Hardco Inc. v. Lutali

14 Am. Samoa 2d 1
CourtHigh Court of American Samoa
DecidedJanuary 16, 1990
DocketCA No. 111-88
StatusPublished

This text of 14 Am. Samoa 2d 1 (Hardco Inc. v. Lutali) is published on Counsel Stack Legal Research, covering High Court of American Samoa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hardco Inc. v. Lutali, 14 Am. Samoa 2d 1 (amsamoa 1990).

Opinion

Plaintiff (hereinafter sometimes referred to as "Hardy") built an extension or addition to a home belonging to defendants A.P. and Susana Lutali. The Lutalis made payments in a total amount of $82,458 but declined to pay several subsequent invoices sent by plaintiff in a total amount of $47,986. Hardy brought this action to recover the unpaid balance.

The Lutalis contend that Hardy agreed to do the entire job for $65,000; that the work was substandard in various ways; and that Hardy fraudulently billed them for labor and materials not actually employed in the building of the addition. By way of counterclaim they demand $97,000 in compensation for the damage they claim to have suffered on account of these alleged breaches of the contract, as well as for punitive damages and attorney fees.

I. Facts

We find the facts to be as follows:

1) In late 1985 or early 1986, Mr. and Mrs. Lutali met with Don Hardy, the managing officer and co-owner of the plaintiff coiporation, to discuss the possibility of his building an extension to their home in Ili‘ili. A.P. Lutali and Don Hardy had been friends for several years.

2) The Lutalis initially wished only to extend by a few feet the length of the existing bedrooms on their one-story house. At the meeting with Mr. Hardy, however, the discussion eventually focussed on the possibility of a discrete two-story addition containing several new rooms.

[3]*33) At this meeting or shortly thereafter, Mr. Hardy may have given a verbal estimate of $65,000 for the two-story addition.

4) On May 27, 1986, Mr. Hardy delivered to Lutali’s office a letter estimating that the addition would "take three months to complete and would cost approximately $75,000." The letter also stated that the addition "would be constructed on the same design as the present house" and that "[a]s all materials would be ordered from the U.S.A., the quality would be of the highest."

5) In June or July of 1986, Mr. Hardy arranged for plans to be drawn up depicting the proposed addition. Although it is not clear whether the Lutalis actually reviewed these plans, the preponderance of the evidence is to the effect that they at least had the opportunity to do so.

6) Don Hardy testified that the initial plan for the addition (on which he says his $75,000 estimate was based) called for a structure 48 feet long, and that at some point the Lutalis ordered the length extended to 53 feet so that it would be the same as the length of their existing house. While a 48 foot extension may have been discussed at some early stage of the negotiations, the evidence does not support a finding that a change in the size of the proposed structure was made between May 27 when Mr. Hardy gave the $75,000 estimate and July when the plans were drawn up. The voluminous documentary evidence with which we have been presented includes no plans for a 48-foot structure and no other documentary evidence reflecting a change in the parties’ understanding. Neither defendant A.P. Lutali nor witness Epenefa Te‘o, the person retained by Hardy to draw the plans, recalls a revision during this period. We therefore find that the structure for which Mr. Hardy ordered plans to be drawn in June or July of 1986 was the same structure he had offered on May 27 to build for approximately $75,000.

7) In July or early August Mr. and Mrs. Lutali met with Don Hardy and his wife, the other co-owner of the plaintiff corporation, to discuss flooring materials, bathroom fixtures, and so forth. The Lutalis selected materials of relatively high quality, such as parquet hardwood floors and ceramic tiles. Neither A.P. Lutali nor Don Hardy recalls any discussion of the price of these materials. Hardy testified that he assumed the Lutalis understood that their selection of such materials would increase the price of the structure; Lutali testified that he believed he was entitled to high quality materials for the price that had already been agreed upon.

[4]*48) During this period the parties discussed having Hardy renovate the existing portion of the Lutali home. The proposed renovations included a master bathroom, a "ladies’ lounge," and improvements to the kitchen.

9) On August 7, 1986, Don Hardy wrote a letter to Susana Lutali enclosing a list of the materials he had ordered for the addition. The total cost to the Lutalis was to be $50,905.17. Hardy noted that it was "very possible" that some material might be "leftover" and therefore available for use on the renovations to the existing structure, and also that he "might have missed something which we can get on the next shipment when we order for your master bath, Ladies lounge, and the kitchen."

10) At some time between August 7 and October 7, the Lutalis paid the $50,905 invoice for materials and an additional $9,000 for freight.

11) Construction on the addition began in late August or early September.

12) On September 15 Hardy sent the Lutalis an additional invoice in the amount of $13,276 ($6,516 for additional materials and $6,760 for labor).

13) On October 4 Hardy sent yet another invoice for $9,277 ($677 for materials and $8,600 for labor).

14) On October 7 Hardy furnished the Lutalis with a written estimate of the entire amount that would be necessary to finish both the two-stpry addition and the renovations to the existing structure. This estimate was for $148,825, not including the $59,905 the Lutalis had already paid. It breaks down as follows:

Material, Labor, and Freight already billed for the addition (including the $59,905 already paid): $82,458
Material and freight for remodeling the existing structure (apparently for materials already ordered or about to be ordered by Hardy from his supplier in the United States): 81,272
"Estimated Material & Labor to complete job": 45.000
[5]*5Total: $208,730
Minus amount already paid: - 59.905
Total cost to complete both projects: $148,825

15) It was not made clear on this invoice how much of the $45,000 "to complete job" was for completing the two-story addition and how much was for the proposed renovations to the older part of the house. Taking account of the evidence that some progress had been made on the addition whereas the renovations were barely begun, we estimate that no less than $10,000 and no more than $20,000 of the remaining $45,000 was to complete the addition. Thus Hardy’s revised estimate of the total cost of the addition, as of October 7, was between $92,458 and $102,458.

16) Shortly after receipt of the October 7 estimate, the Lutalis told Hardy they could not afford the proposed renovations to the preexisting structure. They directed him to proceed with the addition but not with the renovations. (We have insufficient evidence to determine whether the parties ever had a contract with regard to the proposed renovations to the pre-existing structure. It appears that Hardy had begun work on them prior to October 7, yet it also appears that the Lutalis made it clear they did not want the renovations as soon as they were given a firm estimate of the cost. Since neither party seeks relief for the breach of any agreement involving renovations to the pre-existing structure, we need not conclude whether there was such an agreement.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Evans v. Mason
308 P.2d 245 (Arizona Supreme Court, 1957)
Jacob & Youngs, Inc. v. Kent
129 N.E. 889 (New York Court of Appeals, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
14 Am. Samoa 2d 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hardco-inc-v-lutali-amsamoa-1990.