Harrison Rural Electrification Ass'n v. Public Service Commission

438 S.E.2d 782, 190 W. Va. 439, 1993 W. Va. LEXIS 186
CourtWest Virginia Supreme Court
DecidedDecember 9, 1993
DocketNo. 21812
StatusPublished
Cited by2 cases

This text of 438 S.E.2d 782 (Harrison Rural Electrification Ass'n v. Public Service Commission) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harrison Rural Electrification Ass'n v. Public Service Commission, 438 S.E.2d 782, 190 W. Va. 439, 1993 W. Va. LEXIS 186 (W. Va. 1993).

Opinion

PER CURIAM:

Harrison Rural Electrification Association, Inc. (HREA) appeals an order (2-1 Commissioner Frum dissenting) of the West Virginia Public Service Commission (PSC) resolving two customer service disputes between HREA and Monongahela Power Company (MPC) in favor of MPC. On appeal, HREA argues that the PSC should have found that the new customers were part of HREA’s exclusive service territory based on a 1938 agreement of the parties and should not have classified the disputed areas as overlapping, that is an area outside an exclusive franchised area with intermeshed service provided by two or more utility companies. Because the record indicates that the PSC’s decisions were supported by substantial evidence, we affirm the final order of the PSC.

I

The dispute concerns electrical service for customers in two areas in Harrison County, West Virginia, namely, the “Big Elm School,” a new school located at the intersection of Tetrick Road and U.S. Rt. 19, and the “Auburn Woods Subdivision,” a new subdivision located between Route 77/3 and Beard’s Run Road (Route 17). Both HREA, a non-profit, privately-owned electric cooperative that buys electricity and distributes it to its members, and MPC, a public electric utility that also sells and distributes electricity to HREA, seek to provide electrical service in both areas.1 The disputes were first heard by an administrative law judge (ALJ) who recommended that the disputes be resolved in favor of HREA based on an order in the PSC case of Harrison Rural Electrification Association, Inc. v. Monongahela West Penn Public Service Co., No. 2570 (W.Va.P.S.C., Filed August 18, 1938) (hereinafter HREA 1938)2 and the case’s territorial map. The PSC refused to adopt the ALJ’s recommended decision, finding HREA 1938 and its map of limited value for resolving the disputes. Instead, the PSC found that because neither customer site was part of a utility’s exclusive franchised area and because both utilities had served customers on the properties, the territories were considered “grey and overlapping” under the PSC’s case of Lumberport-Shinnston Gas Co. v. Equitable Gas Co., No. 86-749-CN-C (W.Va.P.S.C., Filed Sept. 29, 1987). Because the disputed territories were overlapping, the PSC resolved the disputes by following both customers’ expressed preferences for service from MPC.

HREA appealed to this Court arguing that the PSC should not have reversed the ALJ’s decision finding the disputed territories are part of HREA’s exclusive territory, as shown by HREA 1938’s map. Although both the PSC and MPC acknowledge the existence of HREA 1938’s map, both the PSC and MPC argue that HREA 1938’s map is of limited [441]*441value because it; (1) lacks a scale; (2) marks only certain towns and municipalities and not highways, rivers or other geographical features; (3) has not been updated as additional electrical facilities were constructed; and (4) has not been used as a base for PSC decisions for at least 15 years.3 Both the PSC and MPC maintain that the PSC properly found the customers to be outside exclusive franchised areas and in areas with inter-meshed service, which, following PSC case law, allows the customers’ service preferences to determine the utility company.

A. Big Elm School

The Harrison County Board of Education requested MPC to provide electrical service for its new school located between Tetrick Road, which is primarily served by HREA, and U.S. Rt. 19, which is primarily served by MPC. The ALJ noted that HREA was providing service to an oil well, which although located on the site was not owned by the Board of Education, and that HREA’s lines along Tetrick Road were about 160 feet from the school. HREA also had three-phase service available and its lines crossed MPC’s lines. The ALJ found that although MPC had no distribution lines on site, MPC may, at an earlier date, have served customers on site. To meet the school’s needs, MPC had to upgrade its service line, which is about 300 feet from the school. Based on HREA 1938’s map, the ALJ concluded that the “Big Elm School” was part of HREA’s exclusive territory and recommended that HREA provide service.

The PSC found that although HREA had been providing service to an oil well owned by Interstate Oil and Gas on the site for two years, MPC had had two poles on the site for more than 40 years and had served customers on the site since before 1953. MPC alleges that their lines were removed to allow for construction and that the lines’ removal did not show that MPC had abandoned, exchanged or otherwise disposed of the property. Finding intermeshing services on the “Big Elm School” site, the PSC considered the site to be “gray and overlapping,” that is not clearly part of either utilities’ exclusive service area with intermeshed service. Finding HREA 1938’s map of little value for determining if the school site was within an exclusive franchised area, the PSC used the customer’s preference for MPC to determine which utility would service the area.

B. Auburn Woods Subdivision

Auburn Woods Subdivision is a new subdivision located on a hill between Route 77/3, which is primarily served by MPC, and Beard’s Run Road, which is primarily served by HREA. The subdivision, whose access is from Beard’s Run Road, is located on a 57-acre tract, which has about 41 lots delineated and the possibility of about 100 houses. The subdivision’s developer requested service from MPC.

The ALJ found that HREA had provided service from Beard’s Run Road to two sites on the tract, one of which was a mobile house that had been located near the subdivision’s entrance. The ALJ noted that HREA’s distribution line was within 200 feet of the first house constructed in the subdivision, and that MPC’s line was 3200 feet from the first house with access made by crossing Rt. 77/3, another’s land and then ascending an 800-foot steep hill. The ALJ considered that MPC provides free a one span (500-foot) extension and that the prospective customer pays for any additional extensions. Finally the ALJ noted that in the opinion of the PSC staff, the subdivision’s first two houses were within HREA’s exclusive territory. Based On HREA 1938’s map, the ALJ concluded that the entire subdivision was within HREA’s exclusive territory.

However, instead of using the subdivision’s first two houses to determine the subdivision’s utility, the PSC considered the entire subdivision.4 Specifically, the PSC noted that 100 houses are planned and that both utilities served properties adjacent to the subdivision. The PSC also noted that al[442]*442though prior to 1988 HREA served a mobile house whose location was at the edge of the subdivision’s tract, the subdivision’s plan calls for the mobile house’s site to be a common green area without a house.5 The PSC also noted that although HREA’s lines were 290 feet from the house closest to HREA’s lines, on the far side of the subdivision, MPC’s lines were 820 feet from the planned house closest to MPC’s lines. Approximately 2,400 feet separate the house closest to HREA’s lines and the planned house closest to MPC’s lines. The PSC also noted that most of the subdivision’s lots (the 41 lots already subdivided and surveyed) are shaped to lie closer to MPC’s facilities.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
438 S.E.2d 782, 190 W. Va. 439, 1993 W. Va. LEXIS 186, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harrison-rural-electrification-assn-v-public-service-commission-wva-1993.