STATE OF MAINE SUPERIOR COURT YORK, SS. CIVIL ACTION DOCKET NO. AP-14-24
YVONNE HARRIS
Appellant,
v. ORDER
TOWN OF YORK, MAINE, and AMBER HARRISON
Respondents.
I. Background
A. Procedural Posture
Petitioner Yvonne Harris brings this Rule 80B appeal from a decision of the
Town of York Zoning Board of Appeals. The Board affirmed the Code Enforcement
Officer's denial of a building permit.
B. Facts
In 2008, Petitioner Yvonne Harris ("Petitioner" or "Harris") purchased 157 Long
Beach Avenue, York, Maine ("the parcel" or "the property"). The property is situated in
the RES-7 Base Zone within York's Shoreland Overlay District. The lot size totals
21,344 sq. ft. and has three buildings: (1) a 1,574 sq. ft. year-round Victorian structure
("the Victorian"), (2) a 764 sq. ft seasonal structure ("the seasonal building"), and (3) a
504 sq. ft. garage structure ("the garage"). Harris intended to renovate the buildings and
convert them into three condominium units at the time she purchased the property.
1 Harris or persons working for her communicated with Code Enforcement Officers
("CEOs") in 2008 and 2009 about her intended plans. Harris relied on this information to
hire contractors to renovate and engineers. In particular, the CEOs represented that Harris
could convert the upstairs of the garage into a single-family dwelling unit. (R. 1-3 .) A
2008 email states "You had indicated it would be acceptable to renovate the Garage/barn
as a single family unit and keep the front house as a single family unit. Is this correct?"
CEO Timothy DeCoteau replied: "Setting aside other issues such as setback, lot
coverage, flood zone, building codes, etc. it's possible to relocate one of the dwelling
units in the front building to over the garage." (R. 2.) A second email from 2009 states "if
on the garage you cant [sic] tear it down or add up on existing [sic] structure can you
make the garage space and the 2nd floor both residential space" and next to this appears
"yes 10/5/09" handwritten with CEO DeCouteau's signature. (R. 1.) Harris proceeded to
obtain plumbing and electrical permits and removed one of the dwelling units in the
Victorian. She continued to communicate with Town officials, including CEO Benjamin
McDougal, who in a 2012 email explained the process for applying for the various
permits needed to move forward with the project. (R. 10.)
On May 15, 2014, Amber Harrison, the then-acting York CEO, issued Letter of
Denial that denied Harris's building permit application because the expansion did not
comply with density and shoreland zone setback requirements. (R. 12.) The RES-7 zone
reqmres 12,000 sq. ft. per single-family dwelling unit. Because the CEO concluded
Harris's proposed renovation would result in three single-family dwelling units, the
21,344 sq. ft. lot size fell short of the necessary 36,000 sq. ft. to accommodate three units.
Harris timely appealed to the Zoning Board of Appeals ("the ZBA'').
2 Harris testified before the ZBA that she had expended about $400,000 total on
plans and renovations, including $75,000 on the Victorian. Harris communicated with
prior CEOs and submitted building applications for the garage, but never obtained the
permits. The ZBA affirmed the building permit denial by a 5-0 vote.
II. Discussion
A. Rule SOB Standard
This court reviews government agency decisions pursuant to Rule 80B for errors
of law, abuse of discretion, or findings not supported by substantial evidence. Aydelott v.
City of Portland, 2010 1\ffi 25, ~ 10, 990 A.2d 1024. The party challenging the decision
below has the burden of proof to overturn the decision. Id.
The court reviews the interpretation of municipal ordinances de novo. Nugent v.
Town of Camden, 1998 1\ffi 92, ~ 7, 710 A.2d 245. "The terms or expressions in an
ordinance are to be construed reasonably with regard to both the objectives sought to be
obtained and the general structure of the Ordinance as a whole." Jordan v. City of
Ellsworth, 20031\ffi 82, ~ 9, 828 A.2d 768.
