Hamtramck Housing Commission v. Siemens Industry, Inc.

CourtDistrict Court, E.D. Michigan
DecidedSeptember 11, 2025
Docket2:24-cv-13354
StatusUnknown

This text of Hamtramck Housing Commission v. Siemens Industry, Inc. (Hamtramck Housing Commission v. Siemens Industry, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hamtramck Housing Commission v. Siemens Industry, Inc., (E.D. Mich. 2025).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MICHIGAN SOUTHERN DIVISION

HAMTRAMCK HOUSING COMMISSION,

Plaintiff, Case No. 2:24-cv-13354

v. Honorable Susan K. DeClercq United States District Judge SIEMENS INDUSTRY, INC., and SIEMENS BUILDING TECHNOLOGIES, INC.,

Defendants. _______________________________________/

OPINION AND ORDER DENYING IN PART AND GRANTING IN PART DEFENDANTS’ MOTION TO DISMISS (ECF No. 8)

In 2008, Plaintiff Hamtramck Housing Commission (HHC)—a public housing authority (PHA)—selected Defendant Siemens Industry, Inc (“Siemens”)1 to conduct an energy-consumption audit of HHC’s facilities to determine whether HHC was a suitable candidate for participating in an energy performance contract (EPC) with Siemens to cut utility costs. After Siemens audited the facilities, established energy baselines from the facilities’ historical utility-usage data in the audit, and concluded that HHC was a good candidate, the parties entered a 15-year

1 “Siemens Building Technologies, Inc. has been merged into Defendant Siemens Industry, Inc. and no longer separately exists.” ECF No. 1 at PageID.2. Accordingly, the two named defendants are the same entity. EPC in 2011 with approval from the Department of Housing and Urban Development (HUD). In exchange for HHC purchasing equipment from Siemens

through an interest-bearing loan, Siemens agreed to pay HHC any annual “savings shortfall” if HUD’s utility subsidies and HHC’s energy savings did not fully cover the costs of the loan’s principal and interest.

In this case, HHC claims that Siemens committed misrepresentations in its audit and breached the contract in its sixth year by unilaterally modifying the baselines used to calculate the annual utility usage and savings shortfalls. Siemens has moved to dismiss, arguing that HHC’s claims are time-barred under the statute

of limitations and, even if timely, HHC’s misrepresentation claims fail for lack of specificity. As explained below, HHC’s breach-of-contract claim is not time-barred and

will be allowed to proceed. However, HHC’s misrepresentation claims are barred by the statute of limitations. Therefore, the motion will be granted as to those the misrepresentation claims only. I. BACKGROUND

The following factual allegations come from HCC’s complaint. ECF No. 1-1. At the motion-to-dismiss stage, these facts must be accepted as true with all reasonable inferences drawn in HCC’s favor. See Lambert v. Hartman, 517 F.3d 433,

439 (6th Cir. 2008). Beyond the pleadings, this Court also may consider documents that are public record or that are referred to in the pleadings that are integral to the claims, such as the EPC itself. Com. Money Ctr., Inc. v. Ill. Union Ins. Co., 508 F.3d

327, 335–36 (6th Cir. 2007). HHC is a public housing authority that operates two facilities for low-income residents: Senior Plaza and Colonel Hamtramck. ECF No. 1-1 at PageID.11. As a

participant in HUD’s program to provide public housing, HHC has access to HUD capital funding that “substantially pays for capital improvements of [participant facilities] when reasonably necessary . . . [for] utility-related equipment, appliances and systems.” Id. at PageID.29. HUD also “substantially subsidizes utility costs for

PHAs on an annual basis.” Id. at PageID.11. In the 2000s, HUD began encouraging PHAs to enter EPCs, i.e., “a financing technique that uses energy/electricity cost savings from reduced energy consumption to” offset costs of installing energy-

saving equipment. Id. In August 2007, “HHC issued a request for proposals” to establish an EPC, to which Siemens responded in January 2008. Id. at PageID.11–12. Siemens then conducted “an investment grade energy audit” of HHC’s facilities to determine

whether HHC was a suitable candidate for an EPC. Id. at PageID.12. Siemens determined HHC’s utility consumption for the three previous years to establish the facilities’ energy-consumption baselines. Id. Although Siemens stated that it

conducted an independent analysis of HHC’s raw utility data, id. at PageID.12–13, it was later revealed that the data came from HHC’s third-party service-provider who had prepared HHC’s annual utility-expense reports. Id. at PageID.17.

