Harber Bros. v. Moffat Cycle Co.

37 N.E. 676, 151 Ill. 84
CourtIllinois Supreme Court
DecidedJune 16, 1894
StatusPublished
Cited by36 cases

This text of 37 N.E. 676 (Harber Bros. v. Moffat Cycle Co.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harber Bros. v. Moffat Cycle Co., 37 N.E. 676, 151 Ill. 84 (Ill. 1894).

Opinion

Per Curiam:

This was a suit in assumpsit, brought by the Harber Brothers Company against the Moffat Cycle Company, to recover damages for breaches of a contract for the sale and delivery of personal property. The defendant pleaded nonassumpsit and set-off, and on trial before the court, without a jury, the issues were found for the defendant, and its damages under its plea of set-off were assessed at $1,059.26, and for that sum and costs the defendant had judgment. On appeal to the Appellate Court the judgment was affirmed, and by a further appeal the judgment is now brought to this court. In deciding the case, the Appellate Court delivered the following opinion :

“Pleasants, J.:
“In this case the facts are substantially agreed on, and the question on the record is single, and purely one of law.
“Appellee was an Illinois corporation, engaged in the manufacture of bicycles at Chicago, and appellant, also an Illinois corporation engaged in selling bicycles and other machines at Bloomington.
“On December 8, 1891, the parties entered into a written contract, of which it is unnecessary to say more than that by it appellee agreed, among other things, to deliver to appellant on the cars at Chicago 300 Moffatt Safety bicycles, of 1892 pattern—shipments to commence in January then next, and made thereafter in quantities and at times as appellant should specify, and paid for by-his acceptances at thirty days.
“Appellant ordered one machine the day before the contract was made, and on the 31st of the same month, 24; from time to time, in February, 1892, 46; in March, 113; in April, 67, and in May, 19—in all, 270. Most of these orders were for single machines, to be shipped to different points directly to parties respectively to whom appellant had made sales; some for two or three, and the few for large numbers, to appellant at Bloomington.
‘ ‘In partial compliance with these orders, appellee shipped in February, 2; in March, 9; in April, 19; in May, 56; in June, 16, and in July, 3—in all, 105.
“The evidence showed, and it was admitted, that appellant did not give its acceptance for all of those shipped, but from the time the first was received until this suit was brought, was constantly in arrears for more or less of them. This arrearage was purposely and persistently withheld, on the ground that appellee was first in default, and that the damage to appellant, by reason of the delays and shortness of shipments, always exceeded it. The correspondence between the parties, which is in the record, consists largely of mutual complaints for disregard of their contract obligations. Appellant was insisting on prompt and full compliance with its orders; and appellee, claiming it was doing all it could, and increasing its facilities for doing more than before in that direction, and insisting on prompt and full acceptances for what were shipped. Neither justified or attempted to excuse its own' delinquency on the ground of the other’s until as hereinafter stated. As early as March 15th, appellant wrote to appellee that they were receiving countermands from their customers, because of the failure to ship machines to them as ordered, and saying: ‘Machines we must have or sustain a loss, and you know what that means.’ But the first notice taken of appellee’s complaint of neglect to send acceptances that we find in the correspondence abstracted, is in appellant’s letter of April 19th, in answer to appellee’s of the 12th, enclosing draft, dated March 29th, for acceptance to cover shipments up to that date, for $675.04, in wrhich it says: ‘You can hardly expect us to take up the matter of your account and make settlement, of it in the condition that things are now. We want some very satisfactory proof that you can take care of us during and at the close of the season if we do so.’
“To this letter appellee replied on the 21st, admitting that it had not been able to perform as promised in regard to shipments, but expressing surprise, for reasons stated, at the position taken by appellant, and saying: ‘We must insist that you let us have your acceptance by return post, and we in turn will do our best towards filling your orders.’
