Hancock County v. Hancock Wind, LLC

CourtSuperior Court of Maine
DecidedApril 17, 2019
DocketCUMbcd-cv-19-05
StatusUnpublished

This text of Hancock County v. Hancock Wind, LLC (Hancock County v. Hancock Wind, LLC) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hancock County v. Hancock Wind, LLC, (Me. Super. Ct. 2019).

Opinion

STATE OF MAINE BUSINESS & CONSUMER DOCKET CUMBERLAND, ss. DOCKET NO. BCD-CV-19-05

HANCOCK COUNTY, ) ) Plaintiff, ) ) v. ) ORDER GRANTING PLAINTIFF’S ) MOTION TO DISMISS HANCOCK WIND, LLC, ) COUNTERCLAIM ) Defendant. )

In this case regarding a wind energy project in Hancock County, Maine, Plaintiff Hancock

County (the “County”) has moved to dismiss the Counterclaim filed by Defendant Hancock Wind,

LLC (“Hancock Wind” or the “Company”). The Court heard oral argument on the motion on

Friday, April 5. The County appeared through attorney Edmond Bearor, Esq. and Dan Mitchell,

Esq. appeared for Hancock Wind. For the reasons stated, the Court grants the County’s motion.

BACKGROUND

On September 12, 2014, Hancock Wind entered into a Community Benefit Agreement

(“CBA”) with Hancock County whereby Hancock Wind would make annual payments to the

County, calculated as a function of $3,703 times the “rating generating capacity” of a multi-turbine

wind energy project (the “Project”) that Hancock Wind would construct in the County. (Pl’s

Compl. ¶¶ 7, 12.) Hancock Wind made the first payment by check on November 30, 2016. (Pl’s

Compl. ¶ 15.) Shortly after the County received the check, however, Hancock Wind said that it

had overpaid and asked for $18,885.30 back. (Pl’s Compl. ¶ 16.) The County beleived that the

original amount was the correct amount and declined to refund Hancock Wind. (Pl’s Compl. ¶ 18.)

On December 1, 2017, Hancock Wind made its second annual payment, but deducted $37,770.60

1 from what the County expected to receive: minus $18,885.30 because of the previous year’s

purported overpayment, and minus an additional $18,885.30 for that year’s payment based on what

Hancock Wind believed to be the correct amount due. (Pl’s Compl. ¶¶ 20-24.) Hancock County

filed suit against Hancock Wind on November 14, 2018, requesting a declaratory judgment on the

proper construction of the CBA and alleging breach of contract based on Hancock Wind’s

purported underpayment under the CBA. (Pl’s Compl. ¶¶ 26-31.) The dispute, as alleged, is based

on whether the Project’s “rating generating capacity” is 56.1 megawatts (“MW”) or 51 MW: the

Project’s seventeen wind turbines have a “rated capacity” of 3.3 MW each, but the turbines are

“converter-limited” to 3.0 MW. (Pl’s Compl. ¶ 17.)

Hancock Wind answered and counterclaimed, pleading one count of “indemnification”

based on the CBA. (Def’s Countercl. ¶¶ 1-7.) Hancock Wind alleges that pursuant to section 11 of

the CBA, the County must indemnify Hancock Wind for any legal expenses it incurs in its defense

of the County’s Complaint and prosecution of its own Counterclaim. (Def’s Countercl. ¶ 7.)

Section 11 (the “Indemnification Provision”) of the CBA (Pl.’s Compl., Ex. A, hereafter “CBA”)

provides as follows:1

11. Indemnification. As a further condition of the Agreement, the County agrees to indemnify the Company for any legal expenses incurred by the Company as a result of legal challenges by any person other than the Company or the Company’s successors or assigns to the validity or administration of this Agreement.

Hancock County responded with the motion to dismiss counterclaim now before the Court.

1 A copy of the CBA was attached to the County’s Complaint and the Company’s Counterclaim. The Court may thus consider the CBA without converting the instant motion to one for summary judgment. M.R. Civ. P. 10(c); see also Moody v. State Liq. & Lott. Comm’n, 2004 ME 20, ¶ 10, 843 A.2d 43.

2 DISCUSSION

Hancock County argues that its Complaint is not a legal challenge to the “validity or

administration” of the CBA and that the Indemnification Provision does not specifically reference

direct claims between the parties and therefore does not encompass the County’s lawsuit. Hancock

Wind responds that the Complaint is a challenge to the “administration” of the CBA and,

moreover, the broad language of the Indemnification Provision obligates Hancock County to

indemnify Hancock Wind for its legal expenses, even for the County’s own lawsuit against

Hancock Wind. The Court considers each argument in turn.

