STATE OF MAINE BUSINESS & CONSUMER DOCKET CUMBERLAND, ss. DOCKET NO. BCD-CV-19-05
HANCOCK COUNTY, ) ) Plaintiff, ) ) v. ) ORDER GRANTING PLAINTIFF’S ) MOTION TO DISMISS HANCOCK WIND, LLC, ) COUNTERCLAIM ) Defendant. )
In this case regarding a wind energy project in Hancock County, Maine, Plaintiff Hancock
County (the “County”) has moved to dismiss the Counterclaim filed by Defendant Hancock Wind,
LLC (“Hancock Wind” or the “Company”). The Court heard oral argument on the motion on
Friday, April 5. The County appeared through attorney Edmond Bearor, Esq. and Dan Mitchell,
Esq. appeared for Hancock Wind. For the reasons stated, the Court grants the County’s motion.
BACKGROUND
On September 12, 2014, Hancock Wind entered into a Community Benefit Agreement
(“CBA”) with Hancock County whereby Hancock Wind would make annual payments to the
County, calculated as a function of $3,703 times the “rating generating capacity” of a multi-turbine
wind energy project (the “Project”) that Hancock Wind would construct in the County. (Pl’s
Compl. ¶¶ 7, 12.) Hancock Wind made the first payment by check on November 30, 2016. (Pl’s
Compl. ¶ 15.) Shortly after the County received the check, however, Hancock Wind said that it
had overpaid and asked for $18,885.30 back. (Pl’s Compl. ¶ 16.) The County beleived that the
original amount was the correct amount and declined to refund Hancock Wind. (Pl’s Compl. ¶ 18.)
On December 1, 2017, Hancock Wind made its second annual payment, but deducted $37,770.60
1 from what the County expected to receive: minus $18,885.30 because of the previous year’s
purported overpayment, and minus an additional $18,885.30 for that year’s payment based on what
Hancock Wind believed to be the correct amount due. (Pl’s Compl. ¶¶ 20-24.) Hancock County
filed suit against Hancock Wind on November 14, 2018, requesting a declaratory judgment on the
proper construction of the CBA and alleging breach of contract based on Hancock Wind’s
purported underpayment under the CBA. (Pl’s Compl. ¶¶ 26-31.) The dispute, as alleged, is based
on whether the Project’s “rating generating capacity” is 56.1 megawatts (“MW”) or 51 MW: the
Project’s seventeen wind turbines have a “rated capacity” of 3.3 MW each, but the turbines are
“converter-limited” to 3.0 MW. (Pl’s Compl. ¶ 17.)
Hancock Wind answered and counterclaimed, pleading one count of “indemnification”
based on the CBA. (Def’s Countercl. ¶¶ 1-7.) Hancock Wind alleges that pursuant to section 11 of
the CBA, the County must indemnify Hancock Wind for any legal expenses it incurs in its defense
of the County’s Complaint and prosecution of its own Counterclaim. (Def’s Countercl. ¶ 7.)
Section 11 (the “Indemnification Provision”) of the CBA (Pl.’s Compl., Ex. A, hereafter “CBA”)
provides as follows:1
11. Indemnification. As a further condition of the Agreement, the County agrees to indemnify the Company for any legal expenses incurred by the Company as a result of legal challenges by any person other than the Company or the Company’s successors or assigns to the validity or administration of this Agreement.
Hancock County responded with the motion to dismiss counterclaim now before the Court.
1 A copy of the CBA was attached to the County’s Complaint and the Company’s Counterclaim. The Court may thus consider the CBA without converting the instant motion to one for summary judgment. M.R. Civ. P. 10(c); see also Moody v. State Liq. & Lott. Comm’n, 2004 ME 20, ¶ 10, 843 A.2d 43.
2 DISCUSSION
Hancock County argues that its Complaint is not a legal challenge to the “validity or
administration” of the CBA and that the Indemnification Provision does not specifically reference
direct claims between the parties and therefore does not encompass the County’s lawsuit. Hancock
Wind responds that the Complaint is a challenge to the “administration” of the CBA and,
moreover, the broad language of the Indemnification Provision obligates Hancock County to
indemnify Hancock Wind for its legal expenses, even for the County’s own lawsuit against
Hancock Wind. The Court considers each argument in turn.
