Harbor Insurance v. Schnabel Foundation Co.

992 F. Supp. 419, 1997 U.S. Dist. LEXIS 21591, 1997 WL 829418
CourtDistrict Court, District of Columbia
DecidedApril 4, 1997
DocketCivil Action 87-2212 (HHG)
StatusPublished

This text of 992 F. Supp. 419 (Harbor Insurance v. Schnabel Foundation Co.) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harbor Insurance v. Schnabel Foundation Co., 992 F. Supp. 419, 1997 U.S. Dist. LEXIS 21591, 1997 WL 829418 (D.D.C. 1997).

Opinion

Opinion

HAROLD H. GREENE, District Judge.

This case was retried before the Court between plaintiff Harbor Insurance Company (“Harbor”), subrogee of OMNI Construction, Inc. (“OMNI”), and defendant Schnabel Foundation Company (“Schnabel”), OMNI’s sheeting and shoring subcontractor, following a remand by the Court of Appeals.

BACKGROUND AND PROCEDURAL HISTORY

This dispute revolves around damage to the restored nineteenth century structure at 633 Pennsylvania Avenue, N.W., Washington, D.C. owned by Sears, Roebuck & Company (“Sears Building”) from the construction of an adjoining office building at 601 Pennsylvania Avenue. The damage occurred when the excavation and construction caused the ground under the Sears Building to settle. The crux of the dispute is whether Schnabel was negligent in designing and installing the sheeting and shoring system at the 601 Pennsylvania Avenue site (the “Project”).

American Insurance Company (“American”) was the primary liability insurance carrier, providing a maximum coverage of $300,-000, and Harbor was the umbrella liability insurance carrier for both Westminster and OMNI. Both carriers, as subrogees of OMNI, originally brought this action for breach of contract and negligence against Schnabel and three co-defendants to recover monies paid under the respective policies to OMNI for liabilities incurred when the Sears Building was damaged. The case went to trial in June of 1990, and a jury returned a verdict in favor of Schnabel on all claims. The Court of Appeals reversed, holding that the Court erred in submitting Schnabel’s contributory negligence to the jury because there was insufficient evidence to support such a finding by a reasonable jury. 1 The case was remanded for a new trial. The Court heard the case again 2 — this time without a jury — on April 22,1996 through May 1, 1996.

After consideration of the testimony and exhibits introduced at trial, and the parties’ briefs and post-trial material, the Court makes the following findings of fact and conclusions of law pursuant to Fed.R.Civ.P. 52(a). Any conclusions of law which constitute findings of fact and findings of fact which constitute conclusions of law shall be considered as having been determined accordingly.

FINDINGS OF FACT

I

On May 15, 1984, OMNI and Westminster Investing Corp. (“Westminster”), a real estate development company, entered into an agreement for the construction of a nine *421 story office building and underground parking garage at 601 Pennsylvania Avenue. The construction was to take place directly next to the Sears Building. One of the structures comprising the Sears Building complex- — adjacent to the Project — -was referred to as the Brady Building.

OMNI was Westminster’s general contractor on the project. Westminster hired Leo A. Daly & Associates (“Daly”) as the Project’s Architect/Engineer. Daly generated the construction specifications and drawings for the Project. Westminster also hired Schnabel Engineering Associates (“SEA”), a geotechnical engineering firm, to analyze subsurface soil conditions at the Project. SEA produced three reports dated April 30, 1982, November 16, 1983, and January 23, 1984. The original SEA report provided the “recommended scope of excavation sheeting and underpinning, and criteria for design,” as well as “geotechnical construction considerations that should be considered both in the design, and in the construction plans and specifications.”

