Hardrives Paving Construction v. Mecca, Unpublished Decision (9-30-1999)

CourtOhio Court of Appeals
DecidedSeptember 30, 1999
DocketNo. 98-T-0192.
StatusUnpublished

This text of Hardrives Paving Construction v. Mecca, Unpublished Decision (9-30-1999) (Hardrives Paving Construction v. Mecca, Unpublished Decision (9-30-1999)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hardrives Paving Construction v. Mecca, Unpublished Decision (9-30-1999), (Ohio Ct. App. 1999).

Opinion

OPINION
This is an appeal from the Trumbull County Court of Common Pleas. Appellant, Hardrives Paving Construction, Inc., appeals the trial court's October 19, 1998 judgment entry.

On August 10, 1998, appellant filed a verified complaint against appellee, the Mecca Township Board of Trustees. The complaint sought injunctive relief, declaratory judgment, compensatory damages and punitive damages against appellee. On that same date, appellant moved for a temporary restraining order and applied for a preliminary injunction enjoining appellee from permitting work to commence. The trial court granted appellant's motion for a temporary restraining order. Thereafter, the trial court heard appellant's application for a preliminary injunction on August 21, September 8, and September 9, 1998.

The facts reveal that in July 1998, appellee solicited competitive bids for a project that was advertised in the local newspaper (the "Griffith Drive project"). Appellant, along with other bidders, timely submitted sealed bids in response to the advertisement. On August 3, 1998, the bids were opened and appellant bid $33,637 for the project. Gennaro Pavers, Inc. ("Gennaro") submitted the second lowest bid in the amount of $34,890. Appellee, which consisted of Darryl Black ("Black"), Blake Peterson ("Peterson"), and Michael Colello ("Colello"), awarded the job to Gennaro and a contract was executed.

At the hearing on the preliminary injunction, Black's testimony revealed that he was dissatisfied with appellant's work performance on a former job (the "Housel-Craft project"), which was to be done by June or July of 1996, but was actually completed in April 1997. Black indicated that appellees were still experiencing problems with that project. Black further asserted that in determining whom to award the Griffith Drive project to, his understanding of the lowest and best bid meant, "the lowest bid and the best performance that you have to judge with that. * * * And if you have a contractor that you have problems with or have had problems and they're not corrected, [one] would weigh that as far as applying it again to give you another job * * *."

Peterson testified that following a special meeting on April 8, 1998, he contacted appellant regarding the Housel-Craft project. He told appellant's agent that there were certain cracks that needed to be sealed. Appellant's agent led Peterson to believe that someone from the company would seal the cracks, yet the resealing was never done. However, Peterson indicated that had the sealing been done, it "may have made a difference in [his] opinion" as to who would be awarded the Griffith Drive project.

Colello revealed that he was disappointed with appellant's performance on the Housel-Craft project. He "felt that the way [appellant] conducted [itself] was inappropriate" as was the way it treated residents. Colello believed that appellant used improper equipment and caused unnecessary delays on the Housel-Craft project. He explained that he "* * * was unhappy with everything that had gone on, but the road was completed. [He] was unhappy with the way it got completed * * *." Based on this experience, Colello reasoned that it would have been difficult for him to award the Griffith Drive project to appellant.

The Trumbull County Engineer, John Latell ("Latell"), testified that he knew that a completion date had been set for the Housel-Craft project, but appellant went beyond the period of time.

On September 18, 1998, appellant submitted a "Brief in Lieu of Closing Argument," in which appellant moved for a preliminary injunction pursuant to Civ.R. 65. Appellee also filed a closing argument that moved for a dismissal and denial of appellant's motion for temporary restraining order and preliminary injunction. In a judgment entry dated October 19, 1998, the trial court denied appellant's request for injunctive relief.1 Later that morning, appellant filed a response to appellee's closing arguments. Appellant timely appealed and now asserts the following as error:

"[1.] The Trial Court erred to the prejudice of [appellant] by failing to render its decision to deny [appellant's] Application for Preliminary Injunction, in accordance with the law applicable to injunctive relief.

