Hancock v. Johnson

244 P.2d 285, 69 Wyo. 503, 1952 Wyo. LEXIS 15
CourtWyoming Supreme Court
DecidedMay 6, 1952
Docket2539
StatusPublished
Cited by3 cases

This text of 244 P.2d 285 (Hancock v. Johnson) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hancock v. Johnson, 244 P.2d 285, 69 Wyo. 503, 1952 Wyo. LEXIS 15 (Wyo. 1952).

Opinion

*507 OPINION

Ilsley, Justice.

This case is here by direct appeal. Plaintiff and respondent Hancock states in his petition that as a general contractor he entered into a subcontract with defendant and appellant Johnson, a subcontractor, for the construction, repair and alteration of a school building at Buffalo, Wyoming, for the contract price of $26,000.00. A copy of the contract was attached to the petition and the provisions of the written contract insofar as they are material to the matters before us recite that Hancock is the contractor, Johnson the subcontractor, who:

“For the consideration hereinafter named, the said Subcontractor covenants and agrees with said Contractor, as follows:
“FIRST: The Sub-contractor agrees to furnish all material and perform all work necessary to complete the Grade School Building at Buffalo, Wyoming, School District No. 2. All brick work furnishing all labor and material including terra cotta, for the above named structure, according to the plans and specifications (details thereof to be furnished as needed) of Goodrich & Wilking Architects, and to the full satisfaction of said Architects.
“SECOND: The Sub-contractor agrees to promptly begin said work as soon as notified by said Contractor, and to complete the work as follows: as necessary.
*508 “FIFTH: No extra work or changes under this contract will be recognized or paid for, unless agreed to in writing before the work is done or the changes made.
“IN CONSIDERATION WHEREOF, the said Contractor agrees that he will pay to the said Sub-contractor, in monthly payments, the sum of Twenty-six Thousand ($26,000.00) Dollars for said materials and work, said amount to be paid as follows: Ninety per cent (90%) of all labor and material which has been placed in position by said Sub-contractor to be paid on or about the 10th of the following month, except the final payment, which the said Contractor shall pay to the said Sub-contractor within 80 days after the Sub-contractor shall have completed his work to the full satisfaction of the said Architect or Owner.”

In the interest of brevity, the portions of the contract not material to the issues herein are omitted. The petition alleges that Johnson failed and neglected to furnish all materials and perform all work necessary according to said plans and specifications and defaulted in his contract ; that Hancock took over the work and furnished materials as the general contractor, all of which should have been done by Johnson. An itemized account called “Exhibit B” is attached to the Hancock petition showing labor and material which he claims were necessary to complete the contract according to plans and specifications as required by the contract; that on January 13, 1950 Johnson and Hancock entered into an agreement, evidenced by a written memorandum, with respect to extra work required to be done and the amount to be paid by Hancock to Johnson therefor. A copy of the memorandum, attached to the petition and called

“Exhibit C” is as follows:
“Buffalo, Wyo.
Jan. 13,1950.
Extra work agreed to between Loren Hancock and Chas. W. Johnson, as follows:
*509 Raise lintels on 2nd floor.$ 250.00
8" wall in toilet room over 4". 50.00
Wall around stairway in class room. 649.87
Raise door heads first floor. 114.16
8" tile wall in bsmt. (Cone, blocks). 35.00
8" tile wall in janitors closet. 25.00
$1,124.03
“Chas. W. Johnson agrees to pay all outstanding bills for material and all labor required to finish brick work, and to finish and complete said work.
Chas. W. Johnson.”

The itemized account referred to as “Exhibit B” supra, consists of some 73 items claimed to be furnished by Hancock which were in dispute. A condensation of the account is as follows:

“EXHIBIT “B”
STATEMENT OF ACCOUNT — BUFFALO SCHOOL BRICK WORK CONTRACT
Loren Hancock, Dr.
to
Charles Johnson
Original Contract Price. $26,000.00
6 items of extras allowed and approved by architect i.e. Exhibit “C”. 1,124.03
Credit for 4 items. 83.86
Due Loren Hancock for 73 items.
Last item April 30, 1950.$ 4,653.87
By cash Hancock to Johnson. 24,073.36
Totals.$28,727.23 $27,207.89
Balance due Hancock from Johnson . 1,519.34
$28,727.23 $28,727.23

*510 Hancock prays for judgment in the sum of $1,519.34 and interest from May 30, 1950.

To this petition Johnson filed his Answer and counterclaims setting forth; in his first defense, a general denial; the second defense, admits the general contract; he alleges that Hancock’s agent, David Carson, instructed Johnson to cease work on the school building on January 7, 1950, which was done; that on January 13, 1950 Hancock and Johnson agreed that work was to continue upon arrival of “glazed tile bull nose corners”, which came March 6, 1950 whereupon Johnson finished his work on April 21, 1950; that any alleged delay in the performance of the agreement by Johnson was caused by Hancock with a wilful and purposeful design or negligence and carelessness, to interrupt Johnson’s performance under the contract. The third defense states that any material and labor furnished by Hancock was voluntary and not authorized by Johnson, nor necessary.

Johnson then sets forth in his answer a first counterclaim, stating that of the $26,000.00 contract price only $24,073.36 has been paid, leaving a balance of $1,926.24 which Hancock refuses to pay. The second counterclaim claims Johnson has $1,124.03 as credit due him upon “Exhibit C” supra, which Hancock refuses to pay. The third counterclaim states that there is the sum of $903.00 due Johnson by reason of brick work performed by him at the instance of Hancock’s agent and superintendent, David Carson, and in addition to the plans and specifications referred to in the subcontract “Exhibit A”, attached to Hancock’s petition.

There is a prayer for judgment for the items set forth in the three counterclaims and there are 17 interrogatories attached to the answer.

Hancock filed his reply by way of general denial to all defenses and counterclaims and answered all 17 inter

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
244 P.2d 285, 69 Wyo. 503, 1952 Wyo. LEXIS 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hancock-v-johnson-wyo-1952.