On the basis of this audit, Siemens proposed a 15-year EPC with HHC. Id. at PageID.13. HUD approved the proposed EPC on November 23, 2010, and expressly approved the energy-consumption baseline incorporated into the EPC. Id. The EPC

included a provision in which only the Contracting Officer—Kevin Kondrat, HHC’s Executive Director—could make changes to the EPC. ECF No. 8-4 at PageID.262, 293, 328. “[O]n or about January 17, 2011,” the parties entered the EPC. ECF No. 1-1 at PageID.14.

The EPC included a 15-year “interest bearing bank loan” with which HHC purchased various “energy-related equipment, appliances and systems” from Siemens to reduce utility expenses. Id. at PageID.13. The contract purchase price

was $2,470,268.00. Id. In exchange, Siemens was to pay HHC annually any “savings shortfall” in which “HUD’s utility subsidy to the HHC plus the energy cost savings experienced by the HHC as a result of the performance of the [purchased equipment] did not fully cover the HHC’s principal and interest on the bank loan” for the

equipment. Id. at PageID.14. In other words, Siemens agreed to pay HHC any shortfall amount if HHC did not save the guaranteed amount with the new equipment and baseline calculations. Id. Siemens would identify any shortfalls in its annual

reports to HHC. Id. For the first five annual reports, Siemens used the baselines established in the initial audit. Id. However, in the sixth report, HHC alleges that Siemens unilaterally

modified the baselines without the contracting officer’s approval and used the modified baselines in the sixth and seventh-year reports. Id. at PageID.15. After the seventh year, HHC challenged the calculations as allowed under Section 31 of the

EPC, resulting in a decision in HHC’s favor on June 30, 2020. Id.2 HHC further alleges that, despite that decision, Siemens continued to rely on the modified values in the subsequent reports for years eight, nine, and ten. Id. at PageID.15–16. In its year ten report, Siemens included an appendix with corrections to the

reports from years one through nine. Id. at PageID.16. That appendix explained that the data that had been used to establish the initial baselines “was flawed due to inaccurate reporting by the utility company and misallocations by HHC.” Id. at

2 For additional procedural history in Siemens’ motion, not considered but provided for context, Siemens recounts that HHC’s director and program manager then brought a qui tam action against Siemens on March 16, 2021. ECF No. 8 at PageID.123. The director and manager alleged that Siemens deliberately overstated the water value to secure a higher level of government funding. Id. In 2024, Siemens settled without admitting liability. Id.; see United States et al. v. Siemens Corp. et al., No. 2:21-cv-10594, slip op at 1–2 (E.D. Mich. Mar. 16, 2021) (ordering a dismissal of the case “for the purpose of effectuating a settlement agreement”). PageID.17.3 Siemens eventually issued a letter to HHC on July 27, 2023, terminating the EPC. Id. at PageID.16.4

HHC claims that Siemens’ modification of the baselines was a breach of contract for “failing to use contractually required, HUD approved baseline consumption values” and for modifying these values unilaterally instead of through

the Contracting Officer who, according to Section 28 of the EPC, has sole authority to modify the contract. Id. at PageID.14–15.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Jones v. Bock
549 U.S. 199 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Boyle v. General Motors Corp.
661 N.W.2d 557 (Michigan Supreme Court, 2003)
Lambert v. Hartman
517 F.3d 433 (Sixth Circuit, 2008)
Buntea v. State Farm Mutual Auto Insurance
467 F. Supp. 2d 740 (E.D. Michigan, 2006)
Cataldo v. United States Steel Corp.
676 F.3d 542 (Sixth Circuit, 2012)
QQC, INC. v. Hewlett-Packard Co.
258 F. Supp. 2d 718 (E.D. Michigan, 2003)
Travis v. ADT Security Services, Inc.
884 F. Supp. 2d 629 (E.D. Michigan, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Hamtramck Housing Commission v. Siemens Industry, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/hamtramck-housing-commission-v-siemens-industry-inc-mied-2025.