"[2.] The Trial Court erred to the prejudice of [appellant] by incorrectly applying relevant law to the facts of the instant case.

"[3.] The Trial Court erred to the prejudice of [appellant] by failing to address relevant facts in its determination of the merits of [appellant's] lawsuit.

"[4.] The Trial Court erred to the prejudice of [appellant] by failing to consider relevant evidence in denying [appellant's] Application for Preliminary Injunction.

"[5.] Pursuant to [Civ.R.] 65, the Trial Court erred to the prejudice of [appellant] in rendering a decision on the merits of this action."

Since appellant's first, second, third, and fourth assignments of error are interrelated, they will be addressed in a consolidated fashion. Initially, we note that in considering an application for injunctive relief, the following guidelines are appropriate for a court to take into account: (1) the likelihood of the plaintiff's success on the merits; (2) whether there exists an adequate remedy at law; (3) whether the injunction would prevent irreparable harm; (4) a balancing of the potential injury to the defendant and the general public; and (5) whether the injunctive relief sought is for the purpose of maintaining the status quo pending a trial on the merits. Diamond Co. v. Gentry Acquisition Corp., Inc. (1988), 48 Ohio Misc.2d 1, 2. Pursuant to Gentry, since Civ.R. 65 does not specifically set forth standards for the issuance of relief, the foregoing criteria are appropriate for a trial court to consider when making a determination on a request for injunctive relief. The guidelines are not mandatory, and thus, are not required to be taken into account.

Assuming arguendo, that the balancing test was mandatory, appellant has failed to meet all five standards. In the case at bar, the record is devoid of any evidence that appellant suffered any irreparable harm and/or injury thereby making it difficult for the trial court to consider that factor. Further, appellant has failed to demonstrate how it suffered or will in the future suffer irreparable harm. Hence, the trial court did not err in denying appellant's request for injunctive relief.

Additionally, R.C. 5575.02 requires that "[t]he contract shall be awarded to the lowest and best bidder * * *." However, the "lowest and best" bid does not necessarily mean the lowest dollar bid. See Cedar Bay Constr., Inc. v. Fremont (1990), 50 Ohio St.3d 19,21, quoting Altschul v. Springfield (1933) 48 Ohio App. 356,362. The decision whether to award a contract based on the lowest and best bid lies within the sound discretion of the contracting authority. Altschul, 48 Ohio App. at paragraph one of the syllabus. A decision will only be reversed when the evidence indicates that there has been an abuse of discretion. CampbellContracting Co. v. City of Ravenna (Dec. 9, 1994), 93-P-0044, unreported, at 7. The term "abuse of discretion" implies an unreasonable, arbitrary or unconscionable attitude. Dayton exrel. Scandrick v. McGee (1981), 67 Ohio St.2d 356, 359

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Standard Oil Company of Texas v. Lopeno Gas Company
240 F.2d 504 (Fifth Circuit, 1957)
Hardrives Paving & Construction, Inc. v. City of Niles
650 N.E.2d 482 (Ohio Court of Appeals, 1994)
Turoff v. Stefanac
475 N.E.2d 189 (Ohio Court of Appeals, 1984)
Altschul v. City of Springfield
193 N.E. 788 (Ohio Court of Appeals, 1933)
State v. Dehass
227 N.E.2d 212 (Ohio Supreme Court, 1967)
City of Dayton, ex rel. Scandrick v. City of Dayton Mayor McGee
423 N.E.2d 1095 (Ohio Supreme Court, 1981)
Cedar Bay Construction, Inc. v. City of Fremont
552 N.E.2d 202 (Ohio Supreme Court, 1990)
George P. Ballas Buick-GMC, Inc. v. Taylor Buick, Inc.
449 N.E.2d 805 (Lucas County Court of Common Pleas, 1981)
Diamond Co. v. Gentry Acquisition Corp.
531 N.E.2d 777 (Cuyahoga County Common Pleas Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
Hardrives Paving Construction v. Mecca, Unpublished Decision (9-30-1999), Counsel Stack Legal Research, https://law.counselstack.com/opinion/hardrives-paving-construction-v-mecca-unpublished-decision-9-30-1999-ohioctapp-1999.