I. Hancock County’s Lawsuit is Not a Challenge to the Administration of the CBA.
The County first argues that in the context of the CBA, its lawsuit is not a challenge to the
“administration” of the agreement as that term is used in the Indemnification Provision. Hancock
Wind responds that the “administration” of the CBA includes Hancock Wind’s calculation and
payment of annual contributions under any reasonable interpretation of the word. Neither party
argues that the term is ambiguous, their disagreement is merely over the breadth of the term in the
context of this agreement. See Champagne v. Victory Homes, Inc., 2006 ME 58, ¶ 10, 897 A.2d
803 (“The fact that parties have different views of what an agreement means does not render it
ambiguous.”).
“A contract is to be interpreted to effect the parties’ intentions as reflected in the written
instrument, construed with regard for the subject matter, motive, and purpose of the agreement, as
well as the object to be accomplished.” Eastwick v. Cate St. Capital, Inc., 2017 ME 206, ¶ 16, 171
A.3d 1152 (quotation omitted). “In construing a contract, an interpretation should be avoided that
would render meaningless any particular provision in the contract.” Top of the Track Assocs. v.
Lewiston Raceways, 654 A.2d 1293, 1296 (Me. 1995) (citation omitted); see also Acadia Ins. Co.
3 v. Buck Constr. Co., 2000 ME 154, ¶ 9, 756 A.2d 515 (“a contract [should generally] be construed
to give force and effect to all of its provisions.”); Peerless Ins. Co. v. Brennon, 564 A.2d 383, 385
(Me. 1989) (contracts “construed in accordance with the intention of the parties, which is to be
ascertained from an examination of the whole instrument. All parts and clauses must be considered
together that it may be seen if and how far one clause is explained, modified, limited or controlled
by the others.”) (quoting Swift v. Patrons Androscoggin Mutual Fire Ins. Co., 125 Me. 255, 256,
132 A. 745, 746 (1926)).
The County points out that the second “Whereas Clause” under the Recitals heading of the
CBA explicitly references 35-A M.R.S. § 3451-3459 (the “Statute”). The clause recognizes that
approval of the expedited wind energy development permit for the Project requires that the Project
provide significant tangible benefits to the area in which the Project is located in the form of a
CBA. See id. §§ 3451(1-C), 3454(2). Pursuant to the Statute, the CBA “involves payments by the
developer to the host community to be utilized for public purposes, including, but not limited to,
for property tax reductions, economic development projects, land and natural resource
conservation, tourism promotion or reduction of energy costs. . . .” Id. § 3451(1-B); see also id. §
3454(4). The annual contributions at the center of this dispute are the tangible benefits described
in the Statute. (CBA § 2(a).) Pursuant to the seventh Whereas Clause, the parties “agree and
acknowledge that the [payments provided pursuant to the CBA] shall not influence or have any
bearing whatsoever on the County’s review of any application of the Company for any [p]ermit or
Free access — add to your briefcase to read the full text and ask questions with AI
STATE OF MAINE BUSINESS & CONSUMER DOCKET CUMBERLAND, ss. DOCKET NO. BCD-CV-19-05
HANCOCK COUNTY, ) ) Plaintiff, ) ) v. ) ORDER GRANTING PLAINTIFF’S ) MOTION TO DISMISS HANCOCK WIND, LLC, ) COUNTERCLAIM ) Defendant. )
In this case regarding a wind energy project in Hancock County, Maine, Plaintiff Hancock
County (the “County”) has moved to dismiss the Counterclaim filed by Defendant Hancock Wind,
LLC (“Hancock Wind” or the “Company”). The Court heard oral argument on the motion on
Friday, April 5. The County appeared through attorney Edmond Bearor, Esq. and Dan Mitchell,
Esq. appeared for Hancock Wind. For the reasons stated, the Court grants the County’s motion.
