Hanover Insurance Company v. Dunbar Mechanical Contractors
Opinion
United States Court of Appeals For the Eighth Circuit
No. 19-2226
Hanover Insurance Company, a New Hampshire Corporation
lllllllllllllllllllllPlaintiff - Appellee
v.
Dunbar Mechanical Contractors, LLC, doing business as Dunbar Mechanical Contractors, Inc.
lllllllllllllllllllllDefendant - Appellant
Appeal from United States District Court for the Eastern District of Arkansas - Jonesboro
Submitted: January 16, 2020 Filed: July 9, 2020
Before COLLOTON, SHEPHERD, and ERICKSON, Circuit Judges.
SHEPHERD, Circuit Judge.
Dunbar Mechanical Contractors, LLC (Dunbar), a Service Disabled Veteran Owned Small Business (SDVOSB), was awarded an Army Corps of Engineers ditch and tributary project in Arkansas. Dunbar hired a subcontractor, Harding Enterprises LLC (Harding Enterprises), to work on this project. When Harding Enterprises
defaulted, Dunbar made a demand under the bond guaranteed by Hanover Insurance Company (Hanover). Hanover denied the claim on the basis that the subcontract agreement between Dunbar and Harding Enterprises violated federal law because it subcontracted over 85% of the work on the project to a non-qualifying entity. Hanover filed suit seeking a declaration that it had no obligations under the bond and seeking to have the bond rescinded based on illegality of the subcontract. The district court, converting Hanover’s motion for judgment on the pleadings into a motion for summary judgment, granted the motion, agreeing that the subcontract violated federal law. Dunbar appeals, arguing the district court erred in its determination that the subcontract agreement represented over 85% of the work on the project. Having jurisdiction under 28 U.S.C. § 1291, we reverse.
I.
In 2013, Dunbar bid on an Army Corps of Engineers contract for construction of a ditch and tributary project in Mississippi County, Arkansas. This project was a Service Disabled Veteran Set-Aside Project, which required a bidder to qualify as an SDVOSB to be eligible to receive the prime contract. On December 18, 2013, Dunbar was awarded the project, with the bid price of $2,047,455.74. The terms of the prime contract between Dunbar and the Army Corps of Engineers provided that Dunbar was responsible for:
furnishing all plant labor and materials necessary for but not limited to channel clearing and cleanout within Ditch 27 . . . , Pemiscot Bayou/ Ditch 36/Ditch37 . . . , and Ditch 33 . . . , seeding, mulching and environmental protection. This project also consists of establishment of turf within the right-of-way limits, including the berm, excavated material embankment, and anywhere above top bank that is denuded of grass due to construction activities.
R. Doc. 27-1, at 1.
On the same day that Dunbar was awarded the prime contract, it entered into a subcontract agreement with Harding Enterprises. Under the terms of the subcontract, Dunbar agreed to pay Harding Enterprises $1,794,136.00 “as full compensation for all the work” described in the agreement. R. Doc. 27-4, at 1. The subcontract detailed Harding Enterprises’ “Scope of Work” as follows: “Subcontractor agrees to perform the following work: Provide all work that was provided in the proposal.” R. Doc. 27- 4, at 1. The subcontract also contained a provision regarding “Changes to the Scope of Work,” which provides:
The Contractor may, at any time after the execution of this Agreement, without invalidating this Agreement or any bonds, if any, or security furnished hereunder, and without notice to the sureties, add to, reduce or omit Subcontractors’s scope of work; all such changes shall be authorized by written change order. Reductions or omissions shall be given in writing to Subcontractor not later than five (5) days prior to when the Work that has been reduced or omitted was scheduled to begin. When work is omitted or reduced, in whole or part, the Contractor shall pay, subject to the provisions of this Agreement, for all work actually performed. Subcontractor is not entitled to compensation or damage for any loss, including loss of profit or overhead relating to reduced or omitted work. All claims for unexpected conditions or delays must be given with in [sic] 5 days after subcontractor recognizes the condition or event giving rise to the claim. Except in an emergency, notice shall be given before proceeding with the Work.
R. Doc. 27-4, at 3.
Roughly one month after entering into the subcontract with Harding Enterprises, Dunbar entered into a separate employment agreement with Gregg Harding, who was the sole member of Harding Enterprises. Dunbar hired Harding to serve as the project manager for the ditch project for compensation of $62,000.00. Hanover subsequently issued a subcontract performance bond and a subcontract payment bond guaranteeing Harding Enterprises’ performance. The bond was in the amount of the full stated value
of the subcontract, $1,794,136.00, and listed Harding Enterprises as the Principal and Dunbar as the Obligee.
On April 20, 2017, Dunbar informed Hanover that it was terminating Harding Enterprises as the subcontractor and Gregg Harding as the project manager based on Harding Enterprises’ alleged default under the subcontract agreement. Dunbar demanded performance on the bond and Hanover undertook an investigation of Dunbar’s claim. During this investigation, Hanover discovered that Dunbar had subcontracted more than 85% of the work under the prime contract to Harding Enterprises, which did not qualify as an SDVOSB. Because the federal regulation governing the government award of a contract to an SDVOSB requires the SDVOSB to perform at least 15% of the cost of the prime contract, Hanover determined that Dunbar was in violation of this requirement and denied Dunbar’s claim on this basis.
Hanover then filed a declaratory judgment action seeking a declaration that Hanover had no obligations to Dunbar under the bond and seeking rescission of the bond based on the illegality of the underlying subcontract. Hanover filed a motion for judgment on the pleadings, which, after notifying the parties, the district court converted into a motion for summary judgment. The district court granted Hanover’s motion for summary judgment, concluding that the subcontract between Dunbar and Harding Enterprises undisputedly violated federal law. The district court reached this determination by dividing the amount Dunbar was to pay Harding Enterprises under the subcontract by the total amount of the prime contract, which demonstrated that Dunbar had contracted to pay Harding Enterprises 87.6% of the total prime contract price. The district court then added to the equation the additional $62,000.00 that was to be paid to Gregg Harding as project manager under the employment agreement, concluding that the total amount Dunbar was to pay Harding Enterprises and Gregg Harding combined represented 90.66% of the value of the prime contract. Because this percentage exceeds the federally mandated 85% limit on work the SDVOSB could subcontract, the district court concluded that the subcontract was illegal. The district
court noted that illegality provides grounds for rescinding a contract and ruled that Hanover was not required to fulfill any of its obligations under the bond. In closing, the district court noted that there may be potential liability for Hanover under the False Claims Act (FCA) if it were to perform in “furtherance of an illegal subcontract for work on a Government project.” R. Doc. 32, at 6. The district court entered judgment accordingly, and Dunbar appeals.
II.
Free access — add to your briefcase to read the full text and ask questions with AI
964 F.3d 763 (Hanover Insurance Company v. Dunbar Mechanical Contractors) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.