Hammond v. Knievel

378 P.2d 388, 141 Mont. 433, 1963 Mont. LEXIS 154
CourtMontana Supreme Court
DecidedJanuary 30, 1963
Docket10426.
StatusPublished
Cited by14 cases

This text of 378 P.2d 388 (Hammond v. Knievel) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hammond v. Knievel, 378 P.2d 388, 141 Mont. 433, 1963 Mont. LEXIS 154 (Mo. 1963).

Opinion

MR. JUSTICE JOHN C. HARRISON

delivered the Opinion of the Court.

This is an appeal by the defendants from a judgment for the plaintiff in an action to foreclose a mechanic’s lien.

The action was brought in the district court for Silver Bow County by the plaintiff-respondent, Hammond-Everly Engineering Co., hereinafter referred to as plaintiff, against Ignatius J. Knievel, hereinafter referred to as defendant, and Emma Frances Knievel, his wife.

In 1956, Emma Frances Knievel was the owner of property situated at 112 Galena Street, Butte, Montana, and also the lot adjacent thereto. At that time, defendant was the duly authorized sales representative for Volkswagen automobiles. Defendant’s sales and service facilities were limited at that time, and accordingly he was under pressure from the factory representative to expand his facilities.

*435 The lot adjacent to 112 Galena Street was vacant except for the remains of a building destroyed by fire many years previous. The lot sloped from front to rear with almost a one story differential between the two.

Defendant conceived the idea of constructing a structure that would have a street level sales floor, and repair facilities in the basement with access to the latter from the alley. Because of the cost involved, defendant decided to get by with a temporary structure at street level built on the roof-deck of the basement garage.

Defendant contacted Elmo A. Briggs of Butte for the purpose of getting an estimate of the cost to construct such a structure with a 32 by 50 foot sales room on the street level. The method of construction contemplated at that time involved the use of many supporting posts. An estimate of $31,285 was submitted by Mr. Briggs on September 5, 1956.

Defendant on his own initiative, also contacted Montana Concrete Industries, Inc., concerning the use of pre-stressed concrete planks. Such use would greatly reduce the number of supporting members, and thereby increase the usable area of the basement garage. Through Montana Concrete Industries, Inc., defendant had Norman J. Hamill, an architect, make a preliminary rough sketch of the proposed structure.

In November 1956, two months after the Briggs’ estimate, defendant first contacted the plaintiff concerning the possibility of their doing the construction work. Following that first meeting there were several meetings in which certain changes were discussed and during which the defendant abandoned the idea of constructing a temporary building at street level. Defendant’s plan at that time contemplated using the roof of the garage as an open sales area.

Plaintiff testified that in December of 1956, a cost plus ten percent contract was being formulated between the parties at an estimated cost of $32,500. This was an oral estimate.

On January 19, 1957, plaintiff forwarded a letter to the de *436 fendant reciting therein an estimated cost of $22,750 exclusive of certain extras. Plaintiff’s testimony is that the only purpose of the letter was to help defendant deceive a bank as to the actual cost of the proposed building, and that the defendant was to pay additional money over and above the estimated cost mentioned in the letter. The defendant denies this. Defendant’s uncontradicted testimony is to the effect that this letter was never shown to any bank. Further, plaintiff applied for a building permit from the City of Butte for a building of the value of $18,000 to $20,000 and no change was ever made in the permit to reflect a higher cost.

Plaintiff asserts that the final contract, on a cost plus ten percent basis, was agreed upon by the parties about March 28, 1957. Defendant denies the existence of such contract.

Defendant contends that much of the difficulty stems from the fact that the plaintiff firm is a mining engineering firm. Even if this were so, it was the defendant who contacted the plaintiff to do the job. Moreover, plaintiff testified to extensive prior construction experience involving concrete works. From the extensive list of clients, it is obvious that the plaintiff has had considerable experience in the construction field.

On April 17, 1957, before construction had begun on the new structure, a small fire damaged a portion of the existing building located at 112 Galena Street. Defendant asked the plaintiff to make certain repairs and also to make certain structural changes in the building to facilitate entrance to the new building. No method of payment or agreement as to cost was made at that time. Later an estimate of the cost of repairing the fire damage was presented to the defendant, and the amount thereof was paid over to the plaintiff following a recovery on the fire insurance policy.

On April 18, 1957, construction work began. The first work necessary was the removal of an old concrete floor remaining from the ruins. Thereafter, footings were laid, and fol *437 lowing that walls and columns were added. Thereafter the pre-stressed concrete planks were placed, and then the roof itself was poured and bonded to the pre-stressed planks.

The defendant admitted that certain extra work not previously contemplated became necessary as the work progressed. It was found necessary to remove considerable more of the old floor than was originally contemplated. Erosion was found to have materially weakened the sidewalk in front and the curbing as well. These had to be replaced with new materials. A wall existing on the premises was considered as a possible support for the concrete plank, but the wall was found to have suffered damage by the lateral pressure of the adjoining soil, in fact it caved in during the construction work. This wall had to be torn down, hauled away and a new one constructed to take its place.

On July 15, 1957, while work was still progressing, the plaintiff submitted estimate number one, which included costs up to July 1. This estimate was for an amount of $27,790.60, and at that time the defendant paid the plaintiff $10,000.

Sometime in November 1957, the plaintiff finished the job and removed all tools, equipment and workers from the premises.

On December 3, 1957, plaintiff submitted “estimate number 3” which indicated an additional $12,645.22 was owing. The entire balance due as of that estimate was $30,435. That same day an estimate for the fire repair damage in the amount of $781.97 was prepared. In January 1958, plaintiff received the check for $781.97. No further payment has been received from the defendant, although the defendant has tendered the sum of $19,848.35 which sum represents the claimed balance due on the alleged “contract” sum plus payment for the admitted extras.

There is no dispute that the basement was not fit for use. The concrete slab poured over the pre-stressed concrete planks expanded more than the plaintiff allowed for and as a result *438 the roof leaked at the expansion joints and also through other cracks which developed in the concrete. Moreover concrete is not impervious to water, and moisture condensation also added to the water dripping through the roof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Messick v. PHD Trucking Service, Inc.
615 P.2d 1276 (Utah Supreme Court, 1980)
Merritt v. Merritt
526 P.2d 1375 (Montana Supreme Court, 1974)
Figgins v. Stevenson
517 P.2d 735 (Montana Supreme Court, 1973)
Tindall v. Negaard
Montana Supreme Court, 1973
Hanlon v. Anderson
Montana Supreme Court, 1972
Peery v. Higgins
447 P.2d 481 (Montana Supreme Court, 1968)
Finley v. Rutherford
444 P.2d 306 (Montana Supreme Court, 1968)
Eliason v. Eliason
443 P.2d 884 (Montana Supreme Court, 1968)
Boehler v. Sanders
404 P.2d 885 (Montana Supreme Court, 1965)
Frank J. Trunk & Son, Inc. v. DeHaan
391 P.2d 353 (Montana Supreme Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
378 P.2d 388, 141 Mont. 433, 1963 Mont. LEXIS 154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hammond-v-knievel-mont-1963.