BACKGROUND
On September 12, 2014, Hancock Wind entered into a Community Benefit Agreement
(“CBA”) with Hancock County whereby Hancock Wind would make annual payments to the
County, calculated as a function of $3,703 times the “rating generating capacity” of a multi-turbine
wind energy project (the “Project”) that Hancock Wind would construct in the County. (Pl’s
Compl. ¶¶ 7, 12.) Hancock Wind made the first payment by check on November 30, 2016. (Pl’s
Compl. ¶ 15.) Shortly after the County received the check, however, Hancock Wind said that it
had overpaid and asked for $18,885.30 back. (Pl’s Compl. ¶ 16.) The County beleived that the
original amount was the correct amount and declined to refund Hancock Wind. (Pl’s Compl. ¶ 18.)
On December 1, 2017, Hancock Wind made its second annual payment, but deducted $37,770.60
1 from what the County expected to receive: minus $18,885.30 because of the previous year’s
purported overpayment, and minus an additional $18,885.30 for that year’s payment based on what
Hancock Wind believed to be the correct amount due. (Pl’s Compl. ¶¶ 20-24.) Hancock County
filed suit against Hancock Wind on November 14, 2018, requesting a declaratory judgment on the
proper construction of the CBA and alleging breach of contract based on Hancock Wind’s
purported underpayment under the CBA. (Pl’s Compl. ¶¶ 26-31.) The dispute, as alleged, is based
on whether the Project’s “rating generating capacity” is 56.1 megawatts (“MW”) or 51 MW: the
Project’s seventeen wind turbines have a “rated capacity” of 3.3 MW each, but the turbines are
“converter-limited” to 3.0 MW. (Pl’s Compl. ¶ 17.)
Hancock Wind answered and counterclaimed, pleading one count of “indemnification”
based on the CBA. (Def’s Countercl. ¶¶ 1-7.) Hancock Wind alleges that pursuant to section 11 of
the CBA, the County must indemnify Hancock Wind for any legal expenses it incurs in its defense
of the County’s Complaint and prosecution of its own Counterclaim. (Def’s Countercl. ¶ 7.)
Section 11 (the “Indemnification Provision”) of the CBA (Pl.’s Compl., Ex. A, hereafter “CBA”)
provides as follows:1
11. Indemnification. As a further condition of the Agreement, the County agrees to indemnify the Company for any legal expenses incurred by the Company as a result of legal challenges by any person other than the Company or the Company’s successors or assigns to the validity or administration of this Agreement.
Hancock County responded with the motion to dismiss counterclaim now before the Court.
1 A copy of the CBA was attached to the County’s Complaint and the Company’s Counterclaim. The Court may thus consider the CBA without converting the instant motion to one for summary judgment. M.R. Civ. P. 10(c); see also Moody v. State Liq. & Lott. Comm’n, 2004 ME 20, ¶ 10, 843 A.2d 43.
2 DISCUSSION
Hancock County argues that its Complaint is not a legal challenge to the “validity or
administration” of the CBA and that the Indemnification Provision does not specifically reference
direct claims between the parties and therefore does not encompass the County’s lawsuit. Hancock
Wind responds that the Complaint is a challenge to the “administration” of the CBA and,
moreover, the broad language of the Indemnification Provision obligates Hancock County to
indemnify Hancock Wind for its legal expenses, even for the County’s own lawsuit against
Hancock Wind. The Court considers each argument in turn.
I. Hancock County’s Lawsuit is Not a Challenge to the Administration of the CBA.
The County first argues that in the context of the CBA, its lawsuit is not a challenge to the
“administration” of the agreement as that term is used in the Indemnification Provision. Hancock
Wind responds that the “administration” of the CBA includes Hancock Wind’s calculation and
payment of annual contributions under any reasonable interpretation of the word. Neither party
argues that the term is ambiguous, their disagreement is merely over the breadth of the term in the
context of this agreement. See Champagne v. Victory Homes, Inc., 2006 ME 58, ¶ 10, 897 A.2d
803 (“The fact that parties have different views of what an agreement means does not render it
ambiguous.”).