B. The Operative Decision Under Review
When an appeal comes before the Superior Court after multiple decisions at the
municipal level, the court reviews the operative decision directly. Dunlop v. Town of
Westport Island, 20121\ffi 22, ~ 13, 37 A.3d 300. The court must determine which is the
"operative" decision.
If the Board of Appeals [properly] acted as a tribunal of original jurisdiction, that is, as factfinder and decision maker, we review its decision directly. If, however, the Board acted only in an appellate capacity, we review directly the decision of the [CEO], or other previous tribunal, not the Board of Appeals.
3 Mills v. Town of Eliot, 2008 ME 134, ~ 13, 955 A.2d 258. The general rule is that the
ZBA acts in a de novo capacity and thus renders the operative decision unless the
municipal ordinance expressly provides otherwise. Id. ~ 14. In York, appeals from a
CEO's permit denial proceed to the Board of Appeals. York, Me., Ordinance§ 18-A.4.G.
("Ordinance"). The ordinance expressly permits the ZBA to collect evidence, hear
testimony, and act as a fact-finder. Ordinance§ 18.8.3. While members of the ZBA made
comments at the hearing that suggested they were merely reviewing the CEO's decision
in an appellate capacity, the ZBA heard testimony from Harris, the CEO, and considered
exhibits. The ZBA' s decision is therefore the operative decision under review. Mills,
2008 ME 134, ~ 15, 955 A.2d 258.
C. The Three Structures and Existing Dwelling Units
Harris and the Town disagree as to how to characterize the dwellings on the
property. In Harris' view, there is (and has been) a third dwelling unit on the property.
The Town contends that there are two dwellings and Harris's proposed project would add
a third dwelling unit to the garage, where one never existed. Both parties are partially
correct.
When Harris purchased the property, the Victorian was classified as a two-family
dwelling unit, while the seasonal structure was a single dwelling unit. The renovation
project intended to "remove" a dwelling unit from the Victorian to the space above the
garage. It was for this reason Harris communicated with town officials about plans to use
the garage for a dwelling unit. In a 2008 email, CEO Timothy DeCoteau told Harris that
the Victorian could be renovated to contain one dwelling unit and the unit removed could
be placed above the garage, subject to applicable zoning regulations. (R. 2, 215.)
4 The ZBA first concluded the building permit was properly denied because
Harris's lot is too small for three single-unit dwelling units under applicable density
standards. Harris argues the ZBA erred in treating the proposal to re-locate the dwelling
unit from the Victorian to the garage as an additional dwelling. (Pet.'s Brief 6.) In doing
so, the Town included the unit in the total square footage calculation. The ordinance
requires 12,000 sq. ft. minimum lot size for each one-family dwelling unit. Ordinance §
5.4.2.1. If a dwelling in the garage is included, Harris needs a lot size of at least 36,000
sq. ft. to have a total of three dwellings.
Free access — add to your briefcase to read the full text and ask questions with AI
STATE OF MAINE SUPERIOR COURT YORK, SS. CIVIL ACTION DOCKET NO. AP-14-24
YVONNE HARRIS
Appellant,
v. ORDER
TOWN OF YORK, MAINE, and AMBER HARRISON
Respondents.
I. Background
A. Procedural Posture
Petitioner Yvonne Harris brings this Rule 80B appeal from a decision of the
Town of York Zoning Board of Appeals. The Board affirmed the Code Enforcement
Officer's denial of a building permit.
B. Facts
In 2008, Petitioner Yvonne Harris ("Petitioner" or "Harris") purchased 157 Long
Beach Avenue, York, Maine ("the parcel" or "the property"). The property is situated in
the RES-7 Base Zone within York's Shoreland Overlay District. The lot size totals
21,344 sq. ft. and has three buildings: (1) a 1,574 sq. ft. year-round Victorian structure
("the Victorian"), (2) a 764 sq. ft seasonal structure ("the seasonal building"), and (3) a
504 sq. ft. garage structure ("the garage"). Harris intended to renovate the buildings and
convert them into three condominium units at the time she purchased the property.