SEA made recommendations regarding the “sheeting and shoring” system — the system of support installed to retain the walls of the excavation and protect adjacent properties. The sheeting and shoring system ensures that material does not fall into the site during the excavation and that the adjoining earth and properties do not slip into the excavation site as it is dug. The report recommended that a “free draining sheeting system,” using wood lagging and soldier piles, be used. Soldier piles are driven vertically into the earth spaced some distance apart, with wood lagging or boards placed between the soldier piles to hold the earth back. SEA recommended that the system be designed to a lateral earth retention criteria of 40H and that the construction should use two tiers of tiebaeks to provide support for the system and to provide an underpinning for the Sears Building. 3 It was recommended that these tiebaeks be installed at a maximum angle of 30 degrees and that the anchors for these tiebaeks penetrate the gravelly sand stratum rather than the soft clay layer below Pennsylvania Avenue. This was for a maximum height of excavation of twenty-six feet.

After this report was completed, plans for the Project changed when the building line was set back an additional twenty-five feet from the Brady Building. Due to this setback, Daly requested that SEA provide additional soils and geotechnical reports. In response, on November 16, 1983 SEA submitted an Amendment No. 1 to its previous report. The “Sheeting and Shoring” section recommended that steel sheet piling be installed for the wall of the excavation closest to the Sears Building. This steel sheeting would have eight foot of toe in below the new foundation level. Steel sheet piling consists of either Z or U shaped steel sheets which are driven into the ground with a pile driver. The sheets have an interlocking joint between them and as they are driven into the ground the sheets lock together. This minimizes or prevents clay or water from seeping through. In this amended report, SEA also recommended that tiebaeks as outlined in the original report should be used.

OMNI did not perform the sheeting and shoring design or installation but solicited bids from subcontractors. 4 On March 23, 1984, Schnabel submitted a bid proposal for the design and construction of the sheeting and shoring system for the Project. OMNI provided Schnabel with the documents relating to the contract with Westminster, including the SEA reports, but as was its practice it did not require a design in accordance with these reports. Schnabel proposed a system employing steel H-beams and wood lagging on all sides with one tier of tiebaeks, and a lateral earth retention of 30H.

*422 Schnabel’s bid was accepted by OMNI and on May 29, 1984, OMNI entered into a subcontract agreement with Schnabel for a sheeting and shoring system based on Schnabel’s bid proposal. OMNI also entered into subcontract agreements .with Hutchinson Brothers Excavating Company, Inc. for excavation and Division Two, Inc. for dewatering.

Sears was also provided with information regarding the use of a wood lagging system nearest to the Sears Building. Sears hired its own engineering consultants to evaluate Schnabel’s design. Sears’ consulting engineers, Skidmore, Owings & Merrill (“Skid-more”), brought in STS Consultants, Ltd. (“STS”) who completed a separate evaluation of the system designed by Schnabel. The report prepared by STS observed that the proposed system did not agree with the report of the geotechnical engineer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beacon Bowl, Inc. v. Wisconsin Electric Power Co.
501 N.W.2d 788 (Wisconsin Supreme Court, 1993)
Meek v. Shepard
484 A.2d 579 (District of Columbia Court of Appeals, 1984)
Psychiatric Institute of Washington v. Allen
509 A.2d 619 (District of Columbia Court of Appeals, 1986)
Morrison v. MacNamara
407 A.2d 555 (District of Columbia Court of Appeals, 1979)
Bell v. Jones
523 A.2d 982 (District of Columbia Court of Appeals, 1987)
District of Columbia v. Peters
527 A.2d 1269 (District of Columbia Court of Appeals, 1987)
Sanders v. Wright
642 A.2d 847 (District of Columbia Court of Appeals, 1994)
Toy v. District of Columbia
549 A.2d 1 (District of Columbia Court of Appeals, 1988)
District of Columbia v. Watkins
684 A.2d 395 (District of Columbia Court of Appeals, 1996)
Link Aviation, Inc. v. Downs
325 F.2d 613 (D.C. Circuit, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
992 F. Supp. 419, 1997 U.S. Dist. LEXIS 21591, 1997 WL 829418, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harbor-insurance-v-schnabel-foundation-co-dcd-1997.