Harms v. Fitzgerald

1 Ill. App. 325
CourtAppellate Court of Illinois
DecidedApril 15, 1878
StatusPublished
Cited by1 cases

This text of 1 Ill. App. 325 (Harms v. Fitzgerald) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harms v. Fitzgerald, 1 Ill. App. 325 (Ill. Ct. App. 1878).

Opinion

Murphy, P. J.

On the 28th day of April, 1877, appellee exhibited his bill of complaint on the chancery side of the Circuit Court of Cook county, praying an injunction against the Board of County Commissioners to restrain them from paying appellant $34,609.82, the sum which they propose to pay him as part compensation for the foundations of the Cook county court house. The prayer of the bill was granted, and a perpetual injunction decreed. From this decree, Mr. Harms appealed to this Court, and assigns for error:

First, That the court erred in decreeing that the injunction against him and his co-defendants be made perpetual, and enjoining the payment to Harms of any greater sum than $107,071.03, less $92,692.90.

Second, That the court erred in assuming jurisdiction to settle and adjust the claim of appellant which had been already adjusted and settled by the county board.

Fourth. That the decree of the court is contrary to law and evidence in the case.

It appears that the appellant was a contractor engaged in constructing the foundations for the new court house during the years 1875 and 1876; that he had entered into a contract to that effect in the fall of 1875. After signing the contract, and-after he had entered upon the performance thereof, the county made material changes in the plans it had adopted for the construction of the foundations and superstructure of the building. It appears that J. J. Egan was the architect of said building, and that appellant completed the work and extras ordered by the architect as directed. It is also claimed by the answer of appellant that he did not proceed with the work under the contract nor execute the extras under it; but on the contrary that the original contract, plans and specifications, were wholly abandoned and rescinded by consent of the parties to the same; that the county board ordered the architect to prepare entirely new and much more elaborate and costly plans, which were substituted for the original plans, and which were not accompanied by any specifications whatever as to materials or work, but appellant was required by the architect to furnish such materials and do such work as the architect might require and order from time to time; that the new plans were essentially different from the original plans in form and style of work, and were in no sense the same as the old plans with mere changes and additions, but were totally different in all their features and constituted another and different job, and the materials required under the old specifications could not be used in the building'according to the new plans; that the architect, with the authority and knowledge of the board, agreed with appellant to pay him a fair and reasonable value fot the work, and under this verbal agreement appellant went on and completed the job under the direction of the architect, and that the work and materials furnished by him were reasonably worth $162,967.89; denies that he ever agreed that .the architect should value arid determine the price of the work and materials under the new plans, or that the architect has made a fair and true estimate of the work, or that there is only'due the sum of $107,071.03, less $92,692.90 already paid; denies that the amount of $141,689.90 allowed by the board of commissioners, was based upon the original contract, said allowance having been made on the basis of measurement and value of the whole work; and yet upon an erroneous valuation, said board having been misled in rejecting so large an amount of said appellant’s claim; that it is impossible to apply the original contract or trace it in the work actually done, being so essentially different in character and details from that required by the original specifications, and finally submits that the county board had the exclusive authority by law to manage and control matters connected with the building of said court house, and to audit and settle all claims for work and materials, and denies the jurisdiction of the court to revise and correct the action of the board in the premises, or to enjoin it from exercising its legal power and discretion in regard to the same. To this answer appellee filed a general replication.

As will be seen, the issue thus formed, and the fact thus in dispute- was, whether the work as actually and finally done was done in pursuance of, and in conformity to, the original contract, and whether the compensation therefor was to be ascertained and determined by the stipulations of such contract, or whether the alterations and changes so made were such a departure from such contract as to be in substitution therefor. It appears from the estimates of the architect that if the compensation for such work was to be determined by the original contract, it would amount to $107,071.03; that after the deduction of the sum of $92,692.90, which had been paid him, there would he still due to the appellant the sum of $14,378.13; that if the basis of computation should be the fair market value oí the work ascertained by measurement and valuation, it would be $162,967.89. It appears that appellant presented to the board his claim for payment for said work at that figure, and that the board took said proposition into consideration, and after mature deliberation voted to award him as full compensation for said work, and in full settlement of his said claim, the sum of $141,689.80; being in excess of the amount fixed by the architect on the basis of the contract of $34,609.82, and $21,278.08 less than the sum claimed by appellant, to restrain the payment of which, less the sum previously paid thefeon by said board, the appellee, as resident and tax-payer of the county, filed this bill.

The testimony in the case in support of the respective allegations in the bill and in the answer is in conflict, there being testimony introduced by each side tending to support said allegations respectively; and if the litigation was between the county on the one side and appellant upon the other, it might be a question more or less difficult to determine which wray the testimony preponderates; but in the view taken of the case by the Court, it is not material to decide that question, or further to consider the same than to determine that it presents a question involved in uncertainty and doubt as to the facts of the case; and that being the case, we think it presents a question of the jurisdiction of a court of equity, and it is our purpose to rest our decision upon that question. By the Constitution, Art. 10, Sec. 7, it is provided that “ the county affairs of Cook county shall be managed by a board of commissioners of fifteen persons, ten of whom shall be elected from the city of Chicago, and five from towns outside of said city, in such manner as may be provided by law.”

By an act of the legislature entitled “ An Act to revise the Laws in relation to Counties,” approved March 31st, 1874, Sec. 22 provides that “ each county which has heretofore been, or may hereafter be established in this state, according to the laws thereof, shall be a body politic and corporate, by the name and style of “ The County of -” and by that name may sue and be sued, plead and may be impleaded, defend and be defended against in any Court of Record having jurisdiction of the subject matter, either in law or equity, or other place where justice shall be administered.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cors v. Tompkins
51 Ill. App. 315 (Appellate Court of Illinois, 1894)

Cite This Page — Counsel Stack

Bluebook (online)
1 Ill. App. 325, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harms-v-fitzgerald-illappct-1878.