1 Harris or persons working for her communicated with Code Enforcement Officers
("CEOs") in 2008 and 2009 about her intended plans. Harris relied on this information to
hire contractors to renovate and engineers. In particular, the CEOs represented that Harris
could convert the upstairs of the garage into a single-family dwelling unit. (R. 1-3 .) A
2008 email states "You had indicated it would be acceptable to renovate the Garage/barn
as a single family unit and keep the front house as a single family unit. Is this correct?"
CEO Timothy DeCoteau replied: "Setting aside other issues such as setback, lot
coverage, flood zone, building codes, etc. it's possible to relocate one of the dwelling
units in the front building to over the garage." (R. 2.) A second email from 2009 states "if
on the garage you cant [sic] tear it down or add up on existing [sic] structure can you
make the garage space and the 2nd floor both residential space" and next to this appears
"yes 10/5/09" handwritten with CEO DeCouteau's signature. (R. 1.) Harris proceeded to
obtain plumbing and electrical permits and removed one of the dwelling units in the
Victorian. She continued to communicate with Town officials, including CEO Benjamin
McDougal, who in a 2012 email explained the process for applying for the various
permits needed to move forward with the project. (R. 10.)
On May 15, 2014, Amber Harrison, the then-acting York CEO, issued Letter of
Denial that denied Harris's building permit application because the expansion did not
comply with density and shoreland zone setback requirements. (R. 12.) The RES-7 zone
reqmres 12,000 sq. ft. per single-family dwelling unit. Because the CEO concluded
Harris's proposed renovation would result in three single-family dwelling units, the
21,344 sq. ft. lot size fell short of the necessary 36,000 sq. ft. to accommodate three units.
Harris timely appealed to the Zoning Board of Appeals ("the ZBA'').
2 Harris testified before the ZBA that she had expended about $400,000 total on
plans and renovations, including $75,000 on the Victorian. Harris communicated with
prior CEOs and submitted building applications for the garage, but never obtained the
permits. The ZBA affirmed the building permit denial by a 5-0 vote.
II. Discussion
A. Rule SOB Standard
This court reviews government agency decisions pursuant to Rule 80B for errors
of law, abuse of discretion, or findings not supported by substantial evidence. Aydelott v.
City of Portland, 2010 1\ffi 25, ~ 10, 990 A.2d 1024. The party challenging the decision
below has the burden of proof to overturn the decision. Id.
The court reviews the interpretation of municipal ordinances de novo. Nugent v.
Town of Camden, 1998 1\ffi 92, ~ 7, 710 A.2d 245. "The terms or expressions in an
ordinance are to be construed reasonably with regard to both the objectives sought to be
obtained and the general structure of the Ordinance as a whole." Jordan v. City of
Ellsworth, 20031\ffi 82, ~ 9, 828 A.2d 768.
B. The Operative Decision Under Review
When an appeal comes before the Superior Court after multiple decisions at the
municipal level, the court reviews the operative decision directly. Dunlop v. Town of
Westport Island, 20121\ffi 22, ~ 13, 37 A.3d 300. The court must determine which is the
"operative" decision.
If the Board of Appeals [properly] acted as a tribunal of original jurisdiction, that is, as factfinder and decision maker, we review its decision directly. If, however, the Board acted only in an appellate capacity, we review directly the decision of the [CEO], or other previous tribunal, not the Board of Appeals.
3 Mills v. Town of Eliot, 2008 ME 134, ~ 13, 955 A.2d 258. The general rule is that the
ZBA acts in a de novo capacity and thus renders the operative decision unless the
municipal ordinance expressly provides otherwise. Id. ~ 14. In York, appeals from a
CEO's permit denial proceed to the Board of Appeals. York, Me., Ordinance§ 18-A.4.G.
("Ordinance"). The ordinance expressly permits the ZBA to collect evidence, hear
testimony, and act as a fact-finder. Ordinance§ 18.8.3. While members of the ZBA made
comments at the hearing that suggested they were merely reviewing the CEO's decision
in an appellate capacity, the ZBA heard testimony from Harris, the CEO, and considered
exhibits. The ZBA' s decision is therefore the operative decision under review. Mills,
2008 ME 134, ~ 15, 955 A.2d 258.
C. The Three Structures and Existing Dwelling Units
Harris and the Town disagree as to how to characterize the dwellings on the
property. In Harris' view, there is (and has been) a third dwelling unit on the property.