“On the 26th, appellant, reviewing the course of their dealings, wrote: ‘Now, if you expect us to sign acceptances promptly, then you must expect to do something for us. If you do not show a disposition immediately to give us goods, and in large quantities, this letter is but a forerunner of what you will receive.’ To which appellee replied on the 27th: - ‘I am in receipt of your favor of the 26th, which covers a good deal of ground that we have already gone over, and which convinces me further of the issue your company is leading up to. We shall hold further shipments until we receive an acceptance or cash for all the wheels we have shipped you up to date.’
‘ ‘Notwithstanding further acceptances, but not in full, and further orders, filled only in part and with delay, these mutual complaints and demands continued until July 18th, when appellee, by letter of that date, among other things, notified appellant, that unless payment should be made for the goods shipped and not paid for, and the other matters of difference arranged within five days, it would terminate appellant’s agency for the sale of its wheels in the territory referred to, and fill orders from such territory itself. On the 23d, appellant, in reply to one from appellee on the 21st, not abstracted, wrote, among other things: ‘ * *
* We do not intend to pay you another cent until there is an adjustment of our claim for damages;’ and on the 27th brought this suit.
“It was in assumpsit, on four special counts upon the contract, with the common counts added. The cause of action -set forth in each of the special counts was defendant’s breach of the written contract by unreasonable delay in the shipment of the 105 bicycles shipped, and failure to ship the other 165 ordered. The third and fourth, added by leave of the court, alleged special damages, by reason of defendant’s alleged knowledge that plaintiff bought to resell, and that its profits would be $50 upon each machine resold, and that plaintiff had incurred and would incur a large expense in preparing to resell and in reselling.
“Defendant pleaded the general issue, and set-off in the common counts, and two other pleas, setting off damages by failure of defendant to give acceptances, to which demurrers were sustained. But it was afterwards stipulated ‘that all evidence that would be competent under any issue well pleaded should be considered as though the declaration or pleas or replications were filed, making such issues or averments.’
“The cause was tried by the court without a jury. Appellant admitted that it had withheld acceptances and was in arrears for the 105 wheels actually shipped and received, to the amount of $1,647.96, as a partial indemnity against the damages it claimed to have suffered, but showed in reduction of this sum an account of $588.70 for repairs of defects in them. The court allowed this account, and rendered judgment for the defendant for the difference, $1,059.26, disallowing plaintiff’s claim for damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reno Sales Co., Inc. v. Pritchard Industries, Inc
178 F.2d 279 (Seventh Circuit, 1950)
Lander v. Samuel Heller Leather Co.
50 N.E.2d 962 (Massachusetts Supreme Judicial Court, 1943)
Atlas Coal & Coke Co. v. Kentucky River Coal Mining Co.
253 Ill. App. 475 (Appellate Court of Illinois, 1929)
Ava Blue Grass Creamery Co. v. Sussman Bros.
243 Ill. App. 483 (Appellate Court of Illinois, 1927)
United Boiler Heating & Foundry Co. v. Ackermann-Quigley Printing Co.
236 Ill. App. 111 (Appellate Court of Illinois, 1925)
Worth-Huskey Coal Co. v. Columbia Malting Co.
230 Ill. App. 165 (Appellate Court of Illinois, 1923)
Burge Machine Works v. Mandarin Inn
225 Ill. App. 358 (Appellate Court of Illinois, 1922)
Armstrong Paint & Varnish Works v. Continental Can Co.
220 Ill. App. 90 (Appellate Court of Illinois, 1920)
Black Diamond Fuel Co. v. Illinois Fuel & Phosphate Co.
219 Ill. App. 150 (Appellate Court of Illinois, 1920)
Goodyear Tire & Rubber Co. v. Vulcanized Products Co.
126 N.E. 710 (New York Court of Appeals, 1920)
Consumers Mutual Oil Co. v. Western Petroleum Co.
216 Ill. App. 382 (Appellate Court of Illinois, 1920)
Reskie, Kirshbaum & Co. v. Walzer
213 Ill. App. 305 (Appellate Court of Illinois, 1919)
United Iron Works v. Wagner
167 P. 1107 (Washington Supreme Court, 1917)
Chicago Washed Coal Co. v. Whitsett
116 N.E. 115 (Illinois Supreme Court, 1917)
Staver Carriage Co. v. American & British Manufacturing Co.
188 Ill. App. 634 (Appellate Court of Illinois, 1914)
Maney Milling Co. v. Baker-Wignall & Co.
186 Ill. App. 390 (Appellate Court of Illinois, 1914)
Grier v. McClory
172 Ill. App. 175 (Appellate Court of Illinois, 1912)
Southern Re-distilling & Rectifying Co. v. Frank W. Thurston & Co.
172 Ill. App. 55 (Appellate Court of Illinois, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
37 N.E. 676, 151 Ill. 84, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harber-bros-v-moffat-cycle-co-ill-1894.