I. Hancock County’s Lawsuit is Not a Challenge to the Administration of the CBA.

The County first argues that in the context of the CBA, its lawsuit is not a challenge to the

“administration” of the agreement as that term is used in the Indemnification Provision. Hancock

Wind responds that the “administration” of the CBA includes Hancock Wind’s calculation and

payment of annual contributions under any reasonable interpretation of the word. Neither party

argues that the term is ambiguous, their disagreement is merely over the breadth of the term in the

context of this agreement. See Champagne v. Victory Homes, Inc., 2006 ME 58, ¶ 10, 897 A.2d

803 (“The fact that parties have different views of what an agreement means does not render it

ambiguous.”).

“A contract is to be interpreted to effect the parties’ intentions as reflected in the written

instrument, construed with regard for the subject matter, motive, and purpose of the agreement, as

well as the object to be accomplished.” Eastwick v. Cate St. Capital, Inc., 2017 ME 206, ¶ 16, 171

A.3d 1152 (quotation omitted). “In construing a contract, an interpretation should be avoided that

would render meaningless any particular provision in the contract.” Top of the Track Assocs. v.

Lewiston Raceways, 654 A.2d 1293, 1296 (Me. 1995) (citation omitted); see also Acadia Ins. Co.

3 v. Buck Constr. Co., 2000 ME 154, ¶ 9, 756 A.2d 515 (“a contract [should generally] be construed

to give force and effect to all of its provisions.”); Peerless Ins. Co. v. Brennon, 564 A.2d 383, 385

(Me. 1989) (contracts “construed in accordance with the intention of the parties, which is to be

ascertained from an examination of the whole instrument. All parts and clauses must be considered

together that it may be seen if and how far one clause is explained, modified, limited or controlled

by the others.”) (quoting Swift v. Patrons Androscoggin Mutual Fire Ins. Co., 125 Me. 255, 256,

132 A. 745, 746 (1926)).

The County points out that the second “Whereas Clause” under the Recitals heading of the

CBA explicitly references 35-A M.R.S. § 3451-3459 (the “Statute”). The clause recognizes that

approval of the expedited wind energy development permit for the Project requires that the Project

provide significant tangible benefits to the area in which the Project is located in the form of a

CBA. See id. §§ 3451(1-C), 3454(2). Pursuant to the Statute, the CBA “involves payments by the

developer to the host community to be utilized for public purposes, including, but not limited to,

for property tax reductions, economic development projects, land and natural resource

conservation, tourism promotion or reduction of energy costs. . . .” Id. § 3451(1-B); see also id. §

3454(4). The annual contributions at the center of this dispute are the tangible benefits described

in the Statute. (CBA § 2(a).) Pursuant to the seventh Whereas Clause, the parties “agree and

acknowledge that the [payments provided pursuant to the CBA] shall not influence or have any

bearing whatsoever on the County’s review of any application of the Company for any [p]ermit or

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moody v. State Liquor & Lottery Commission
2004 ME 20 (Supreme Judicial Court of Maine, 2004)
Peerless Insurance Co. v. Brennon
564 A.2d 383 (Supreme Judicial Court of Maine, 1989)
Champagne v. Victory Homes, Inc.
2006 ME 58 (Supreme Judicial Court of Maine, 2006)
Acadia Insurance Co. v. Buck Construction Co.
2000 ME 154 (Supreme Judicial Court of Maine, 2000)
Devine v. Roche Biomedical Laboratories, Inc.
637 A.2d 441 (Supreme Judicial Court of Maine, 1994)
Farrand v. Redington Memorial Home
270 A.2d 871 (Supreme Judicial Court of Maine, 1970)
Top of the Track Associates v. Lewiston Raceways, Inc.
654 A.2d 1293 (Supreme Judicial Court of Maine, 1995)
Matthew Eastwick v. Cate Street Capital, Inc.
2017 ME 206 (Supreme Judicial Court of Maine, 2017)
Swift v. Patrons' Androscoggin Mutual Fire Insurance
132 A. 745 (Supreme Judicial Court of Maine, 1926)
Nassau Chapter, Civil Service Employees Association, Inc. v. County of Nassau
77 A.D.2d 563 (Appellate Division of the Supreme Court of New York, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
Hancock County v. Hancock Wind, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hancock-county-v-hancock-wind-llc-mesuperct-2019.