the plaintiff Harrison, who handled the negotiations, asserts that there was no agreement that the defendant could enter upon the property for the purpose of construction and Lynch, defendant’s right-of-way agent, testifies only that there was an agreement for the placement of the poles and the trimming of the trees.

We agree with the trial judge’s findings and proceed to the issue of damages.

Despite the limited agreement the evidence shows that during the month of March, 1967, the defendant caused its contractor to enter upon the premises, and in order to construct its power line, the contractor cleared an area along the front of the property and used it as an access road and base for the construction. This area was left with very deep ruts located therein and it was necessary for plaintiff to refill and regrade this area to make it level. Additionally, the evidence shows that there were several piles of brush and logs left upon the property which were required to be cleaned up. There was also some damage to an existing fence, although the actual amount of damages and the value thereof cannot be placed with any degree of certainty.1

These damages were caused by the construction work beyond the scope of the agreement and by unauthorized entry upon the land. Plaintiffs seek the amount necessary to repair the damages and for trespass. The trial judge awarded the amount of $2,000.00 for these trespass damages and an examination of the record causes us to conclude that his assessment of the damages was substantially correct and cannot be fixed precisely. We do not propose to change them herein. LSA-Civil Code Art. 1934(3).

The main problem in this case, as we view it, is the location and removal of the utility poles. As remarked above, the agreement was to install the poles one foot from the property line of plaintiffs and within the highway right-of-way. Plaintiffs have produced a surveyor who testified that he determined the location of the poles to be as follows:

Pole #1—entire diameter of 13 inches located within property of plaintiff;

Pole #2—edge of pole to the extent of 1 % inches located inside property line ;

Pole #3—edge of pole to the extent of 4 inches located within the property line;

Pole #4—A distance of 5 inches outside of property line to near edge of pole.

As opposed to this, defendant has produced a surveyor whose measurements show the following locations:

Pole #1—the edge of the pole to the extent of 3T/ioo of a foot located inside of the property line;

Pole #2—a distance of 3§ioo of a foot outside of the property line to near edge of pole;

Pole #3—a distance of 32/ioo of a foot outside of the property line to near edge of pole;

[788]*788Pole #4 — a distance of 89ioo of a foot outside of the property line to near edge of pole.

The trial court concluded that the locations advanced by defendant’s surveyor are the correct locations of these poles. The difference between these two surveys is apparently caused by the starting point or base of measurement. The defendant’s surveyor testified that he used the corner pipe of this property as determined by previous surveys, and from that pipe found the center line of the highway as noted by highway engineers who were doing work in the vicinity. As opposed to this, the plaintiffs’ surveyor used concrete monuments, which are square posts of some 3 or 4 feet in height marking the line of the right-of-way in this area. Both concede that there could be some movement of the reference points that they used, but because of testimony that the concrete monuments were leaning, the trial judge concluded apparent-' ly that the defendant’s base of measurements was more precise and found the poles to be in the position as stated by him. We find no error in his conclusion.

Plaintiffs do not seek damages for mis-location of the poles, and thus the issue is whether we should order the removal of the poles as located on defendant’s survey, bearing in mind that there is only an encroachment of one pole upon plaintiffs’ property to the extent of 3%oo of a foot.

The trial judge found that the defendant obtained a utility servitude upon the property because plaintiffs allowed the use and occupancy of their property for a public purpose to continue for nearly a year before instituting legal action. He held that plaintiff was not entitled to cause removal of the power line because of this acquiescence and the following language of the court stated in Gumbel v. New Orleans Terminal Co., 186 La. 882, 173 So. 518 (1937), following the doctrine in the case of St. Julien v. Morgan L. & T. R. Co., 35 La.Ann. 924 (1883):

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lake, Inc. v. Louisiana Power & Light Co.
318 So. 2d 911 (Louisiana Court of Appeal, 1975)
Harrison v. Louisiana Power and Light Co.
288 So. 2d 37 (Supreme Court of Louisiana, 1973)
Harrison v. Louisiana Power & Light Co.
278 So. 2d 503 (Supreme Court of Louisiana, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
274 So. 2d 785, 1973 La. App. LEXIS 6075, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harrison-v-louisiana-power-light-co-lactapp-1973.