“A contract is to be interpreted to effect the parties’ intentions as reflected in the written
instrument, construed with regard for the subject matter, motive, and purpose of the agreement, as
well as the object to be accomplished.” Eastwick v. Cate St. Capital, Inc., 2017 ME 206, ¶ 16, 171
A.3d 1152 (quotation omitted). “In construing a contract, an interpretation should be avoided that
would render meaningless any particular provision in the contract.” Top of the Track Assocs. v.
Lewiston Raceways, 654 A.2d 1293, 1296 (Me. 1995) (citation omitted); see also Acadia Ins. Co.
3 v. Buck Constr. Co., 2000 ME 154, ¶ 9, 756 A.2d 515 (“a contract [should generally] be construed
to give force and effect to all of its provisions.”); Peerless Ins. Co. v. Brennon, 564 A.2d 383, 385
(Me. 1989) (contracts “construed in accordance with the intention of the parties, which is to be
ascertained from an examination of the whole instrument. All parts and clauses must be considered
together that it may be seen if and how far one clause is explained, modified, limited or controlled
by the others.”) (quoting Swift v. Patrons Androscoggin Mutual Fire Ins. Co., 125 Me. 255, 256,
132 A. 745, 746 (1926)).
The County points out that the second “Whereas Clause” under the Recitals heading of the
CBA explicitly references 35-A M.R.S. § 3451-3459 (the “Statute”). The clause recognizes that
approval of the expedited wind energy development permit for the Project requires that the Project
provide significant tangible benefits to the area in which the Project is located in the form of a
CBA. See id. §§ 3451(1-C), 3454(2). Pursuant to the Statute, the CBA “involves payments by the
developer to the host community to be utilized for public purposes, including, but not limited to,
for property tax reductions, economic development projects, land and natural resource
conservation, tourism promotion or reduction of energy costs. . . .” Id. § 3451(1-B); see also id. §
3454(4). The annual contributions at the center of this dispute are the tangible benefits described
in the Statute. (CBA § 2(a).) Pursuant to the seventh Whereas Clause, the parties “agree and
acknowledge that the [payments provided pursuant to the CBA] shall not influence or have any
bearing whatsoever on the County’s review of any application of the Company for any [p]ermit or
any other decision the County may have occasion to make relative to the project.” Section 2 of the
CBA further explicitly contemplates third-party litigation challenging the County’s use of CBA
payments. (CBA § 2(b).)
4 Taken as a whole, the CBA contextualizes what the parties intended when Hancock County
agreed to indemnify Hancock Wind for any “legal challenges . . . to the validity or administration
of” the CBA. (CBA § 11.) The CBA does not contemplate “legal challenges” between the parties
to the proper calculation of Hancock Wind’s annual contributions to the County, but it does
explicitly contemplate third party challenges to the administration and use of those payments. The
use of these payments is also a central concern of the Statute, which is explicitly and implicitly
referenced throughout the CBA. The Court therefore concludes that “administration” as that term
is used in the Indemnification Provision unambiguously refers to the County’s use of Hancock
Wind’s payments to the County. Read in its entirety, the CBA does not support a broader
construction of the term.
Hancock Wind argues that the County’s construction of the provision reads out the
language “of this Agreement” and reads in the language “under the Statute,” and therefore relies
on material beyond the four corners of the CBA. Hancock Wind further argues that the County’s
attempt to limit the broad scope of the language of the Indemnification Provision is unsupported
by the unambiguous, plain language of the provision, which provides that the County will
indemnify Hancock Wind for legal expenses incurred as a result of lawsuits challenging the
“administration of this Agreement[,]” with no other qualifiers. The problem with Hancock Wind’s
first argument is that the CBA explicitly and implicitly references the Statute. (CBA, Second
Whereas Clause; § 2(a) (quoting the Statute verbatim).). Hancock Wind’s second argument
focuses too narrowly on the Indemnification Provision in isolation, without consideration of the
entire agreement as a whole. Here, the term “administration” is rendered unambiguous and
narrowed in scope when considered in tandem with the CBA’s other provisions. See Peerless Ins.
