Hanssel v. P. Tomasetti Contracting Corp.

27 N.E.2d 977, 283 N.Y. 164, 1940 N.Y. LEXIS 929
CourtNew York Court of Appeals
DecidedMay 28, 1940
StatusPublished
Cited by4 cases

This text of 27 N.E.2d 977 (Hanssel v. P. Tomasetti Contracting Corp.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hanssel v. P. Tomasetti Contracting Corp., 27 N.E.2d 977, 283 N.Y. 164, 1940 N.Y. LEXIS 929 (N.Y. 1940).

Opinion

Conway, J.

On May 10,1937, P. Tomasetti Contracting Corporation (hereinafter called Tomasetti) entered into a contract with Buffalo Sewer Authority (hereinafter called Sewer Authority) for the construction of certain portions of the sewer system in the city of Buffalo. Included in the contract was division X, item X-l, covering the construction of the Cornelius creek intercepting and overflow chamber and connection. The agreed price for that portion of the work was $60,000. The contract covered other items also but with them we are not concerned on this appeal. Nor are we concerned with the cause of action of plaintiff against Sewer Authority. The trial court dismissed the complaint against the Sewer Authority and plaintiff appealed to the Appellate Division from that decision and judgment. After the affirmance by the Appellate Division, no further appeal was taken by plaintiff to this court.

The contract between Tomasetti and Sewer Authority provided, in the event that extra work was required:

The amount of compensation to be paid to the Contractor for any extra work as so ordered shall be determined as follows:
“ 1. By such applicable unit prices, if any, as are set forth in the contract, or
“ 2. E no such unit prices are so set forth, then by a lump sum mutually agreed upon by the Authority, and the Contractor; or
‘‘ 3. If no such unit prices are so set forth and if the parties cannot agree upon a lump sum, then by the actual net cost in money to the Contractor of the materials and of the wages of applied labor (including premium for workmen’s compensation insurance) required for such extra work, plus such rental for plant and equipment (other than small *168 tools) required and approved for such extra work, plus fifteen per cent (15%) as compensation, for all other items of profit and cost or expense, including administration, overhead, superintendence, insurance (other than workmen’s compensation insurance), materials used in temporary structures, allowances made by the Contractor to the subcontractors, additional premium upon the performance bond of the Contractor and the use of small tools.”

On June 22, 1937, Tomasetti entered into a contract with the plaintiff, Frank G. Hanssel, doing business as the Frank G. Hanssel Company (hereinafter referred to as Hanssel). By the terms of that contract Hanssel agreed to furnish the labor, equipment and material called for in doing the work in division X, item X-l, for the agreed price of $49,145. Tomasetti did not reserve to itself the doing of any work under its contract with Sewer Authority. Hanssel was to do all of it.

Tomasetti’s contract with Hanssel provided:

Twelfth. It is mutually agreed that the intent of this agreement is that the respective rights and obligations of the parties hereto shall, except as otherwise provided herein, be precisely the same as the respective rights and obligations of the contractor and the Buffalo Sewer Authority with respect to items X-l and X-5 of Division X of the contractor’s agreement with the Buffalo Sewer Authority, dated, as aforesaid, May 10,1937.” (Italics added.)

Among those matters in the contract between Tomasetti and Hanssel which were “ otherwise provided herein ” was extra work. As to that, the contract provided:

“ Third. The amount to be paid to the subcontractor for items not provided in the contractor’s contract with the Buffalo Sewer Authority such as subsequent items or extra work orders and for which no unit or lump sum price is provided, shall be agreed upon between the parties hereto in advance of the work being done, subject, however, to the approval of the Buffalo Sewer Authority, should the same be required.” (Italics added.)

*169 Hanssel was approved as subcontractor by Sewer Authority and made ready to do the work. Then an unfortunate situation developed. On July 23, 1937, Sewer Authority wrote to Tomasetti advising that it had come to its attention that there were four lines of sixty-inch pipes in the bed of Cornelius creek. Sewer Authority directed that the excavation be carried to a point sufficient to expose the pipes so that they might be examined and stated that the payment therefor would be under item X-8, additional earth excavation.” That excavation was made and paid for as stated and there is no dispute with reference thereto. Hanssel testified that he had his equipment ready about September 1st and began driving piles about September 8th. The old pipes were found to be three or more feet below the lowest point to be excavated. The increased depth necessitated the use of longer piles. Under the pipes was found timber about which Hanssel had never been told. After the pipes were exposed, plaintiff notified Sewer Authority and its engineers made an inspection about November 10th or 11th. Then followed conflicting orders from the engineers of Sewer Authority. First Hanssel was told to fill the excavation with washed crushed stone and to build bulkheads so that the stone would not slide. Then Hanssel was told to take out the crushed stone. That was at a time when Hanssel was ready to pour concrete upon it. After the removal of the crushed stone, work was suspended on the orders of the engineers of Sewer Authority and nothing was done for some days. Then Hanssel was directed to drive wooden piles between the old pipes. Upon the insistence of the engineers Hanssel ordered the piles although he told the engineers there was no room between the pipes to drive them. The engineers of Sewer Authority were depending upon a blueprint which was inaccurate. Then Hanssel was told to take out the pipes, which would necessitate breaking them up. Hanssel had been directed to purchase the washed crushed stone on November 11th and began to break up the old pipes on November 22nd. On November 18th Hanssel wrote a letter to Tomasetti. This letter *170 and those following determine whether or not there was any contract between Hanssel and Tomasetti for the extra work done by Hanssel on a cost plus basis and whether there is any right of recovery in this action. I shall, therefore, quote in part the correspondence.

The letter of November 18, 1937, detailed at some length the difficulties under which Hanssel had been laboring. It then continued:

“You realize that this delay has seriously hindered us from completing our contract and caused us a great additional expense.

“ In view of the above, we wish to state before proceeding further with this contract, we demand that we receive from you, officially in writing, instructions to proceed on a definite plan with the understanding that we are to be reimbursed for all additional expense we have been put to for proceeding thus far, on the indefinite plans, plus a reasonable profit and an extension of time for every day delayed; also an extension of time for any additional work we are authorized to perform that was not shown on the original drawings or specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Talco Capital Corp. v. United States Rubber Co.
32 A.D.2d 547 (Appellate Division of the Supreme Court of New York, 1969)
Cerp Construction Co. v. J. J. Cleary, Inc.
59 Misc. 2d 489 (New York Supreme Court, 1968)
Terminal Const. Corp. v. Bergen, Etc., Authority
112 A.2d 762 (New Jersey Superior Court App Division, 1954)
Hanssel v. P. Tomasetti Contracting Corporation
28 N.E.2d 415 (New York Court of Appeals, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
27 N.E.2d 977, 283 N.Y. 164, 1940 N.Y. LEXIS 929, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hanssel-v-p-tomasetti-contracting-corp-ny-1940.