The Town contends that there are two dwellings and Harris's proposed project would add
a third dwelling unit to the garage, where one never existed. Both parties are partially
correct.
When Harris purchased the property, the Victorian was classified as a two-family
dwelling unit, while the seasonal structure was a single dwelling unit. The renovation
project intended to "remove" a dwelling unit from the Victorian to the space above the
garage. It was for this reason Harris communicated with town officials about plans to use
the garage for a dwelling unit. In a 2008 email, CEO Timothy DeCoteau told Harris that
the Victorian could be renovated to contain one dwelling unit and the unit removed could
be placed above the garage, subject to applicable zoning regulations. (R. 2, 215.)
4 The ZBA first concluded the building permit was properly denied because
Harris's lot is too small for three single-unit dwelling units under applicable density
standards. Harris argues the ZBA erred in treating the proposal to re-locate the dwelling
unit from the Victorian to the garage as an additional dwelling. (Pet.'s Brief 6.) In doing
so, the Town included the unit in the total square footage calculation. The ordinance
requires 12,000 sq. ft. minimum lot size for each one-family dwelling unit. Ordinance §
5.4.2.1. If a dwelling in the garage is included, Harris needs a lot size of at least 36,000
sq. ft. to have a total of three dwellings. The property, however, is only 21,344 sq. ft.
Harris mounts several arguments as to why the density requirements should not
apply to the property. Harris argues CEO Amber Harrison made a mistake of fact when
she determined that there were only two dwelling units. Harris also contends that two
prior CEOs concluded there are three and the Town cannot reverse this finding. (Pet.' s
Brief 6-7.) 1 As there were three existing dwelling units, the proposed use is either lawful
or legally nonconforming and the density restrictions do not apply. (Pet.'s Brief 8-10.) 2
The Town argues Harris has failed to establish there was a legal or existing
nonconforming use, and even if she could, the proposal to "move" the third unit to the
garage would change the use and thus lose protection. (Resp.'s Brief 4-5.)
Assuming that three legal units existed on the property, this does not necessarily
mean that Harris may proceed with plans for the garage. The "three" included the two
units that existed in the Victorian prior to renovations. Whether Harris may lawfully have
1 Harris's procedural argument that the ZBA cannot reverse the previous CEOs' decisions because the appeal window has run was not raised below and is therefore waived. Tarason v. Town ofS. Berwick, 2005 ME 30, ~ 8, 868 A.2d 230. 2 Harris's arguments on this issue are somewhat confusing. Harris appears to argue that neither the use nor the lot is nonconforming, but elsewhere concedes that the proposed project is in fact a "nonconforming situation." (Pet.'s Brief8-10.)
5 three units and whether one of those units may be put m the garage are separate
questions.
Harris does not have a legal right to construct a dwelling in the garage. The
preexisting nonconformity, if any, would allow Harris to have two units in the Victorian
and one unit in the seasonal structure, not three single-unit dwellings in separate
structures. There is a substantive difference between a two-family dwelling structure and
two separate single-family dwelling structures. Both consist of "two" dwellings, but they
are plainly regulated differently under the density ordinance. See Ordinance § 5.4.2.1.
(detailing distinct minimum square footage requirements for two-family dwellings and
single-family dwellings). Furthermore, the ordinances prohibit moving nonconforming
uses from one part of a structure to another part of the same structure, Ordinance §
17.1.3.3., and nowhere permit an owner to take a nonconforming use or structure and
effectively transfer or reassign that nonconformity to another conforming use or structure
on the lot. Ordinance § 17.2.
Constructing a residential unit in the garage would clearly introduce a new use in
a separate structure and constitute an "extension" or "expansion" of the nonconformity.
