Hansen v. Virgin Islands Water & Power Authority

56 V.I. 25
CourtSuperior Court of The Virgin Islands
DecidedJanuary 12, 2012
DocketSX-11-CV-364
StatusPublished

This text of 56 V.I. 25 (Hansen v. Virgin Islands Water & Power Authority) is published on Counsel Stack Legal Research, covering Superior Court of The Virgin Islands primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hansen v. Virgin Islands Water & Power Authority, 56 V.I. 25 (visuper 2012).

Opinion

WILLOCKS, Judge

MEMORANDUM OPINION

(January 12, 2012)

THIS MATTER is before the Court on Petitioner Alicia “Chucky” Hansen’s (hereinafter Petitioner) Petition of Appeal, filed August 10, 2011.1 Petitioner appeals the denial by the Virgin Islands Public Service Commission (hereinafter the PSC or Commission) of her Petition for Reconsideration of Order 38/2011. For the reasons stated below, the Court [28]*28shall dismiss the following issues on appeal: (1) The Virgin Islands Water and Power Authority, (hereinafter WAPA) has failed to comply with the legislative mandate that required it to have conducted a public hearing for comment within a reasonable time after the creation of the LEAC, and (2) WAPA’s Petition for increase should not be based on the fluctuation of oil prices on the market and the refinancing of its $40 million loan; but, rather, WAPA’s request should have been based on the below market prices provided by HOVENSA, which is not indicated in its petition for an increase (based on the Third'Extension and Amended Agreement). The Court shall remand the third issue — whether the PSC had insufficient information to consider the interest payments on WAPA’s loans as a factor to increase the LEAC — to the Commission for an appropriate Finding.

FACTS AND PROCEDURAL BACKGROUND

On June 24, 2011, the PSC issued Order No. 38/2011 in Docket No. 289, approving the increase of the Levelized Energy Adjustment Clause (hereinafter referred to as the LEAC) rates for the period of July 1 through September 30, 2011. In 1989, the PSC — in an attempt to address the increases and shifts in oil prices — opened docket 289, which created the LEAC. The LEAC is a fuel cost recovery method employed by WAPA to counter the shifts in the prices of crude oil. Each customer is billed for the cost of fuel required to generate electricity and water according to their actual consumption. The level of the LEAC is adjusted on a quarterly basis to allow for quick recovery of fuel cost if the price of fuel rises too high or to give credits to the public in the event fuel prices are lower than projected. The Legislature of the U.S. Virgin Islands has never authorized a LEAC charge; and, as such, there is no legislation governing this rate charge. The configuration of rates such as the LEAC is a task apportioned solely to the PSC.2

On June 29, 2011, Petitioner filed a timely “Request Stay and Reconsideration for the Order Approving LEAC Rates for the Period of July 1 Through September 30, 2011.”3 On July 1, 2011, the PSC issued [29]*29an amended agenda, setting a meeting date for July 12, 2011 at 5:00 p.m. Included on the agenda was Petitioner’s Request Stay and Reconsideration for the Order Approving LEAC Rates for the Period of July 1 Through September 30, 2011. On July 7, 2011, WAPA filed an Objection and an Opposition thereto. Neither Petitioner nor any of her representatives appeared at the July 12, 2011 meeting. The PSC heard testimony from Hugo Hodge, Director of WAPA, on the increase of the LEAC. On July 13,2011, Attorney George Hodge filed a letter to the PSC on Petitioner’s behalf requesting that the hearing be rescheduled because of the untimely death of Petitioner’s brother on July 11, 2011. In the correspondence to the PSC, Attorney Hodge also noted his appearance as counsel for Petitioner. The PSC denied Petitioner’s request for Reconsideration by Order 39/2011 dated July 15, 2011. Petitioner’s request for a rescheduling of the hearing was also denied. Petitioner filed a timely Petition of Appeal with the Court on August 10,2011. Thereafter, an Amended Petition of Appeal was filed on August 30, 2011, requesting that the Court sustain Petitioner’s Appeal and to vacate the July 15, 2011 Order by the PSC.4

DISCUSSION

Standard of Review

This Court has jurisdiction to hear this appeal pursuant to Title 30 V.I.C. § 34. The Court is cognizant that the Legislature in the establishment of the PSC has by statute required that the courts must view the actions of the PSC as omnia praesumuntur legitime facta donee probetur in contrarium (all things are presumed to be lawfully done until it is shown to be in the reverse). This is adverted to by Title 30 V.I.C. § 35 which limits the Courts’ powers on appeal from an order or decision of the PSC. Title 30 V.I.C. § 35 provides that:

[30]*30In the determination of any appeal from an order or decision of the Commission the review by the court shall be limited to questions of law, including constitutional questions; and the findings of fact by the Commission shall be conclusive unless it shall appear that such findings of the Commission are arbitrary, capricious or procured through fraud.

According to Title 30 V.I.C. § 33, the Court is limited to the issues raised in the Petition for Reconsideration. These issues are restricted to the Court’s determination as to whether the PSC acted in an arbitrary or capricious manner or whether the decision on the issues was based through fraud. The Court’s review is also restricted to questions of law, including constitutional questions.

The issues raised by Petitioner are of such that this Court does not have the authority or the power to be the slayer of the LEAC as was foretold. The issue raised by Petitioner in her Petition for Reconsideration was three-fold.

WAPA failed to comply with the legislative mandate that required it to conduct a public hearing for comment within a reasonable time after the creation of the LEAC.
The Virgin Islands Water and Power Authority’s (WAPA) petition for an increase should not be based on the fluctuation of oil prices on the market and the refinancing of its $40 million loan. But, rather, WAPA’s request should have been based on the below market prices provided by HOVENSA, which is not indicated in its petition for an increase (based on the Third Extension and Amended Agreement).
The PSC had insufficient information to consider the interest payments on WAPA’s loan as a factor to increase the LEAC.5

I. WAPA HAS FAILED TO COMPLY WITH THE LEGISLATIVE MANDATE THAT REQUIRED IT TO HAVE CONDUCTED A PUBLIC HEARING FOR COMMENT WITHIN A REASONABLE TIME AFTER THE CREATION OF THE LEAC

Petitioner argues that “WAPA has failed to comply with the Legislative mandate that required it to have conducted a public hearing [31]*31for comment within a reasonable time after the creation of the LEAC” pursuant to Title 30 V.I.C. § 105(12). Petitioner also argues that the creation of the LEAC brought changes to the general rate structure for water and power, and therefore required a public hearing pursuant to Title 30 V.I.C. § 105(12).6 Petitioner’s arguments are flawed. It has been firmly established that the Virgin Islands Public Services Commission (PSC) has power over the Virgin Islands Water and Power Authority (WAPA) with respect to rate setting. The Virgin Islands Legislature created WAPA as a “public corporation and autonomous governmental instrumentality” in 1964.7 The Legislature also created a governing board for WAPA for the purpose of developing and providing water and electric power services for the people of the Virgin Islands.8 Ab initio,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Securities & Exchange Commission v. Chenery Corp.
318 U.S. 80 (Supreme Court, 1943)
Dickinson v. Zurko
527 U.S. 150 (Supreme Court, 1999)
Aggie Investments GP v. Public Service Commission
470 N.W.2d 805 (North Dakota Supreme Court, 1991)
Dickinson v. Zurko
527 U.S. 150 (Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
56 V.I. 25, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hansen-v-virgin-islands-water-power-authority-visuper-2012.