This text of 6 P.R. Fed. 394 (Hansen v. Nine Hundred & Ninety-Eight Tons of Coal) is published on Counsel Stack Legal Research, covering District Court, D. Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hansen v. Nine Hundred & Ninety-Eight Tons of Coal, 6 P.R. Fed. 394 (prd 1913).

Opinion

HamilxoN, Judge,

delivered tbe following opinion:

The libel in rem filed January 15, 1913, sets up that the ■owners of the Tillie Baker on November 14, 1912, chartered to the Consolidation Coal Company the Tillie Baker for a voy.age from Philadelphia to San Juan. The charter party annexed to the libel calls for freight at the rate of $2.40 per ton •of 2,240 pounds of coal, which was to constitute the cargo. The charterers were to pay the vessel’s Porto Bican port charges, freight was payable on proper delivery of cargo, and vessel to be free of all wharfage and lighterage charges. The vessel [396]*396was to discharge at San Juan 100 tons per day, Sundays and legal holidays excepted, the lay days commencing from the time the captain reports himself ready and prepared to discharge cargo. For every day’s detention by default of the Consolidation Coal Company, of agent, $58 day by day should be paid by said Consolidation Coal Company, or agent, to the parties of the first part. The cargo was to be delivered alongside within reach of the vessel’s tackle, vessel to haul to wharf designated by charterers to discharge cargo, provided there was sufficient water, and if moved again charterers to pay towage.

So far the charter party. The master, H. T. Hansen, issued five bills of lading on November 22, all of one tenor, for 998 tons of Somerset coal in the hold, which he promised to deliver in good order unto the “American Railroad Company of Porto Rico for the Porto Rico Brewing Company, San Juan, Porto Rico, or to his or their assigns, he or they paying freight on delivery of same.”

The vessel accomplished her voyage safely, and arrived at San Juan on December U, 1912. The testimony seems to show that the captain reported to the consignee the next day, saying that he was ready. There was some testimony that the piston rod of the gasolene winch was out of order, but it was repaired at once, and in any event the captain claims he could borrow and use a hand winch. The consignee and the captain went to see the captain of the port, and the vessel was given a berth at what was called the Quartermaster Dock, at the stern of a barkentine already there, named the Minnie Swan. The Baker went in and dropped anchor on the 18th, and the stern of the vessel was hauled in early on the 19th. The result was that she had to lie with her bow on the outside of the barken-[397]*397“tine, and it was found impracticable to turn the vessel around. As the Minnie Swan was'to clear in a couple of days, the captain agreed to wait that length of time, so as to get the full berth. Instead of this, however, a five-master came in, with coal for the consignee, and the consignee then had the Baker moved to a small wharf called Under the Hopper. There she actually began to discharge the coal on December 23 at 1 o’clock p. m. This wharf was 14 feet wide, and there could be used but one cart at a time, for lack of room for two to pass.

On the 4th of January the captain wrote the consignee that the Tillie Baker was ready and prepared to discharge cargo on the 21st of December, and that at the rate of 100 tons per day the time for discharging expired on the day the letter was written. And he, therefore, claims demurrage from Monday, January 6th, according to the charter party. The unloading ■was actually finished on January 9th at 3:30 p. M. Although he requested it, the captain was not given his receipt for the ■cargo until January 18th. In the meantime the captain had filed this libel on the 15th, seeking to recover freight and de-murrage.

1. This is a suit in rem, in which a vessel seeks to recover freight and demurrage from the cargo after discharge. ' It is defended by the charterer, by the nominal, and also by the real, consignee. The first aspect of the case which presents itself relates only to the charter party, for it concerns the discharge of the cargo, which the vessel was, under the charter party, bound to effect at 100 tons per day. As to this, the question is as to delays due to the vessel, and delays due to the nature of the wharf, which the charterer was to provide. At present, therefore, the question is not as to delivery of the coal to the [398]*398consignees under tbe bill of lading, but the discharge of the vessel in accordance with the charter party. 275 Tons of Mineral Phosphates, 9 Fed. 209.