Shackjord & Gooch, Inc. v. Town ofKennebunk, 486 A.2d 102, 105 (Me. 1984); see also
8A McQuillin, Municipal Corporations § 25:220 (3d ed.) (stating that increasing the
number of buildings in connection with a nonconforming use constitutes a prohibited
enlargement of the use); compare Keith v. Saco River Corridor Comm 'n, 464 A.2d 150,
156 (Me. 1983) (holding mere sale of preexisting nonconforming dwelling units would
not change quality, character, degree, or intensity of established use). Adopting Harris's
argument would allow property owners to freely move units between structures on their
6 property without obtaining zoning relief. Such a policy would offend the purpose of
zoning, which aims to "eliminate nonconforming uses as speedily as justice will permit."
Id.; see also Gagne v. Inhabitants of City of Lewiston, 281 A.2d 579, 581 (Me. 1971)
("The spirit of the zoning ordinances and regulations is to restrict rather than to increase
any nonconforming uses.")
The ZBA therefore properly considered the garage proposal as a separate and
distinct dwelling unit that was not protected as a lawful conforming dwelling. See
Wickenden v. Luboshutz, 401 A.2d 995, 996 (Me. 1979) (deferring to Board of Appeals'
determination that a studio structure was a preexisting nonconforming "dwelling"). The
ZBA did not err in determining the proposal to install a dwelling unit in the garage was
not a lawful, protected use and would contravene the density requirements.
D. Whether the ZBA Properly Applied the Shoreland Ordinance
The second ground for denying the permit was a failure to comply with the
Shoreland Ordinance setback, which the ZBA interpreted to prohibit expansion of
accessory structures. Harris argues the ZBA erred. (Pet.' s Brief 11-14.) The relevant
ordinance provision, "Expansions of Structures that Do Not Comply with Setback
Requirements," refers only to "principal" structures. Ordinance § 8.3 .11.4 ("[T]he portion
of a principal structure that does not satisfy the required shoreland setback may be
expanded only in accordance with the following provisions .... ")(emphasis added). The
ZBA concluded that because Section 8.3 .11.4. only refers to principal structures,
accessory structures may not expand. The ZBA found the garage is situated within 100
feet of a wetland, does not meet the setback requirement, and as an accessory structure
cannot expand under Section 8.3 .11.4.
1 Harris interprets the "plain language" of Section 8.3.11.4. to mean that accessory
structures may be expanded subject to a limitation that any alteration cannot increase the
structure's footprint more than 30%. 3 Harris relies in part on state law and points to 38
M.R.S. § 439-A(4), which states "all new principal and accessory structures" must meet
setback requirements, but also allows accessory structures to expand, subject to the 30%
limitation. As the renovation to the garage complies with the 30% limitation, Harris
contends the ZBA erred in denying the building permit for failure to comply with the
setback.
Section 8.3.11.4 appears to address only principal structures. Expansion of
accessory structures is not expressly prohibited by the ordinances, but unlike principal
structures, there are no standards for accessory structure expansion. As Harris
emphasizes, under state law, a nonconforming accessory structure may expand subject to
the 30% limitation. 38 M.RS. § 4~9-A(4)(C). The statute, however, only allows
accessory structures to expand "as long as other applicable standards of land use adopted
by the municipality are met." Id As discussed above, the Town's density requirements
are not met. In any event, the plain terms of the ordinance do not explicitly embrace the
state law standard that accessory structures may expand. The ZBA therefore did not err in
sustaining the building permit denial.
E. Equitable Estoppel
Harris lastly argues that even if the proposal does not meet zoning requirements,
in light of the substantial expenditures made in reliance on representations by past CEOs,
the Town should be equitably estopped from enforcing the zoningrestrictions. 3 Harris specifically designed the garage to comply with this 30% standard.
8 A municipality can be equitably estopped from zoning enforcement where (1) the
statements or conduct of a municipal official induced the claimant to act, (2) the claimant
relied on the statements to her detriment, and (3) that reliance was reasonable. Tarason v.
Town of S. Berwick, 2005 :ME 30, ~ 15, 868 A.2d 230. Due to the policy implications, a
party seeking to estop a municipality from enforcing an otherwise valid ordinance "bears
a significant burden." Id.
