Harper, Drake & Associates, Inc. v. Jewett & Sherman Co.

182 N.W.2d 551, 49 Wis. 2d 330, 1971 Wisc. LEXIS 1121
CourtWisconsin Supreme Court
DecidedJanuary 5, 1971
Docket159
StatusPublished
Cited by6 cases

This text of 182 N.W.2d 551 (Harper, Drake & Associates, Inc. v. Jewett & Sherman Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harper, Drake & Associates, Inc. v. Jewett & Sherman Co., 182 N.W.2d 551, 49 Wis. 2d 330, 1971 Wisc. LEXIS 1121 (Wis. 1971).

Opinion

Hanley, J.

The following issues are presented on appeal:

(1) When a written, proposed contract is unexecuted and unenforceable may resort be had to one of its terms in determining the reasonable value of an architect’s services; if not,

(2) Then is the remaining evidence in the record as to reasonable value of services sufficient to support the verdict; and

*336 (3) Was there a rational and credible basis for the amount claimed by Harper for the services of Richard Kirsch?

Resort to one term of an unexecuted and unenforceable contract.

The jury verdict broke down as follows:

Architectural services $14,141.00
Plumbing consulting services 600.00
Heating, ventilating and air-conditioning consulting services 1,050.00
Electrical consulting services 787.50
Landscape architecture consulting services 2,870.00
$19,448.50

On appeal, only the first item on this list is in dispute. Respondent contended at trial that the reasonable value of the architectural services rendered by himself and his staff could be arrived at in either of two ways. The first would be to simply accept his percentage computations based on the terms of the contract. 2 The second would be to accept the evidence he offered of the time spent on the project by his office. Respondent explained at trial that when he billed on an hourly basis, he took each employee’s hourly rate, multiplied that by a profit and overhead factor of 2.5 and then multiplied the resulting figure by the number of hours worked by the employee. Under this approach Harper submitted the following figures as to the reasonable value of the services of himself and his staff: 3

*337 Architect or Draftsman Hourly rate times factor Honrs times gross hourly rate Value of services
Harper 15x2.5 = 37.50 156x37.50 = 5,850.00
Drake 15x2.5 = 37.50 65 x 37.50 = 2,437.50
Kirsch 5x2.5 = 12.50 160.5 x 12.50 = 2,006.25
Kinnich 10 x 2.5 = 25.00 8x25.00 = 200.00
Arndt 7.5x2.5 = 18.75 7.5 x 18.75 = 140.63
Groff 5x2.5 = 12.50 6.5x12.50 = 81.25
Knoll 5x2.5 = 12.50 8 x 12.50 = 100.00
Guerin 10 x 2.5 = 25.00 6x25.00 = 150.00
Total $ 10,965.63

The jury’s award for architectural services was $14,141. There is no way of knowing how the jury reached that figure. If they used the hours expended approach, then the verdict is clearly excessive in the amount $3,175.37 {i.e., he proved $10,965.63, but they gave him $14,141 or $3,175.37 more than he proved).

On oral argument, respondent’s attorney admitted that, as to this item, there was no specific evidence to support the extra $3,175.37. He speculated that the jury must have compromised and used parts of each approach {i.e., a combination of the percentage of cost method and the hours expended method).

Obviously, the respondent was only entitled to be compensated once, and since each method represents a separate and distinct means of answering the same question {i.e., What is the reasonable value of respondent’s architectural services?), a combination of those methods would be improper.

Respondent acknowledges this, but points out that the demand in the complaint was for $21,727.12. He then argues that the jury might have used only the percentage of cost of construction method in arriving at its special verdict of $19,448.50. He contends that this court has previously approved the percentage cost of construction approach and, therefore, the court should not disturb the verdict.

*338 The respondent cites Barnes v. Lozoff (1963), 20 Wis. 2d 644, 123 N. W. 2d 543, for the proposition that a percentage of cost of construction is the proper measure of an architect’s services in an action for quantum meruit. The Barnes Case did so hold, hut in Barnes the supreme court noted and accepted the trial court’s conclusion of law to the effect that an actual “contract” existed between the parties. One of the terms of that contract was that the plaintiff would be paid on a percentage basis. The defendant builder in Barnes abandoned the project. As a result the plaintiff was unable to fully perform the contract. Consequently, his cause of action lay not in contract but in quantum meruit. The court first decided that the plaintiff was entitled to recover the “value” of his services, even though those services were of no “value” to the defendant, since he never used the plans and sketches. In other words, the plaintiff, to recover in quantum meruit, is not required to show that the defendant benefited from his services but merely that he rendered such services under the reasonable assumption that he would be paid therefor.

The next issue in Barnes, supra, was — How should the value of plaintiff’s services be measured? The court held that the percentage method was the proper measure but, in doing so, it noted that: (1) There was a contract between the parties (unenforceable as such) which provided for compensation to the plaintiff on a percentage basis; and that (2) no evidence was introduced by the plaintiff as to what his services would be worth on an hourly basis.

The court in Barnes did not hold, or even imply, that the hourly method of measuring value would be improper. 4 It simply did not discuss it because no evidence *339 had been produced on that method. Consequently, the proper conclusion to be drawn from Barnes is this: Where the parties have made a contract which is certain as to its terms, but unenforceable for other reasons, then resort to one of those terms for finding the proper measure of recovery, in an equitable action like quantum meruit, is proper and equitable.

Contrasted with Barnes, the case at bar differs in two significant respects. In this case:

(1) There is evidence on both the percentage and the hourly method of measuring the value of respondent’s services; and

(2) If there is a contract at all, it is unenforceable because of indefiniteness as to the consideration agreed upon.

In Barnes, the parties made a contract and specified how the architect would be compensated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Huelett
603 P.2d 1258 (Washington Supreme Court, 1979)
State Ex Rel. Huser v. Rasmussen
267 N.W.2d 285 (Wisconsin Supreme Court, 1978)
State v. Wind
208 N.W.2d 357 (Wisconsin Supreme Court, 1973)
Rice v. Zurich Insurance
206 N.W.2d 620 (Wisconsin Supreme Court, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
182 N.W.2d 551, 49 Wis. 2d 330, 1971 Wisc. LEXIS 1121, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harper-drake-associates-inc-v-jewett-sherman-co-wis-1971.