Harris v. Phillips Pipe Line Company

517 S.W.2d 361, 50 Oil & Gas Rep. 370, 1974 Tex. App. LEXIS 2816
CourtCourt of Appeals of Texas
DecidedDecember 4, 1974
Docket12172
StatusPublished
Cited by19 cases

This text of 517 S.W.2d 361 (Harris v. Phillips Pipe Line Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harris v. Phillips Pipe Line Company, 517 S.W.2d 361, 50 Oil & Gas Rep. 370, 1974 Tex. App. LEXIS 2816 (Tex. Ct. App. 1974).

Opinion

O’QUINN, Justice.

Appellants brought this suit for damages and to enjoin appellee pipe line company from replacing and relocating a ten inch line across land owned by appellants in Travis County. 1

Trial was before the court without the aid of a jury and resulted in judgment that the pipe line company, in replacing its line at a different location from an existing line, acted within its grant of easement and acted in a reasonable and necessary manner to effect a safe and orderly replacement of the line.

Appellants bring the single point of error that the judgment “is contrary to Texas law concerning the proper construction of easements and the narrow and limited terms of the assignment from Shell [Pipe Line Corporation] to Appellee Phillips [Pipe Line Company] ; there was no evidence to support such findings.”

Shell Pipe Line acquired the original easement in 1928 from a predecessor in title to the Harris group, and in 1929 constructed the ten inch pipe line which Phillips later acquired, the replacement of which by Phillips became the subject of this suit. The easement granted Shell, under which it constructed the line, conveys to Shell, its successors and assigns “ . . . the right of way from time to time to lay, construct, reconstruct, replace, renew, maintain, repair, change the size of and remove pipes and pipe lines for the transportation of oil, petroleum or any of its products, gas, water and other substances, or any thereof . . .” (Emphasis added)

Phillips acquired the 1929 pipe line from Shell in 1953, together with easement rights. The assignment from Shell to Phillips grants “ . . . the rights and easements evidenced by instruments described on exhibit ‘A’ hereto attached [which includes the 1928 grant to Shell over the Harris lands], insofar and only insofar as they provide for the laying, maintaining, use, operation, repair, replacement and removal of a ten inch pipe line located thereon this day sold by Shell to Phillips, Shell hereby retaining all rights and easements evidenced by such instruments not herein assigned, including all second line rights . . . ” (Emphasis added)

The record shows that Shell maintains and operates a “second line” approximately seventy feet from and parallel to the ten inch line Phillips acquired from Shell in 1953.

Since obtaining the pipe line Phillips has used the line continuously to transport gas *363 liquids, derived from about twenty gasoline plants which are connected to more than 200 gas wells in the region of Odessa, in Ector County, to the Phillips refinery at Sweeney, in Brazoria County, a distance of more than 430 miles. The gas liquids are transported in the line under high pressure, and a break in the line would permit the liquids to vaporize and become highly combustible.

The record shows that the possibility of this hazard was one of the reasons Phillips decided that the 1929 line, buried to an average depth of only twenty inches, should be replaced by a line buried to a depth of forty-eight inches. The replacement program was limited to about forty-seven miles of line in Travis County, near and within the City of Austin. When laid in 1929 the pipe line in Travis County was largely in open prairie country. Growth of the City of Austin since that time has brought part of the line within the limits of the City, and the pipe line, buried only twenty inches beneath the surface of the soil, became subject to disruption by activity of an urban, rather than a rural, occupancy. The undisputed testimony at the trial was that by burying the replacement line to a depth of four feet it would be less hazardous than the earlier line buried to a depth of slightly more than one and a half feet.

On the Harris tract the new pipe line was constructed parallel to and fifteen feet north of the old (1929) line, but the pipe size remains the same, ten inches. An engineer for Phillips, whose testimony was not rebutted, testified that in order to bury the new line to a depth of four feet the operation required a ditch one foot wider than a ditch necessary to lay a line to a depth of twenty inches. It was also shown that from five to ten feet more working space was required to bury the line in a trench four feet deep than was needed to bury a line at the shallow depth of twenty inches. The new line was laid no closer than fifteen feet to the existing line because construction would have been hazardous at any less distance from the old line, which was still in operation during construction of the new line.

