Harris v. Trippi

72 S.E.2d 704, 209 Ga. 369, 1952 Ga. LEXIS 491
CourtSupreme Court of Georgia
DecidedOctober 14, 1952
Docket17974
StatusPublished
Cited by7 cases

This text of 72 S.E.2d 704 (Harris v. Trippi) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harris v. Trippi, 72 S.E.2d 704, 209 Ga. 369, 1952 Ga. LEXIS 491 (Ga. 1952).

Opinion

Head, Justice.

The instrument attached to the plaintiff’s petition is nothing more than a proposal by the defendant to lease from the plaintiff a filling station, if and when a station might be constructed by the plaintiff. The trial judge quite properly found that the instrument was without consideration, and being without consideration, although continuing in character as to time, the plaintiff had the right to reject the proposal by the defendant and to decline to proceed with the construction of a filling station. Prior v. Hilton & Dodge Lumber Co., 141 Ga. 117 (80 S. E. 559); Phinizy v. Bush, 129 Ga. 749; Hackett *372 v. Ladson, 152 Ga. 483 (110 S. E. 232); Tobey v. Seaboard &c. Construction Co., 169 Ga. 104, 105 (2) (149 S. E. 914); Rivers v. Key, 190 Ga. 852 (11 S. E. 2d, 14); State Highway Dept. v. MacDougald Construction Co., 54 Ga. App. 310 (187 S. E. 734).

The defendant’s amendment, in which he relies upon a purported oral agreement, can not be sustained. The amendment alleges that the proposed lease would be in accordance with “Texas Company’s Form G 77 A,” and a copy of this form is attached to the amendment.

A contract upon which specific performance is sought must be certain, definite, and clear, and so precise in its terms that neither party can reasonably misunderstand it. Studer v. Seyer, 69 Ga. 125; Hill v. Hill, 149 Ga. 50, 52 (99 S. E. 31); Adcock v. Shaw, 167 Ga. 710 (146 S. E. 478); Blumenfeld v. Citizens Bank & Trust Co., 168 Ga. 322 (147 S. E. 579).

Even the most casual consideration of the form of the lease, which the defendant alleges was to be executed at some future time, shows a wholly incomplete agreement, and one wherein specific performance could not be decreed. Much of the purported lease agreement is in blank, and the items would have to be agreed upon by the parties at some future time, or be supplied by the court. In paragraph 9 (b) there are nine items that would have to be agreed upon by the parties, and in sub-paragraph (c) of the same paragraph there are sixteen items that would have to be agreed upon. For the court to decree specific performance of the purported lease agreement would be for the court to make a contract between the parties. This a court of equity will not do.

The trial court properly sustained the demurrers to the answer as amended.

Judgment affirmed.

All the Justices concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lee v. Green Land Co., Inc.
538 S.E.2d 189 (Court of Appeals of Georgia, 2000)
Stone Mountain Game Ranch, Inc. v. Hunt, III
746 F.2d 761 (Eleventh Circuit, 1984)
Stone Mountain Game Ranch, Inc. v. Hunt
746 F.2d 761 (Eleventh Circuit, 1984)
Charles v. Simmons
113 S.E.2d 604 (Supreme Court of Georgia, 1960)
Smith v. Georgia Industrial Realty Co.
111 S.E.2d 37 (Supreme Court of Georgia, 1959)
Hardin v. Rosenthal
98 S.E.2d 901 (Supreme Court of Georgia, 1957)
Williams v. Manchester Building Supply Co.
97 S.E.2d 129 (Supreme Court of Georgia, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
72 S.E.2d 704, 209 Ga. 369, 1952 Ga. LEXIS 491, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harris-v-trippi-ga-1952.