Co., 564 A.2d at 385; Farrand v. Redington Mem'l Home, 270 A.2d 871, 875 (Me. 1970).
5 II. The Indemnification Provision Does Not Apply to the County’s Lawsuit.
The County next argues that the Indemnification Provision applies only to third-party
claims, and not direct claims brought by the County, because it is broadly worded and does not
specifically provide for indemnification in the case of direct claims brought by Hancock County.
Hancock Wind responds that the County’s lawsuit is clearly within the scope of the plain language
of the Indemnification Provision, and that nothing more specific is required.
Assuming arguendo that the County’s lawsuit is a challenge to the “administration” of the
CBA, the Indemnification Provision nonetheless lacks the specificity and explicitness required
under Maine law. “An indemnification claim based on contract must rest on a clear, express,
specific, and explicit contractual provision, under which the party against which a claim is to be
asserted has agreed to assume the duty to indemnify.” Devine v. Roche Biomedical Labs., 637 A.2d
441, 446 (Me. 1994); see also Patco Constr. Co. v. Peoples United Bank, No. 09-503-P-H, 2010
U.S. Dist. LEXIS 136748 (D. Me. March 31, 2010) (“for a contractual indemnification provision
to apply to claims between the parties to the contract, rather than to third parties’ claims, it must
be stated clearly and unambiguously”) (applying Maine and Connecticut law).
Hancock Wind’s main argument is that the Indemnification Provision is clear and
unambiguous, albeit broad, and that its generality does not remove the County’s lawsuit from its
scope. Under Devine, however, an indemnification claim based on contract must rest on a specific
and explicit contractual provision, not merely a clear and express one. In other words, the parties
did not state their intention for the Indemnification Provision to apply to the County’s own claims
against Hancock Wind specifically and explicitly. Therefore, under Devine, the Indemnification
Provision cannot support an indemnification claim by Hancock Wind against Hancock County for
the County’s own lawsuit against the Company. 637 A.2d at 446.
6 Finally, the Court is persuaded by a hypothetical raised by Hancock County at the oral
argument. Hancock County pointed out that under Hancock Wind’s construction of the
Indemnification Provision, Hancock Wind could blatantly breach the CBA by simply withholding
the entirety of each annual payment, and the County would be required to finance Hancock Wind’s
defense of the County’s ensuing action for breach of contract. Litigation costs could easily outpace
the County’s potential recovery. The Indemnification Provision as construed by Hancock Wind
would thus result, practically, in an absurd result.2
Generally, “[a]n interpretation which gives a reasonable, lawful, and effective meaning to
all the terms is preferred to an interpretation which leaves a part unreasonable, unlawful, or of no
effect” and “a contract construction which produces an unreasonable result should be avoided.”
Moody v. Me. State Lottery, No. CV-02-540, 2003 Me. Super. LEXIS 153, *5 (June 12, 2003)
(quoting Restatement (Second) of Contracts § 203(a) (1981)) (citing Nassau Chap., Civ. Svc. v.
Nassau Cty., 430 N.Y.S.2d 98, 100), aff’d, 2004 ME 20, 843 A.2d 43. The Court thus concludes
that, as written, no reasonable interpretation of the Indemnification Provision could result in a
construction where the County is required to indemnify Hancock Wind for its litigation costs in a
case brought by the County against Hancock Wind to enforce the Company’s payment obligations
under the CBA.
CONCLUSION
For all the foregoing reasons, Hancock County’s motion to dismiss counterclaim is
granted.
2 At oral argument, both parties rejected the Court’s query as to whether a “prevailing party” condition could be read into the Indemnification Provision in the case of direct claims on the grounds that there is nothing in the CBA or the Indemnification Provision to support the insertion of such a term.
7 Pursuant to M.R. Civ. P. 79(a), the Clerk is instructed to incorporate this Order by
reference on the docket for this case.
So Ordered.
Dated: April 17, 2019 ___/s_____________________________ Michael A. Duddy Judge, Business and Consumer Docket