When asked why the new line was not laid “practically in the same ditch” as the old line, the engineer testified, “As a matter of safety, working over the old line, and also there is a — -we had to blast rock, and anything closer [than fifteen feet] would be too close.”

Phillips did not shut down, or discontinue operation of, the old line while the new line was being laid, which required a period of three months. To discontinue use of the operating line .during construction would have required Phillips to shut down its refinery at Sweeney, and the twenty gasoline plants, as well as the more than 200 gas wells supplying the plants, would have been required to stop production for the three months during which the new line was being laid. To avoid shutdowns, Phillips laid the new line a short distance from and parallel to the existing line, and, upon completion of the new line, Phillips “switched” from the old line to the new line, which was shown to be a common practice in the industry. Phillips operates only one line on the Harris land and has agreed to remove the 1929 line, which is no longer in operation, if requested by appellants.

The trial court filed conclusions of law and finding of fact, pursuant to the request of plaintiffs below, as set out:

“Conclusions of Law

1. The grant of the easement expressly includes the right of the grantee, Shell Pipe Line Corporation, to replace its pipe line, and it follows that the grantee may do that which is reasonably necessary to effect a replacement.

2. The partial assignment from Shell Pipe Line Corporation to Phillips Pipe Line Company assigned the rights of Shell Pipe Line Corporation to replace a ten inch (10") pipe line, and it follows that Phillips Pipe Line Company may do that *364 which is reasonably necessary to effect the replacement.”

Finding of Fact

1. What Defendant, Phillips Pipe Line Company, has done in replacing the pipe line at a different location from its existing pipe line was reasonable and necessary to effect a safe and orderly replacement of the line.”

The easement rights Shell acquired from the landowner in 1928 patently are very broad. The grant does not limit Shell to the number of lines the grantee may lay, and, as to any such line, Shell acquired the right to “construct, reconstruct, replace, renew, maintain, repair, change the size of and remove pipes and pipe lines.” Shell’s grant to Phillips expressly gives Phillips the right to replace and remove the ten inch line Shell sold to Phillips.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atmos Energy Corporation v. Charles L. Paul
Court of Appeals of Texas, 2020
Lindemann Properties, Ltd. v. Campbell
524 S.W.3d 873 (Court of Appeals of Texas, 2017)
Sinclair Transportation Co. v. Sandberg
2014 COA 76M (Colorado Court of Appeals, 2014)
Danny Ray McCrary v. State
Court of Appeals of Texas, 2011
Ferrara v. Moore
318 S.W.3d 487 (Court of Appeals of Texas, 2010)
Corley v. Entergy Corp.
246 F. Supp. 2d 565 (E.D. Texas, 2003)
Hall v. Lone Star Gas Co.
954 S.W.2d 174 (Court of Appeals of Texas, 1997)
Tom Hall v. Lone Star Gas Company
Court of Appeals of Texas, 1997
Mielke v. Yellowstone Pipeline Co.
870 P.2d 1005 (Court of Appeals of Washington, 1994)
Mobil Pipe Line Co. v. Smith
860 S.W.2d 157 (Court of Appeals of Texas, 1993)
Phillips Pipe Line Co. v. Clear Creek Properties, Inc.
553 S.W.2d 389 (Court of Appeals of Texas, 1977)
Berryhill v. Marshall Exploration, Inc.
420 F. Supp. 198 (W.D. Louisiana, 1976)
Smith v. Ethyl Corp.
417 F. Supp. 669 (S.D. Texas, 1976)
Board of Regents of the University of Texas v. S & G Construction Co.
529 S.W.2d 90 (Court of Appeals of Texas, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
517 S.W.2d 361, 50 Oil & Gas Rep. 370, 1974 Tex. App. LEXIS 2816, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harris-v-phillips-pipe-line-company-texapp-1974.