2. Looking at the terms of the charter party, which was the contract between the Consolidation Coal Company, who furnished the cargo, and the owners of the bark Tillie Baker, we find that the Consolidation Coal Company were to pay $2.40 freight per ton delivered and Porto Rican port charges. Furthermore, that for discharging at San Juan 100 tons per day were allowed, Sundays and legal holidays excepted. That the lay days commenced from the time the captain reported himself ready and prepared to discharge, and that for each day’s detention by default of the Consolidation Coal Company demur-rage was to be paid at the rate of $58. The vessel was to be hauled to the wharf designated by the Consolidation Coal Company, and delivery of the cargo was to be alongside within reach of vessel’s tackles.

Freight need not be further considered except in the matter of costs, because settled after the filing of the libel; but there is a great difference between the parties as to demurrage. At 100 tons per day, the vessel should finish in ten lay days, but, commencing on the 23d of December, Christmas, New Near’s and two Sundays intervened. The earliest that she could have finished, therefore, under the charter, would have been fourteen days.

3. It is quite possible that the vessel was ready on December 21st, after she had been hauled to the Quartermaster Dock. The captain’s, waiver of two days at that dock in order to let the Minnie Swan get out of the way might not have been binding when another vessel was put in the place of the Minnie [399]*399Swan; but at all events the captain later reaffirmed his waiver, and, as he controls the vessel, no demurrage will be allowed as to this period. Davis v. Wallace, 3 Cliff. 123, Fed. Cas. No. 3,657.

4. The evidence seems to show that the vessel was then delayed by putting her at the dock called Under the Hopper, where the facilities did not permit the unloading of the 100 tons a day called for by the charter party, and which it seems the vessel could discharge. Only one hatch could be used at a time, the wharf was so small that carts could not pass each other, and these were so small that they had to be built up with planks, which resulted in breakdowns and loss of some coal. The Glenfinlas, 1 C. C. A. 85, 1 U. S. App. 22, 48 Fed. 758. It is true that the gasolene winch of the vessel did not always work smoothly. There was delay every day or two, lasting from a few minutes to an hour, but not more than one day can be attributed to this cause, and the rest was due to insufficiency of the dock. It was, under the charter, the duty of the charterer or his agent to furnish a proper wharf or dock. Lindsay v. Cusimano, 12 Fed. 504. The result is therefore that the delay from the 7th of January to the 9th, that is three days, should be charged as demurrage.

5. The case is complicated by the fact that, although it is in the first instance one between the vessel and the charterers, the bills of lading were to be signed by the vessel, and this resulted in conferring rights upon the consignees for proper delivery of the cargo.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brittan v. Barnaby
62 U.S. 527 (Supreme Court, 1859)
The Kimball
70 U.S. 37 (Supreme Court, 1866)
Ostrander v. Brown & Stafford
15 Johns. 39 (New York Supreme Court, 1818)
Ray v. One Block of Marble
19 F. 525 (S.D. New York, 1884)
Lindsay, Gracie & Co. v. Cusimano
12 F. 504 (U.S. Circuit Court for the District of Eastern Louisiana, 1882)
The Oluf
19 F. 459 (U.S. Circuit Court for the District of Eastern Louisiana, 1883)
Davis v. Wallace
7 F. Cas. 182 (U.S. Circuit Court for the District of Massachusetts, 1868)
Sears v. Four Thousand Eight Hundred & Eighty-Five Bags of Linseed
21 F. Cas. 934 (U.S. Circuit Court for the District of Massachusetts, 1858)
Isham v. A Cargo of Pine Piles
46 F. 403 (S.D. New York, 1891)
Davis v. Cargo of Chalk
48 F. 758 (Second Circuit, 1891)
Compagnie du Boleo v. Scandinavia
49 F. 658 (N.D. California, 1892)
Whitman v. Vanderbilt
75 F. 422 (Second Circuit, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
6 P.R. Fed. 394, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hansen-v-nine-hundred-ninety-eight-tons-of-coal-prd-1913.