Harbert International Establishment v. Power Shipping, Etc., New York Navigation Company, Inc.

635 F.2d 370, 1981 U.S. App. LEXIS 20692
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 26, 1981
Docket79-2156 to 79-2161
StatusPublished
Cited by12 cases

This text of 635 F.2d 370 (Harbert International Establishment v. Power Shipping, Etc., New York Navigation Company, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harbert International Establishment v. Power Shipping, Etc., New York Navigation Company, Inc., 635 F.2d 370, 1981 U.S. App. LEXIS 20692 (5th Cir. 1981).

Opinion

GODBOLD, Circuit Judge:

New York Navigation (N.Y.Nav.) appeals from a judgment awarding nearly $375,000 to appellee Harbert-Howard Companies (Harbert) for damages incurred when six shipments of ductile iron pipe were unloaded from vessels at Abu Dhabi, United Arab Emirates.

In 1975 Harbert entered into a contract with the Water and Electricity Department (WED) of Abu Dhabi for the installation of more than 70 miles of pressurized water pipeline. For this project Harbert purchased approximately 18,000 sections of ductile iron pipe from American Cast Iron Pipe Company (ACIPCO) located in Birmingham, Alabama. ACIPCO agreed to arrange transport of the pipe from Birmingham to Mobile, Alabama, and as Harbert’s agent, contracted with Power Shipping Corporation for shipment from Mobile to Abu Dhabi. N.Y.Nav. guaranteed Power Shipping’s performance and chartered the six vessels involved in this case; it also hired the loading and discharging stevedores, while Harbert arranged transport of the pipes from the docks to storeyards in Abu Dhabi.

Both parties agree that only undamaged pipes were loaded in Mobile, and each of the vessels issued a clean bill of lading. The voyages were uneventful. At Abu Dhabi, Masaood Shipping Company (hired by appellant) unloaded the pipes onto trucks supplied by A1 Fahad Transportation Company (hired by appellee). Tally clerks employed *372 by Masaood counted the pipes as they were unloaded and noted some damage. 1 Har-bert officials present at various times during discharge observed pipes being damaged and complained to Masaood’s superintendent that the clerks were not recording all of the damage. But Masaood did not modify either the manner of unloading or the manner of tallying damage.

As the pipes were unloaded they traveled by truck to storeyards. The ride was smooth. Approximately a dozen of the more than 18,000 pipes fell off the trucks en route, but only one was damaged. The pipes were removed from the trucks and stacked in the storeyards by crane. No damage was observed during the truck unloading or in subsequent handling of the pipe in the storeyards. As required by its contract with WED, Harbert officials conducted a cursory inspection of the pipe within two days after each vessel was unloaded, noting those pieces that were damaged so severely that they had to be reordered. The results were compiled in Receiving Cum Damage reports. 2

As the pipes were removed from the storeyards to be laid it became apparent that some were damaged and had to be repaired before they could be used. The damage consisted primarily of dents in the spigot ends of the pipes and cracks in the cement linings at the spigot ends. Harbert set up a mass production repair operation to saw off the damaged ends of the pipes and repair the cement linings; 1,536 pipes were repaired in this manner.

Harbert sued N.Y.Nav., Power Shipping, and the six vessels, alleging that the pipe was delivered to the vessels in good condition and discharged in damaged condition. N.Y.Nav. assumed the defense for Power Shipping and the shipowners. After a non-jury trial the district court found for Har-bert. The suit was governed by the Carriage of Goods by Sea Act, 46 U.S.C. § 1300 et seq. Harbert contended that the damage occurred when Masaood unloaded the pipes at Abu Dhabi and that it far exceeded that recorded by Masaood’s tally clerks. N.Y. Nav. conceded that the damage recorded by Masaood’s tally clerks occurred at discharge but maintained that damages exceeding that amount occurred after discharge during transport by Al Fahad’s trucks and subsequent handling in the storeyards. It also presented evidence that, on this appeal, it contends showed that inherent defects in the cement lining of the pipes contributed to damages incurred during discharge. 3 The district judge found that 90% of the damage was caused by Masaood’s practices in unloading the pipes from the vessels.

I. LACK OF NOTICE AS PRIMA FACIE EVIDENCE OF GOOD DELIVERY.

COGSA provides that failure by the shipper to give notice of damage to the carrier at or near the time of delivery is prima facie evidence of delivery of the cargo as described in the bill of lading, 46 U.S.C. § 1303(6). 4 Harbert did not satisfy the no *373 tice requirements of this provision, but the district judge nevertheless concluded that Harbert had overcome its burden:

This statute does no more than to raise a presumption of delivery to the consignee in good order and condition, in the absence of proof to the contrary. However, once plaintiffs came forward with sufficient evidence to suggest that the cargo was damaged prior to delivery, this presumption evaporates and has no further effect on the Court’s weighing of the evidence as to the amount of damage at the time of delivery.

N.Y.Nav. argues that the district judge applied an erroneous legal standard by failing to give continual weight to the statutory “presumption” when considering evidence relating to the amount of damage. The argument is based on the assumption that where, as here, the carrier conducts tallies at discharge and is willing to admit the amount of damage those tallies reveal, the shipper’s lack of notice under § 1303(6) is prima facie evidence that the cargo was damaged only in the amount listed on the tally sheets. While this theory might serve the goal of encouraging shippers to give prompt notice, the language of the statute will not support it.

Under § 1303(6), failure to notify the carrier of damage is prima facie evidence that the goods were delivered in the same condition described in the bill of lading, see Associated Metals & Mineral Corp. v. M/V Rupert De Larrinaga, 581 F.2d 100, 101 (5th Cir. 1978); Miami Structural Iron Corp. v. Cie Nationale Belge De I.M., 224 F.2d 566, 569 (5th Cir. 1955). Prima facie evidence under § 1303(6) is thus evidence negating the fact of damage prior to discharge, not the amount of damage. Since the pipes were loaded in Mobile with a clean bill of lading, Harbert’s failure to give notice constituted prima facie evidence that they were delivered to Abu Dhabi in undamaged condition.

When sufficient evidence indicating that the cargo was damaged prior to discharge is introduced, the prima facie evidence under § 1303(6) is accorded no special weight beyond that given other evidence concerning where the damage occurred:

[Section 1303(6)] is conclusive only where there is no other evidence on the disputed point. Once the plaintiffs come forward with sufficient evidence to suggest that the cargo was contaminated before discharge, a fact issue is created, which the Court must resolve.

Socony Mobil Oil Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
635 F.2d 370, 1981 U.S. App. LEXIS 20692, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harbert-international-establishment-v-power-shipping-etc-new-york-ca5-1981.