Opinion

Mr. Justice Walker

delivered the opinion of the Court:

Appellee was employed on the first of January, 1873, by Hamlin, Hale & Co., as a salesman in their store, for one year, at a salary of $1020, in monthly installments of $85. They, on the 23d of June following, dismissed him from their service, when they offered to pay him the amount that was due him to that date, which he declined to receive, and on the 6th of the following August brought this suit, to recover the balance for the full year, and on a trial in the court below recovered the full amount.

The declaration was in assumpsit, and contains a special count, with the usual common counts. The plea of the general issue was filed, and on the trial the defense relied on was, that appellee was discharged for good and sufficient cause. It is contended that appellee was insolent to his employers, and coarse and vulgar in his conduct, to such an extent as fully justified appellants in discharging him. This was a question of fact for the determination of the jury. All will at once concede that an employee must be respectful, and obedient to all reasonable commands of his employers, and those having control of the business in which he is employed; and no one will dispute that a person so employed, when engaged in the discharge of his business, and in his intercourse with customers and persons transacting business with the house and with his employers, and those having charge of the business, must be respectful, and must abstain from all vulgarity and obscenity of language and conduct. If wanting in any of these requirements, it would be grounds for discharging a salesman in a store from his employment.

But the question raised and pressed on our consideration is, as to the measure for the recovery of damages in the case, appellants contending that appellee was, in no event, on the pleadings in the case, entitled to recover more than was due at the time he brought his suit; that, under the pleadings, he can not recover for the monthly installments, or any of them, which accrued after the suit was brought. On the other hand it is urged, that, as the year for which appellee was engaged had fully expired before the suit was tried, he was entitled to recover the unpaid balance of the $1020 which appellants had agreed to pay him.

Appellants contend, that, inasmuch as appellee did not, when he was discharged, terminate the contract or elect to so treat it, but, on the contrary, considered it as still subsisting, and was ready and willing to perform it in full, if required, he can only claim as damages in this suit the amount that would have been due him at the time the suit was commenced, had he continued in the employment of appellants; that if he desired to recover damages beyond that sum, he should, when discharged, have notified appellants that, as they had chosen to terminate the contract, he would treat it as rescinded, and hold them for all damages he had sustained by their terminating the agreement.

This precise question, in the shape now presented to the court, has never been passed upon by us, although analogous questions may have been.

The law is well settled, that, on a contract for the payment of money by installments, assumpsit will usually lie to recover each installment as it falls due, without waiting for the last to mature. 1 Chit. Pl. 116. Here was a sum of money to be paid by monthly installments; and there can be no doubt that appellee, at the end of each month, could have sued for and recovered for the installment which accrued and became due at that time. But it is equally well settled that a party can not, when he sues for an installment which is due, recover for installments not due when the suit was brought. And where the declaration showed, by its averments, that a recovery of installments not due was claimed, and there was a general verdict, the courts considered it ground for arresting the judgment, because the plaintiff was not entitled to recover for the portion claimed in the declaration, which was not due at the institution of the suit. If it were necessary to cite authorities on so simple and well settled a proposition, we might refer to note 1, to the case of Hambleton v. Veere, 2 Saund. R. 171 a and b, and the cases therein cited ; Gordan v. Kennedy, 2 Binn. 287, and the authorities there referred to by the court.

We had supposed no rule was more inflexible or better established than that a plaintiff can not recover for money not due at the institution of the suit. Gordan v. Kennedy, supra; 1 Chit. Pl. 372; Cunningham v. Morrell, 20 J. R. 203 ; McLure v. Rush, 9 Dana, 64; Allen v. Sanders, 7 B. Monr. 593; Kettle v. Harvey, 21 Verm. 301; Lord v. Belknap, 1 Cush. 279; and Tompkins v. Elliott, 5 Wend. 496. If this rule could be seriously questioned, other cases could be referred to as establishing the rule; but, to our minds, it requires no authority, as it is based upon principles obviously just.

