Harlev v. Sanitary District of Chicago

80 N.E. 771, 226 Ill. 213
CourtIllinois Supreme Court
DecidedFebruary 21, 1907
StatusPublished
Cited by10 cases

This text of 80 N.E. 771 (Harlev v. Sanitary District of Chicago) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harlev v. Sanitary District of Chicago, 80 N.E. 771, 226 Ill. 213 (Ill. 1907).

Opinion

Mr. Justice Cartwright

delivered the opinion of the court:

This is a suit in assumpsit commenced by appellant in the superior court of Cook county to recover damages suffered by him by reason of the alleged wrongful forfeiture by appellee of a contract entered into by the said parties, by which appellant undertook to excavate a section of the drainage canal extending from Willow Springs south-west six thousand feet. The contract was executed on July 12, 1892, and in addition to excavating the main "channel plaintiff was to excavate a new channel for the Desplaines river for about three thousand feet of the distance for the purpose of confining that stream to the north-west side of the canal, and this was called the river diversion. The right of way of the main channel" was covered, over the greater part of its surface, with a heavy growth of timber, which^ the plaintiff was required to grub out, and all material so grubbed out which was oí any value was to be his property. He was to build and construct, at his own expense, all levees necessary to protect the work, and all expenses and damages from flooding were to be borne by him. He was required to give his personal attention to the execution of the work and not to sub-let all or any part of it, and any sub-letting was to work a forfeiture of the contract, at the option of the'defendant: Plaintiff agreed to begin work within thirty days after the execution of the contract, or as soon after the expiration of thirty days as defendant should acquire title to the necessary right of way and notify him to begin, and he was to carry on the work at such points and in such manner as the time and manner of procuring the right of way might render necessary. Only such work as building levees, changing river channels, grading road-beds, and other subsidiary work where the land had been acquired, was to be required of plaintiff until it was possible to open the main channel at the best point from which to execute the work. The contract was to be completed on or before April 30,1896, but if plaintiff was not permitted to begin the main excavation on or before August 1, 1892, the time for the completion of the contract was to be extended as much after the time specified for its completion as the time of beginning the main work was subsequent to August 1, 1892. It was provided that the work done each month should not be less than such portion of the whole work as one month bore to the total number of months agreed upon for the completion of the whole work, counting the first four months after notice to begin as one month and the last two months before the date of completion as one month. The provision of the contract under which the forfeiture was declared is as follows : “In case the contractor fails to comply with the provisions of this contract as to progress and character of work, he shall be notified in writing, and thirty days after the giving of said notice the party of the first part may dedare this contract forfeited, if there is substantial failure to comply with its provisions.” On November 26, 1892, notice was served on plaintiff by defendant to commence work on the river diversion. On December 17, 1892, the defendant notified him that it would be in possession on December 19 of the necessary land, and directed him to begin work at once 011 the main excavation. After receiving the notice of December 17 plaintiff made a contract for the construction of buildings for the accommodation of his men and teams and for the opening of a store. On January 10, 1893, he reported what he had done and promised to proceed as fast as possible. On January 18, 1893, he made a contract with Nelson Bleau for. the grubbing and removal of the timber. That work was commenced the last of January, 1893, and in taking out the timber a considerable quantity of earth was removed, of which plaintiff procured an estimate and for which he was paid in February as for earth excavated. That contract was abandoned by Bleau, and plaintiff hired men and was engaged for nine months in doing the grubbing. In June, 1893, plaintiff began excavating earth -with scrapers and shovels. He was also working on the river diversion, and had a controversy with defendant about extra payment for excavating hard-pan in that channel. In settlement of that-difficulty the defendant took upon itself the construction of the river diversion, and a new contract was made on August 30, 1893, by which the provisions for that work in the original contract were eliminated and plaintiff was employed as superintendent of the work on the river diversion, and was to use his own implements and machinery and have fifteen per cent of the cost of the work. The river diversion was completed on November 16, 1893: The defendant was not satisfied with the rate of progress made by the plaintiff and claimed that it was not the rate required by the contract, and plaintiff made some promises, but the controversy continued, and on February 10, 1894, the defendant declared the contract for-felted on account of the failure of plaintiff to comply with its provisions. This suit was begun on August i, 1894, and the declaration alleged that the plaintiff was at all times ready and willing and offered to perform his contract, but the defendant illegally, wrongfully and improperly declared it forfeited and prevented him from performing it, whereby he suffered the damages alleged in the declaration. The case was twice tried. On the first trial the court instructed the jury to return a verdict for the defendant, which was done and judgment was entered. On appeal to the Appellate Court for the First District the judgment was reversed and the cause was remanded for another trial. On that trial a verdict was returned for the defendant, with the following special interrogatories submitted to the jury at the request of plaintiff, and their answers thereto:

“At the time notice was served on the plaintiff by the defendant, December 30, 1893, for the forfeiture of the contract, was the plaintiff behind in the amount of work required by the contract ?—A. Yes.

“Was the character of the work bad?—A. Yes.

“Was the contract forfeited by the defendant because of • the character of the work as well as lack of progress ?—- A. Yes.”

■ Judgment for the defendant was entered, from which appellant took an appeal to the Appellate Court for the First District, and the branch of that court affirmed the judgment.

Many questions exhaustively argued by counsel for appellant have been conclusively settled in favor of appellee by the judgment of affirmance of the Appellate Court. The same arguments were addressed to the Appellate Court, and in this court counsel have added thereto comments on the opinion of the Appellate Court, insisting that the conclusions of fact reached by that court are contrary to the evidence. With those questions we have nothing to do. One such question is whether it was necessary to change the channel of the river to open the main channel at the best point from which to execute the work, on which counsel say that much evidence was introduced on both sides. Counsel say that the court ought to have determined that the time for beginning the work was November 16, 1893, but that question depended entirely upon the facts proved, and unless the jury were misdirected as to the law the question has been finally settled.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Library Trustees v. Fidelity & Deposit Co.
429 N.E.2d 203 (Appellate Court of Illinois, 1981)
Ard Dr. Pepper Bottling Co. v. Dr. Pepper Co.
202 F.2d 372 (Fifth Circuit, 1953)
Mosso v. Lee
295 P. 776 (Nevada Supreme Court, 1931)
Grounds v. VanLaningham
256 Ill. App. 540 (Appellate Court of Illinois, 1930)
Parker-Washington Co. v. City of Chicago
267 Ill. 136 (Illinois Supreme Court, 1915)
Tarr v. Stearman
264 Ill. 110 (Illinois Supreme Court, 1914)
Springfield & Northeastern Traction Co. v. Warrick
94 N.E. 933 (Illinois Supreme Court, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
80 N.E. 771, 226 Ill. 213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harlev-v-sanitary-district-of-chicago-ill-1907.