Hammond v. Miller

13 D.C. 145
CourtDistrict of Columbia Court of Appeals
DecidedDecember 18, 1882
DocketLaw. No. 21,785
StatusPublished
Cited by1 cases

This text of 13 D.C. 145 (Hammond v. Miller) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hammond v. Miller, 13 D.C. 145 (D.C. 1882).

Opinions

Mr. Justice Cox

delivered the opinion of the court.

On the 3rd of July, 1879, a contract was made between William Lawson and William H. Hazle on the one part, and -James E. Miller on the other, that the firm of Lawson & [146]*146Hazle were to erect three houses for Miller on a lot of ground owned by him, at an aggregate cost of $8,499. The price was to be paid in seven different instalments, the last instalment when the houses were completed and the keys turned over to defendant Miller; with this exception, that 25 per cent, was to be reserved from each instalment and retained by Miller until thirty days after the dwelling-houses should have been completed and the keys of the same turned over by Lawson & Hazle, or their representatives, to him. The houses were to be completed iu four months; that is, by the third of November ; and it was stipulated that if the contractors should fail to complete them within the four months, Miller should have the right to charge them $50 for each week of delay in the completion. It was further stipulated that if the contractors should fail to finish the houses within a period of Jive months from the execution of the contract, Miller should have “ full power and authority to employ other person or persons to finish and complete the said dwelling-houses or residences, at the cost and expense of the said Lawson & Hazle, their executors, &c.; which cost will and can be deducted' by said Miller from any money which may be in his possession at the time of said failure ” on the part of Lawson & Hazle to complete the dwelling-houses, &c.

Lawson & Hazle employed this plaintiff, John B. Hammond, as sub-contractor, to furnish certain materials, doors, windows, blinds, &c., but Hammond was unwilling to deliver these materials on the credit of Lawson & Hazle only, and required an order upon the defendant, the owner of the ground, and the acceptance of such order by him before he would deliver the materials. Accordingly, Lawson & Hazle made this order:

“ Sir : You will please pay John B. Hammond for materials for your three houses, which we are erecting for you, &c., * * * the sum of $796.54, and deduct the same out of payment which will be due us on the completion of said houses.”

On the paper was written: “ This order is hereby accepted, [147]*147payable when Messrs. Lawson & Hazle complete the three houses herein stated; that is, per contract. James E. Miller.”

Lawson & Hazle failed to complete the houses by the-third of November, and thirty days more time was given them. They failed to complete them by that time, and' after having done perhaps three-fourths of the work, they formally abandoned the contract and refused to complete the houses. The defendant, Miller, after importuning them to go on with the work, and calling upon the plaintiff also, in his own interest, to prevail upon them to complete the houses, seems to have acted upon the assumption that there was no more to be expected from them, and to have taken possession of the houses. Having taken possession, he entered into new contracts in his own name with other parties and went on to finish the houses at his own expense. At the time when Lawson & Hazle formally refused to go on with the work, Miller had paid them all that was due them for the work already done, and a little over, including even the 25 per cent, which, by the contract, he had been entitled to reserve; so that at- that time he owed them nothing. As I have said, he then proceeded to finish the houses himself, under new contracts with other persons. In making these new contracts, he effected a saving, upon the price stipulated in the original contract, of $382.19 ; that is, he got the work done for so much less than Lawson & Hazle would have been entitled to if they had done the work under their contract.

Then this plaintiff, Hammond, the sub-contractor, sued Miller upon this accepted order, calling it a bill of exchange, and included in his declaration the common counts. At the trial below, several exceptions were taken to the ruling of the court, but the most important one relates to the last instruction which the judge gave the jury, to return a verdict in favor of the plaintiff for the sum of $382.19, the amount found in the defendant’s hands after he had completed the houses. To that instruction of the court the defendant excepted. Now, in giving this instruction, the court below [148]*148clearly proceeded upon the theory that when the defendant took possession of the unfinished houses and completed them, he did so in the interest of the defaulting contractors and substantially as their agent, and that the defaulting contractors, being chargeable with the cost of building the houses, were entitled to credit for the balance of the contract price. This leads us to consider what are the rights of a contractor who has partly performed his contract and then refuses to complete it. ¥e speak now in the first instance of his rights at common law independent of any special provision such as is contained in this contract, and is relied upon particularly by the plaintiff". It is perfectly well settled at common law that if a man partly performs his contract and then refuses to complete it, he has no right of action upon the contract even for the work which has been done. The later authorities go further than -that. For instance, the rule is laid down in 2 Smith’s Leading Cases, (Am. Ed. Hare’s Notes, p. 25), in comments upon the case of Cutter vs. Powell: “ But if there has been an entire ■executory contract, and the plaintiff has performed a part of it, and then wilfully refuses, without legal excuse and against the defendant’s consent, to perform the rest, he can recover nothing, either in general or special assumpsit.”

But there are cases which hold that where the work has been partially performed and is accepted even under compulsion, that' is, where it cannot be avoided by the other party, that fact alone raises an implied assumpsit to pay the reasonable value of the work which has been so accepted and used. But it is perfectly clear that even if the party can recover upon the contract for work which is already done, he cannot recover upon the contract for work which he did not do and which he refused to do. His rights under the contract are gone when he abandons it, and the other party has a right to treat it at once as at an end. In this case the owner had paid for all the work that had been done. He had the right, immediately upon the default of the contractors, to take possession of the unfinished houses, as he did take possession of them, and to finish them if he pleased, or [149]*149to sell them to somebody else, or to employ other persons to do the work which the contractors had been engaged to do and had refused to do. Under no such circumstances can it be conceived that the contractors so in default could have a claim upon the owner of the land. They certainly could not sue upon an implied assumpsit for work which had been done by other people. They certainly could Dot sue upon the contract, because they would have been compelled either to aver and prove that they had performed the contract, or to aver a readiness to perform it, and that they were prevented from doing so by the other party.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fleming v. Twine
58 A.2d 498 (District of Columbia Court of Appeals, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
13 D.C. 145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hammond-v-miller-dc-1882.