The Town argues that Harris cannot rely on equitable estoppel as an affirmative
cause of action to obtain the building permit. (Resp. 's Brief 8.) In Buker v. Town of
Sweden, a landowner asserted equitable estoppel after the Town denied a conditional use
permit. 644 A.2d 1042, 1044 (Me. 1994). In affirming the Town's decision, the Law
Court noted that equitable estoppel "can be asserted against a municipality only as a
defense and cannot be used as a weapon of assault." Id. The Law Court reaffirmed this
principle in Tarason v. Town of South Berwick to conclude that a landowner could not
affirmatively estop the municipality, but could only raise estoppel as a defense to an
enforcement action. 2005 :ME 30, ~ 16, 868 A.2d 230.
Harris distinguishes Tarason and Buker on the grounds that she "already had a
lawful third dwelling unit" and "the legality of the third dwelling unit was not one that
implicated the issuance of a building permit." (Pet. 's Reply Brief 8.) Timothy DeCoteau,
the prior CEO, represented that Harris could proceed with plans to move a dwelling unit
from the Victorian into the garage. Harris contends that by relying on the CEO's
statement that the property had three lawful units, she is now entitled to construct a third
unit above the garage. This argument illustrates why equitable estoppel cannot be used
offensively in zoning matters. Whether Harris had three pre-existing dwellings and
9 whether: a dwelling may be located above the garage are separate questions. It would
significantly hamper zoning uniformity if applicants like Harris could force a
municipality to grant zoning relief to place a dwelling in any other existing structure on a
lot irrespective of other applicable requirements. The Town was not required to grant
Harris the permit she needed to construct the dwelling in the garage.
Harris complains that she has now lost the dwelling that was removed from the
Victorian. (Pet's Brief 16-17.) The removal required permits to relocate plumbing,
electrical, and other amenities in the structure. Harris testified that she has spent "about
$400,000" on the project overall. (R. 231.) The record does not break down where and
how Harris spent this sum. The expenditures specifically tied to the garage largely
involved preparatory studies and surveys, not physical construction.
Harris's equitable estoppel claim ultimately concerns the construction to remove
the dwelling from the Victorian rather than construction to add a dwelling in the garage. 4
Equitable estoppel protects property owners from zoning enforcement actions to remove
a structure or cease a use after that use or structure is in existence. See, e.g., City of
Auburn v. Desgrosseilliers, 578 A.2d 712 (Me. 1990). Equitable estoppel does not
guarantee future relief when the owner makes preparatory expenditures knowing they
still must satisfy substantive zoning requirements to obtain permits. Tarason v. Town of
S. Berwick, 2005 ME 30, ~ 17, 868 A.2d 230; Kittery Retail Ventures, LLC v. Town of
Kittery, 2004 ME 65, ~ 36, 856 A.2d 1183; H.E. Sargent, Inc. v. Town ofWells, 676 A.2d
920, 925 (Me. 1996). If in the future Harris reestablishes the second dwelling in the
Victorian and the Town brings a zoning enforcement action, Harris could conceivably
4 Harris fails to appreciate this distinction when she points to the loss of the dwelling in the Victorian and concludes equity requires allowing her to construct a dwelling in the garage.
10 assert equitable estoppel as a defense. But that is not the case before the court. The Town
is not equitably estopped from denying Harris a building permit to create a new dwelling
unit in the garage.
ill. Conclusion
For the reasons stated, the court concludes the ZBA did not err in denying Harris
a building permit to construct a single-unit dwelling in the garage structure. Harris may
not assert equitable estoppel to force the Town to grant a permit for the proposal.
The entry shall be:
Petitioner's Rule SOB appeal is hereby DENIED. The ZBA's decision is AFFIRMED.
SO ORDERED.
DATE: April .2~015
JohnM Justice, Superior Court
11 AP-14-24
ATTORNEY FOR PLAINTIFF: WILLIAM H DALE JENSEN BAIRD GARDNER & HENRY P OBOX4510 PORTLAND ME 04112
ATTORNEY FOR DEFENDANT: MARY E COSTIGAN BERNSTEIN SHUR P OBOX9729 PORTLAND ME 04104