Haren Construction Company, Inc. v. Olen Ford

CourtCourt of Appeals of Tennessee
DecidedMarch 19, 2024
DocketE2023-00503-COA-R3-CV
StatusPublished

This text of Haren Construction Company, Inc. v. Olen Ford (Haren Construction Company, Inc. v. Olen Ford) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Haren Construction Company, Inc. v. Olen Ford, (Tenn. Ct. App. 2024).

Opinion

03/19/2024 IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE February 15, 2024 Session

HAREN CONSTRUCTION COMPANY, INC. v. OLEN FORD

Appeal from the Chancery Court for Knox County No. 203538-2 Richard B. Armstrong, Jr., Chancellor ___________________________________

No. E2023-00503-COA-R3-CV ___________________________________

The Chancery Court for Knox County (the “Trial Court”) granted the motion for partial summary judgment filed by Haren Construction Company, Inc. (“Plaintiff”), concluding that Olen Ford d/b/a Olen Ford Masonry and Construction (“Defendant”) had breached his contract with Plaintiff. The Trial Court awarded a judgment to Plaintiff against Defendant in the amount of $64,971.40. Defendant has appealed. Discerning no reversible error, we affirm the Trial Court’s judgment.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed; Case Remanded

D. MICHAEL SWINEY, C.J., delivered the opinion of the court, in which JOHN W. MCCLARTY and KRISTI M. DAVIS, JJ., joined.

John P. Valliant, Jr., and John P. Valliant, III, Knoxville, Tennessee, for the appellant, Olen Ford.

Robert P. Noell and David J. Cantrell, Knoxville, Tennessee, for the appellee, Haren Construction Company, Inc. OPINION

Background

On November 5, 2021, Plaintiff filed a complaint in the Trial Court, alleging claims of breach of contract and promissory estoppel against Defendant. Plaintiff explained that it had served as the prime contractor for Knoxville Utility Board’s (“KUB”) Fourth Creek WWTP Sodium Hypochlorite Conversion Project (“the project”). In preparing its bid to construct the project for KUB, Plaintiff solicited bids for various components of the project. On March 18, 2021, Defendant submitted a bid to Plaintiff for the masonry component of the project.

Plaintiff alleged that it had relied on Defendant’s bid in submitting its bid for the prime contract to KUB and identified Defendant as the masonry subcontractor in its bid. Plaintiff submitted its bid on March 19, 2021, and was awarded the prime contract on April 20, 2021. On May 18, 2021, Plaintiff tendered to Defendant a purchase order, titled “Subcontract/Material Order/Service Agreement,” for the amount of $185,028.60. Plaintiff alleged that Defendant had begun his performance of the masonry work by providing Plaintiff with multiple rounds of submittals and delivering sample materials for approval. Plaintiff further claimed that Defendant then ceased work and abandoned the project prior to installing the masonry.

Plaintiff alleged that it had sent Defendant a letter and email in October 2021, placing Defendant on notice that if he did not perform the masonry work as promised, Plaintiff would be forced to procure another subcontractor. Defendant continued to refuse to complete the work. As a result, Plaintiff entered into a subcontract with another masonry subcontractor, who agreed to complete the work for $250,000. Plaintiff sought damages in the amount of $64,971.40, the difference between the $250,000 owed to the new subcontractor and the amount for which Defendant had agreed to complete the project. Plaintiff additionally sought interest, delay damages, attorney’s fees, and other damages in an amount to be proven at trial. Plaintiff attached to its complaint the purchase order sent to Defendant in May 2021. Defendant never signed the purchase order.

On April 21, 2022, Defendant filed an answer to the complaint, denying the substance of Plaintiff’s allegations. Defendant specifically claimed that Plaintiff had no right to rely on his bid without a signed contract and that there had been no “meeting of the minds as to the terms of the contract.”

Plaintiff filed a motion for partial summary judgment, a memorandum of law in support, and a statement of undisputed material facts on December 7, 2022. Plaintiff argued that there were no genuine issues as to any material facts concerning the formation of the parties’ contract or Defendant’s breach of their contract. Alternatively, -2- Plaintiff claimed that there was no dispute that Defendant had made an unambiguous promise to perform the masonry work and that Plaintiff had justifiably relied on that promise to its detriment.

In its statement of undisputed material facts, Plaintiff set forth the following, in pertinent part:

3. On February 11, 2021, [Plaintiff] sent Defendant an “Invitation to Bid,” which included the KUB Plans and Specifications for the Project, proving Defendant an opportunity to bid on work as one of [Plaintiff’s] subcontractors on the Project. See id. at ¶ 6.

4. The Invitation to Bid included the KUB Plans and Specifications for the Project, which potential bidders would use to familiarize themselves with the Project, the terms and conditions of acting as a subcontractor on the Project, and to formulate their respective bids on the Project. See id. at ¶ 7.

