Hance Hardware v. Denbigh Hall Incorporated

152 A. 130
CourtCourt of Chancery of Delaware
DecidedOctober 21, 1930
StatusPublished

This text of 152 A. 130 (Hance Hardware v. Denbigh Hall Incorporated) is published on Counsel Stack Legal Research, covering Court of Chancery of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hance Hardware v. Denbigh Hall Incorporated, 152 A. 130 (Del. Ct. App. 1930).

Opinion

The insolvent corporation was organized for the purpose of constructing and operating an apartment house in the city of Wilmington. In order to finance the construction, it made application to Integrity Trust Company for a mortgage loan. The loan was granted in the amount of $237,500, and was secured by a mortgage dated and recorded on March 7, 1929. The premises described in the mortgage are the same land which the receiver has sold and the proceeds from the sale of which are now in hand subject to such disposition as the court may order.

At the time the mortgage was given, the apartment house was yet to be built. A building operation agreement was entered into by which it was agreed between the mortgagor and mortgagee that the proceeds of the mortgage should be deposited with the mortgagee (which carried on a banking business), and credited to the building operation; and further that the moneys so credited "shall be applied and are hereby irrevocably appropriated to the payment of indebtedness of party of the first part (mortgagor) to party of second part (mortgagee) and to the payment of debts contracted for, in and about the erection and construction of the said building." The agreement then proceeds to provide that the deposited moneys "shall be disbursed or paid out from time to time to the several contractors and mechanics, directly, for work actually done and for materials actually furnished in and about the erection and construction of the said buildings * * * upon orders or vouchers only, signed by the said party of the first part (mortgagor), or his duly constituted attorney-in-fact, herein and countersigned by the proper officers of the said party of the second part (mortgagee), * * * etc."

A so-called settlement sheet, dated March 12, 1929, prepared by the Trust Company and signed by the president of Denbigh Hall Incorporated, shows the sum of $237,500, the amount of the loan, to have been deposited by the mortgagor with the Trust Company. Appropriate entries were made by the Trust Company in its own books showing a credit to Denbigh Hall Incorporated of the same amount. Thereafter the Trust Company, from time to time as the requirements of the construction demanded, transferred to Denbigh Hall Incorporated Building Operation Cash Account from the sum so credited to Denbigh Hall Incorporated, various sums which were disbursed on vouchers in accordance with the agreement in payment of work done and materials furnished for the building. The first of such transfers is shown by the Building Operation Cash Account to have occurred on March 28, 1929. Since then, all but a few hundred dollars of the total credit of $237,500 has been duly transferred to the cash account above referred to and paid out on vouchers on account of the construction costs.

It is apparent from the foregoing statement of facts that the mortgage in question was what is known as a building construction mortgage. The mortgage on its face is a straight mortgage. It purports to show a present obligation for money advanced in the sum of $237,500. While on the date of the mortgage this sum had not been actually advanced, yet the understanding of the parties entered into under date of a few days later shows that the mortgagee was obligated to advance the sum. The acts of the parties were in accordance with this understanding. The amount of the loan was in fact immediately credited by the Trust Company to the borrower's loan account and as before stated it was thence transferred to the borrower's Building Operation Cash Account from which it was checked out on the borrower's orders to pay for construction bills.

The mortgage was therefore not one under which the mortgagee retained an option to make future advances. When a construction mortgage is of that type, there are authorities which hold that the priority of the mortgage as to future advances over liens entered subsequently to its recording, is affected by the presence or absence of actual notice to the mortgagee of the existence of the subsequent liens. See 3 Pomeroy's Equity Jurisprudence (4th Ed.) § 1198 et seq. The case of Ackerman v. Hunsicker et al., 85 N. Y. 43, 39 Am. Rep. 621, upon which the mechanics' lien claimants rely, belongs to this class of authorities. The instant case does not, however, call for a consideration of the question *Page 132

which those authorities present, for this is not a case of optional advances.

In the instant case, various mechanics' lien claimants contend that their liens have priority of rank over the Integrity Trust Company's mortgage. In this State a mechanic's lien takes rank according to the time when the work and labor was begun or the furnishing of materials was commenced. Revised Code 1915, § 2843. In the case of every mechanic's lien claimant here concerned, it appears that the labor was begun or the furnishing of materials commenced not only after the mortgage was dated and recorded but as well also after the amount secured by it was actually placed by the mortgagee to the credit of the mortgagor.

The mechanic's lien created by the Delaware statute, unlike the lien created by statute in some of the American states, gives to the lienors a priority only over liens and encumbrances obtained subsequently to the beginning of the work or the commencing of the furnishing of materials. France v. Woolston, 4 Houst. 557. If the act of the Trust Company mortgagee of placing the full amount of the mortgage to the credit of the mortgagor on or about March 12, 1929, subject to disbursements on the mortgagor's orders, can be said to constitute an advancement at that time of the entire loan, as its solicitors contend and I am inclined to agree, then the loan was fully advanced ahead of all the mechanics' lien claims, and the latter would be clearly junior to the mortgage.

[1] But even if the view be taken that the facts do not warrant the conclusion that the entire sum was advanced at the outset as just stated, yet the facts leave no room to doubt that in any event the mortgagee was irrevocably bound to make advances from time to time up to the full amount named in the mortgage. It had no option in the matter. Taking this as the true aspect of the matter for the moment, the case is one therefore where a straight mortgage for $237,500 was given and recorded to secure future advancements from time to time aggregating that sum with a definite obligation on the part of the mortgagee to make such advancements. The fact that the mortgage did not on its face disclose that the loan was to be thus laid out in future obligatory installments, can in no wise vitiate the validity of the mortgage or its lien. 3 Pomeroy's Equity Jurisprudence (4th Ed.) § 1197; Kentucky Lumber Mill Work Co. v. Kentucky Title Savings Bank Trust Co., 184 Ky. 244,211 S. W. 765, 5 A. L. R. 391.

[2, 3] Where a construction mortgage is for a specified sum which the mortgagee is obligated to advance in installments in the future, and the law governing mechanics' liens is similar to that which is found in this jurisdiction, the decided weight of authority is to the effect that the mortgage lien is a valid one from the date of its recordation and takes priority accordingly to the extent of the advancements made over liens for work and labor done and materials furnished after the date of its recording. Smith v. Anglo-California Trust Co., 205 Cal. 496,271 P. 898; Boise Payette Lumber Co. v. Winward, 47 Idaho, 485, 276 P. 971; Platt v. Griffith et al., 27 N. J. Eq. 207; Micele v. Falduti,101 N. J. Eq. 103

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Anglo-California Trust Co.
271 P. 898 (California Supreme Court, 1928)
Boise Payette Lumber Co. v. Winward
276 P. 971 (Idaho Supreme Court, 1929)
Micele v. Falduti
137 A. 92 (New Jersey Court of Chancery, 1927)
Ackerman v. . Hunsicker
85 N.Y. 43 (New York Court of Appeals, 1881)
Gray v. McClellan
100 N.E. 1093 (Massachusetts Supreme Judicial Court, 1913)
Rowan v. Sharps' Rifle Manufacturing Co.
29 Conn. 282 (Supreme Court of Connecticut, 1860)
Brinkmeyer v. Helbling
57 Ind. 435 (Indiana Supreme Court, 1877)
Kingsport Brick Corp. v. Bostwick
145 Tenn. 19 (Tennessee Supreme Court, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
152 A. 130, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hance-hardware-v-denbigh-hall-incorporated-delch-1930.