Harrison v. Family Home Builders, LLC

84 So. 3d 879, 2011 WL 5252566, 2011 Ala. Civ. App. LEXIS 301
CourtCourt of Civil Appeals of Alabama
DecidedNovember 4, 2011
Docket2100524
StatusPublished
Cited by7 cases

This text of 84 So. 3d 879 (Harrison v. Family Home Builders, LLC) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harrison v. Family Home Builders, LLC, 84 So. 3d 879, 2011 WL 5252566, 2011 Ala. Civ. App. LEXIS 301 (Ala. Ct. App. 2011).

Opinions

BRYAN, Judge.

Gary Harrison and Patsy Harrison appeal from a summary judgment in favor of Family Home Builders, LLC (“FHB”). We affirm in part, reverse in part, and remand.

Factual Background and Procedural History

On January 5, 2007, the Harrisons and FHB entered into a written contract (“the contract”) in which FHB agreed to perform remodeling and construction work (“the work”) on the Harrisons’ existing house in Lauderdale County. FHB began the work; however, on May 4, 2007, the Harrisons terminated the contract before FHB had completed the work.

On July 16, 2007, the Harrisons sued FHB, stating claims of breach of contract, negligence, and fraud. As the basis of their breach-of-contract claim, the Harri-sons alleged (1) that FHB had agreed to perform the work in accordance with plans and specifications provided by the Harri-sons and had failed to do so; (2) that FHB had failed to complete the work; (3) that FHB had agreed to perform the work in accordance with applicable building codes and had failed to do so; (4) that the work performed by FHB had defects in materials and workmanship; (5) that FHB had failed to coordinate and supervise the work in an efficient manner; and (6) that FHB had overbilled the Harrisons for costs not related to the work.

As the basis of their negligence claim, the Harrisons alleged that FHB had breached the duty of care it owed the Harrisons by failing to perform the work in a workmanlike manner, by failing to perform the work in accordance with the plans and specifications provided by the Harrisons, by failing to complete the work in a timely manner, by failing to perform the work in accordance with the applicable [882]*882building codes, and by failing to coordinate and supervise the work in a proper manner.

As the basis of their fraud claim, the Harrisons alleged that, while it was performing the work, FHB had misrepresented to the Harrisons that certain costs were incurred in performing the work and that, in reliance on those misrepresentations, the Harrisons had paid FHB for materials and labor costs that had not been incurred in the performance of the work.

Answering, FHB denied the material allegations of the Harrisons’ complaint. The Harrisons later amended their complaint to add a claim that FHB had negligently hired, trained, supervised, and retained (“the negligent-supervision claim”) Kyle Gean, the individual who had supervised the work for FHB. Answering, FHB denied the material allegations of the Harri-sons’ amended complaint.

On March 29, 2010, FHB moved for a partial summary judgment with respect to the Harrisons’ fraud claim. The Harrisons filed no evidence in opposition to that motion, and the trial court entered an order granting it on May 20, 2010.

On August 17, 2010, FHB moved for a summary judgment with respect to the breach-of-contract claim, the negligence claim, and the negligent-supervision claim. FHB asserted that it was not liable for breach of contract or negligence based on the allegation that it had failed to perform the work in accordance with the plans and specifications because, FHB said, the Har-risons had substantially changed the plans and specifications after the contract was executed. FHB asserted that it was not liable for breach of contract or negligence based on the allegation that it had failed to complete the work because, FHB said, it was entitled to a reasonable amount of time to complete the work because the contract neither specified a date for completion of the work nor stated that time was of the essence and the Harrisons had unilaterally terminated the contract before FHB had had a reasonable amount of time to complete the work. FHB asserted that it was not liable for breach of contract or negligence based on the allegation that it had failed to perform the work in accordance with the applicable building codes because, FHB said, the Harrisons had not produced substantial evidence indicating that FHB had failed to perform its work in accordance with the applicable building codes and, even if FHB had failed to perform its work in accordance with the applicable building codes, the evidence indicated that the Harrisons had not given FHB a reasonable amount of time to correct such failures before unilaterally terminating the contract. FHB asserted that it was not liable for breach of contract or negligence based on the allegation that there were defects in material and workmanship because, FHB said, the Harrisons had failed to produce substantial evidence indicating that there were defects in materials and workmanship. FHB asserted that it was not liable for breach of contract or negligence based on the allegation that it had failed to coordinate and supervise the work in an efficient manner because, FHB said, the Harrisons had failed to produce substantial evidence indicating that FHB had failed to coordinate and supervise the work in an efficient manner. FHB asserted that it was not liable for breach of contract based on the allegation that it had overbilled the Harrisons because, FHB said, the Harrisons had admitted that they had no evidence indicating that FHB had overbilled them. Finally, FHB asserted that it was not liable for negligent supervision because, it said, the Harrisons had not produced substantial [883]*883evidence indicating that Gean was incompetent.

FHB supported its summary-judgment motion with, among other things, the deposition testimony of Gean and the contract. Gean testified as follows. He was not an employee of FHB; he acted as a subcontractor of FHB in preparing an estimate of the cost of the work before the contract was signed and in supervising the work after the contract was signed. Before the execution of the contract, he discussed the work with the Harrisons and submitted an estimate to them. His estimate was based on drawings provided by the Harrisons and quotes he had received from vendors and subcontractors. The drawings on which he based his estimate showed the addition of an outdoor kitchen, the removal of the windows from the back of the house, the removal of the windows from the garage, the removal of the doors from the garage, the addition of a concrete pad, and the remodeling of a bedroom and bathroom located in the western end of the house. Based on those drawings, Gean estimated that the work would cost $109,000 and would take approximately four months to complete. After the contract was signed, the Harrisons and their decorator, Madelyn Hereford, made substantial changes to the work. For example, in March and April 2007, the size of the outdoor kitchen was changed, the size of a pavilion was changed, a porch was added to the western side of the house, a porch was added to “the bay addition” to the house, sidewalks were added, the bay addition to the house was enlarged and changes were made to the recessed tub, the mantel, the fireplace, the tray ceiling, the coffee bar, the windows, and the french doors in that addition. Those changes increased the amount of the work to be performed, increased the cost of the work, and delayed the performance of the work because those changes required that some of the work that had been completed in accordance with the original drawings be redone. Gean estimated that approximately one-half of the work had been completed when the Harrisons unilaterally terminated the contract on May 4, 2007.

The contract signed by the parties on January 5, 2007, expressly provided that all representations made before the signing of the contract were merged into the contract. The contract neither specified a date for completion of the work nor stated that time was of the essence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kaufman v. Oldenettel
Court of Appeals of Kansas, 2020
Pope, Mcglamry, Kilpatrick, Morrison & Norwood, P.C. v. Dubois
266 So. 3d 1064 (Court of Civil Appeals of Alabama, 2017)
ECR Properties, LLC v. Camden County Development, LLC
998 F. Supp. 2d 1295 (M.D. Alabama, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
84 So. 3d 879, 2011 WL 5252566, 2011 Ala. Civ. App. LEXIS 301, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harrison-v-family-home-builders-llc-alacivapp-2011.