Harold A. Newman Co. v. Nero

31 Cal. App. 3d 490, 107 Cal. Rptr. 464, 1973 Cal. App. LEXIS 1090
CourtCalifornia Court of Appeal
DecidedApril 5, 1973
DocketCiv. 1631
StatusPublished
Cited by9 cases

This text of 31 Cal. App. 3d 490 (Harold A. Newman Co. v. Nero) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harold A. Newman Co. v. Nero, 31 Cal. App. 3d 490, 107 Cal. Rptr. 464, 1973 Cal. App. LEXIS 1090 (Cal. Ct. App. 1973).

Opinion

Opinion

GARGANO, J.

This is a judgment roll appeal by appellants, the Ready Power Co. and William Nero from a judgment in favor of Harold A. Newman Co., Inc. and one Lindell Thompson. Ready Power, a Michigan corporation, is the manufacturer of air conditioning equipment, and Nero is that company’s sales and service agent in Fresno, doing business as United Mechanical Equipment Co. The Harold A. Newman Co., hereafter referred to as Newman, is a mechanical contractor. Lindell Thompson *494 is an installer and repairer of air conditioning systems, doing business as Lindell Thompson Refrigeration and Air Conditioning Co.

The action was instituted by Newman against Ready Power, Nero and Western Greyhound Lines for damages and declaratory relief; the action against Ready Power and Nero was predicated on the theory that Newman installed an air conditioning system for Western Greyhound Lines, that certain units of the system were purchased from Ready Power, that those units were defective and caused the system to break down, that Ready Power replaced the equipment, that the replacement work was negligently performed, causing a second breakdown, and that Newman was damaged in the amount of $5,829.92 for additional replacement parts and labor.

Ready Power filed an answer to plaintiff’s complaint. It denied the material allegations and, by way of counterclaim, sought $5,625 in damages for breach of contract; the counterclaim alleged that Newman had agreed to pay for the replacement units and for the cost of installation if Ready Power determined that the first breakdown was not caused by a defect in the original Ready Power equipment. Ready Power also filed a counterclaim to recover the reasonable value of goods and services furnished to Newman; Ready Power filed a cross-complaint against Thompson, alleging that his negligence caused the second breakdown and seeking indemnification for any judgment entered against it under plaintiff’s complaint.

After court trial the court made extensive findings of fact. From these findings the court concluded that Newman was entitled to- judgment in the amount of $5,640.57 for parts and labor. The court also- concluded that Ready Power was not entitled to any compensation for the replacement units it installed after the first breakdown or for the cost of installation. The court determined that Ready Power was not entitled to indemnification from Thompson. Judgment was entered accordingly, and Ready Power and Nero have appealed.

Appellants do not, nor can they, challenge the sufficiency of the evidence; in a judgment roll appeal it is conclusively presumed that the evidence supports the court’s findings. (Block v. Laboratory Procedures, Inc., 8 Cal.App.3d 1042 [87 Cal.Rptr. 778]; Pierce v. Turner, 205 Cal. App.2d 264, 268 [23 Cal.Rptr. 115].) Appellants’ sole attack is directed against the court’s findings of fact. They assert that the findings are deficient and do not support the judgment.

The facts, as taken from the court’s findings, are as follows: In 1968 Newman installed an air conditioning system for Western Greyhound Lines at its bus station in Fresno; the agreed date of completion was in August *495 1968. In September 1968 the air conditioning system, failed to function because of damages to a compressor unit and a chiller unit caused by water in the refrigerant lines; the units were manufactured by Ready Power and were purchased by Newman from that company through the company’s agent, Nero; Newman and Ready Power each sought to attribute the cause of the failure to the other. Ready Power informed Newman that it would replace the original equipment pursuant to its warranty if the units proved to be defective; Newman did not agree to the proposal.

In October 1968 Ready Power, through Nero, engaged Thompson, an independent contractor, to replace the damaged units and to clean, dry and recharge the system. At that time Newman knew that Ready Power was replacing the units and “did not object or assent.”

In early November 1968, Nero attempted to start up the air conditioning system but it again failed to function, this time because of a faulty valve. Afterward, Thompson continued with the repair work until December when the system broke down for the second time; Thompson failed to dry out the system before he recharged it with refrigerant, and the acids formed, destroying the replacement compressor. Thereupon, Newman allegedly expended $5,829.92 for labor and parts to repair and replace the damaged replacement unit.

Appellants complain because the court found that the second compressor was destroyed by Thompson’s negligence in failing to dry out the air conditioning system before he recharged it with refrigerant, and then held appellants liable for the damages resulting from this negligence. They argue that once appellants employed Thompson, an independent contractor, to replace the damaged Ready Power units, they owed no further duty to Newman and could not be held responsible for the independent contractor’s negligence. Appellants assert that the trial court ignored the basic common law rule universally followed in this country, which adheres to the proposition that an independent contractor is ordinarily not liable to third persons for losses attributable to the negligence of the independent contractor.

There is no merit to appellants’ contention. The court’s findings not only support the conclusion that Ready Power had a nondelegable contractual duty to Newman which was violated vicariously by the independent contractor, Thompson, but the findings also support the conclusion that Ready Power, through its agent Nero, was itself guilty of negligence and violated its contractual duty to Newman. The court found that Nero was Ready Power’s agent, that he was a qualified engineer, that he was *496 present on various occasions in October and in early November 1968 when the replacement units were being installed by Thompson, and that he gave directions and observed methods used. The court found, further, that Nero specifically directed Thompson to dry out the air conditioning system before recharging it with refrigerant, that Nero knew, or should have known, that Thompson was not using sufficient vacuum and that notwithstanding this knowledge Nero did not give Thompson instructions on how to proceed. Finally, the court found that in early November, when the system failed to start because of a faulty expansion valve, Nero discovered that it was partially charged, and thereafter left the job site knowing that Thompson would fail to “evacuate” and would nevertheless recharge the system.

It is true that an employer of an independent contractor is ordinarily not liable to third persons for losses attributable to the negligence of the independent contractor; this doctrine of nonliability “is founded on the principle that one person should not be compelled to answer for the fault or neglect of another over whom he has no control, and that the employer has a right to rely on the presumption that the contractor will discharge his legal duties owing to his employees and third persons.” (57 C.J.S., Master and Servant, § 584, p.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sabetian v. Exxon Mobile Corp.
California Court of Appeal, 2020
Sabetian v. Exxon Mobil Corp. CA2/7
California Court of Appeal, 2020
Bowman v. Wyatt
186 Cal. App. 4th 286 (California Court of Appeal, 2010)
Barry v. Raskov
232 Cal. App. 3d 447 (California Court of Appeal, 1991)
Fettig v. Whitman
285 N.W.2d 517 (North Dakota Supreme Court, 1979)
Foremost Insurance Co. v. Rollohome Corporation
221 N.W.2d 722 (North Dakota Supreme Court, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cal. App. 3d 490, 107 Cal. Rptr. 464, 1973 Cal. App. LEXIS 1090, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harold-a-newman-co-v-nero-calctapp-1973.