5. The KUB Plans and Specifications for the Project provided, among other things, that the masonry scope of work included submittals (KUB Plans and Specifications, Section 01300) and the furnishing and installation of the masonry work at the Project (KUB Plans and Specifications, Sections 03200, 04100, 04150, and 04200). See id. at ¶ 8.

6. On March 18, 2021, in response to the Invitation to Bid, Defendant submitted its written bid to [Plaintiff] to perform the masonry work on the Project for $174,154. See Exhibit 1 attached to the Motion.

7. On March 19, 2021, prior to submitting its bid to KUB, [Plaintiff] notified Defendant that it was the low bidder for the masonry scope of work on the Project by a large margin, and [Plaintiff] wanted to confirm Defendant’s bid was accurate and complete. See Anders Aff. ¶ 10. [1]

8. Defendant told a representative from [Plaintiff] that its bid was accurate and complete, and that it was not uncommon for Defendant’s bid to be significantly lower than its competitors. See Anders Aff. ¶ 11.

9. Under Tennessee law, because the Project was a public project, prior to submitting its bid to KUB, [Plaintiff] must select the masonry

1 The “Anders Affidavit” refers to an affidavit by Marcus Anders, a project manager employed by Plaintiff and the “Assistant Project Manager” on the project. The affidavit was attached as an exhibit to Plaintiff’s motion for partial summary judgment. -3- subcontractor that will perform the masonry scope of work at the Project, and write the name, license number, expiration date of the license, and license classification of that masonry contractor on the exterior of the bid sheet that [Plaintiff] submits to KUB. See Tenn. Code Ann. § 62-6- 119(b)(2).

10. On March 19, 2021, in reliance on Defendant’s written bid, [Plaintiff] wrote Defendant, “Olen Ford Masonry,” as its mason on the bid coversheet [Plaintiff] submitted to KUB to serve as the prime contractor on the Project. See Anders Aff. ¶ 13; see also Exhibit 2 attached to the Motion.

11. On March 23, 2021, [Plaintiff] notified Defendant via email that [Plaintiff] was the low bidder on the Project and that [Plaintiff] accepted Defendant’s bid to perform the masonry work on the Project for $174,154, creating a binding and enforceable contract (the “Contract”). See Anders Aff. ¶ 14; see also Exhibit 3 attached to the Motion.

12. Defendant acknowledged [Plaintiff]’s acceptance of its offer, by responding to [Plaintiff]’s email, “Great, thanks for the update.” See id.

13. Shortly thereafter, the parties made two amendments to the Contract. See Anders Aff. ¶ 15.

14.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Estate of Ina Ruth Brown
402 S.W.3d 193 (Tennessee Supreme Court, 2013)
R. Douglas Hughes v. New Life Development Corporation
387 S.W.3d 453 (Tennessee Supreme Court, 2012)
Abshure v. Methodist Healthcare-Memphis Hospitals
325 S.W.3d 98 (Tennessee Supreme Court, 2010)
Staubach Retail Services-Southeast, LLC v. H.G. Hill Realty Co.
160 S.W.3d 521 (Tennessee Supreme Court, 2005)
Burton v. Warren Farmers Cooperative
129 S.W.3d 513 (Court of Appeals of Tennessee, 2002)
Moody Realty Co., Inc. v. Huestis
237 S.W.3d 666 (Court of Appeals of Tennessee, 2007)
Doe v. HCA Health Services of Tennessee, Inc.
46 S.W.3d 191 (Tennessee Supreme Court, 2001)
T.R. Mills Contractors, Inc. v. WRH Enterprises, LLC
93 S.W.3d 861 (Court of Appeals of Tennessee, 2002)
Owens v. Bristol Motor Speedway, Inc.
77 S.W.3d 771 (Court of Appeals of Tennessee, 2001)
Bain v. Wells
936 S.W.2d 618 (Tennessee Supreme Court, 1997)
APCO Amusement Co. v. Wilkins Family Restaurants of America, Inc.
673 S.W.2d 523 (Court of Appeals of Tennessee, 1984)
Scandlyn v. McDill Columbus Corp.
895 S.W.2d 342 (Court of Appeals of Tennessee, 1994)
Michelle RYE Et Al. v. WOMEN’S CARE CENTER OF MEMPHIS, MPLLC Et Al.
477 S.W.3d 235 (Tennessee Supreme Court, 2015)
Cole-McIntyre-Norfleet Co. v. Holloway
141 Tenn. 679 (Tennessee Supreme Court, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
Haren Construction Company, Inc. v. Olen Ford, Counsel Stack Legal Research, https://law.counselstack.com/opinion/haren-construction-company-inc-v-olen-ford-tennctapp-2024.