If, then, a party can not sue for and recover a debt or claim before it is due, why should he do, indirectly, the same thing by suing for a small part when due, and recovering a greater and more substantial part accruing after the suit has been brought ? The law never permits that to be done indirectly which it prohibits from being done directly. To permit the recovery of the sums falling due after suit brought, would be an evasion of the rule that the cause of action must be complete when suit is brought. It would be without analogy to any rule of law which now occurs to us. In the case of Crab-tree v. Hagenbaugh, 25 Ill. 233, it was said, that where a party sued for the breach of an independent portion of a contract, he might recover for its breach, though his recovery would be limited to the damages sustained at the time the suit was commenced. We have no hesitation in holding that appellee was only entitled to recover for the amount that would have been due had he continued in the service of appellants at the time the suit was instituted, and the court below erred in admitting evidence of the installments that would have matured afterwards.

Suppose that, after the suit had been brought, appellants had demanded of appellee the fulfillment of his part of the contract, and he had refused them, what would have been the measure of damages ? Obviously not more than the wages which had accrued up to the time of the demand. Then why permit a recovery beyond the damages sustained when suit was brought ? Or, suppose a trial had been had ten or fifteen days after suit was brought, and the same damages as were recovered in this case had been allowed, and after the recovery appellants had demanded of appellee to go on and perform his contract, and he had refused, would appellants have been compelled to sue and recover the amount back ? Yet such a thing might occur, when the plaintiff is still insisting upon being allowed to perform his part of the agreement. Such a state of things would be an anomaly. If he insists upon going on with his part of the agreement, he should sue when each installment occurs, or wait till the end of the time, and sue for the whole.

At common law it was a ground of arrest to claim such installments in the declaration ; so it is a ground requiring the granting of a new trial, to permit proof of the same, unless it is apparent that it was not considered by the jury, and was excluded from the verdict.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Myers v. Mundelein College
Appellate Court of Illinois, 2002
Munoz v. Expedited Freight Systems, Inc.
775 F. Supp. 1181 (N.D. Illinois, 1991)
Kemnetz v. Elliott Farmers Grain Co.
482 N.E.2d 1076 (Appellate Court of Illinois, 1985)
Anthony J. Gasbarra v. Park-Ohio Industries, Inc.
655 F.2d 119 (Seventh Circuit, 1981)
Keel v. Illinois Terminal Railroad
104 N.E.2d 659 (Appellate Court of Illinois, 1952)
Magnusen v. Klemp
89 N.E.2d 533 (Appellate Court of Illinois, 1949)
Ginsburg v. Prudential Insurance Co. of America
13 N.E.2d 792 (Appellate Court of Illinois, 1938)
United States v. Worley
42 F.2d 197 (Eighth Circuit, 1930)
United States v. Worley
281 U.S. 339 (Supreme Court, 1930)
Brownholtz v. Providers Life Assurance Co.
236 Ill. App. 494 (Appellate Court of Illinois, 1925)
Wade v. Hefner
84 S.E. 598 (Court of Appeals of Georgia, 1915)
Greenwald v. Ruby
178 Ill. App. 415 (Appellate Court of Illinois, 1913)
Doherty v. Schipper & Block
95 N.E. 74 (Illinois Supreme Court, 1911)
Alexander v. Potts
151 Ill. App. 587 (Appellate Court of Illinois, 1909)
Bates v. Winifrede Coal Co.
1 Hosea's Rep. 225 (Ohio Superior Court, Cincinnati, 1907)
Shields v. Carson
102 Ill. App. 38 (Appellate Court of Illinois, 1902)
McCormick Harvesting Machine Co. v. Cordsiemon
101 Ill. App. 140 (Appellate Court of Illinois, 1902)
Bacon v. Schepflin
56 N.E. 1123 (Illinois Supreme Court, 1900)
Bacon v. Schepflin
85 Ill. App. 553 (Appellate Court of Illinois, 1899)
Monarch Cycle Mfg. Co. v. Mueller
83 Ill. App. 359 (Appellate Court of Illinois, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
78 Ill. 422, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hamlin-hale-co-v-race-ill-1875.