Hamilton v. Title Ins. Agency of Tampa, Inc.

338 So. 2d 569
CourtDistrict Court of Appeal of Florida
DecidedOctober 27, 1976
Docket75-765, 75-803
StatusPublished
Cited by17 cases

This text of 338 So. 2d 569 (Hamilton v. Title Ins. Agency of Tampa, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hamilton v. Title Ins. Agency of Tampa, Inc., 338 So. 2d 569 (Fla. Ct. App. 1976).

Opinion

338 So.2d 569 (1976)

H.S. HAMILTON, Appellant.
v.
TITLE INSURANCE AGENCY OF TAMPA, INC., Appellee.
TITLE INSURANCE AGENCY OF TAMPA, INC., Appellant,
v.
H.S. HAMILTON, Appellee.

Nos. 75-765, 75-803.

District Court of Appeal of Florida, Second District.

October 27, 1976.

*570 Marjorie D. Gadarian of Jones, Paine & Foster, West Palm Beach, for appellant-appellee H.S. Hamilton.

John W. Frazier of Peavyhouse, Giglio, Grant, Clark & Charlton, Tampa, for appellant-appellee Title Ins. Agency.

HOBSON, Judge.

These are consolidated appeals from a final judgment ordering the defendant, Title Insurance, to return $12,500 of a $25,000 earnest money deposit, paid by the plaintiff, Hamilton, pursuant to a real estate contract, and allowing Title Insurance to keep the remaining $12,500. The trial court held both parties at fault for the failure of the contract. We reverse.

On September 10, 1973, Hamilton contracted with Title Insurance to purchase certain real estate in Temple Terrace, Florida for $500,000. The contract reveals this land was to be utilized to build some 295 dwelling units. The contract further provided for the plaintiff to pay a $25,000 earnest money deposit, to be made at execution, and another payment in like amount was to be made within 90 days. Section seven of the contract specifically made the closing of this sale contingent upon the purchaser/plaintiff's ability to secure building permits for the units. Failure to obtain such permits required the seller/defendant to return both deposits. In addition to the contingency of obtaining building permits,[1] section seven further provided "[T]hat this contract is contingent upon the fact that there shall be water and sewer to the property line at no cost to the Purchaser."[2]

In late September of 1973, the plaintiff hired a civil engineering firm to prepare plans and specifications for the development. This engineering firm was to prepare preliminary plans for water and sewage facilities and to make application for the necessary approvals to state and local health departments, pollution control units and the City of Tampa. In November of 1973 the plaintiff was advised that a sewer and water moratorium had just gone into effect. As a result of this moratorium, and following the engineering firm's application to water and sewage authorities, the plaintiff contacted the defendant, informing the latter of the problem and expressing that he was not in a position to pay the second earnest money installment of $25,000.

On December 17, 1973, the parties negotiated an addendum to the original contract which provided for payment of the second $25,000 installment on that date with refund of the same should the plaintiff fail to obtain the building permits by January 3, 1974.[3] The plaintiff failed to obtain the *571 necessary permits by the agreed upon date in the addendum. Even after this date the parties met and negotiated in an attempt to complete the purchase agreement. The moratorium having blocked successful acquisition of the building permits, the plaintiff demanded a return of the deposit. Upon refusal by the defendant this suit was instituted.

It is clear from the language of the contract ("[I]n the event such building permits are not secured ... the two (2) earnest money deposits ... each shall be returned ..."), as modified by the addendum ("In the event that the purchaser is unable to obtain the said permits ... the seller agrees to refund the ... deposit ...), that the entire contract's performance was dependent and conditioned upon the plaintiff's procurement of these permits.

Indeed the express condition precedent was contractually tempered with a provision for insuring the exercise of reasonable efforts and diligence by the plaintiff in seeking those permits. The issue for determination then is whether the plaintiff exercised such effort and diligence in attempting to secure these permits sufficient to justify the return of the $25,000 deposit specified in the addendum to the contract.

The parties have correctly asserted that one who prevents or makes impossible the performance or happening of a condition precedent, upon which his liability by the terms of a contract is made to depend, cannot avail himself of its nonperformance. Walker v. Chancey, 96 Fla. 82, 117 So. 705 (1928); Hart v. Pierce, 98 Fla. 1087, 125 So. 243 (1929). Such a situation is not presented here. In fact, the plaintiff, Hamilton, was expressly bound to use reasonable efforts and diligence in seeking these permits. Cf. Chancey, supra (recognizing implied obligation to use reasonable diligence). Here the record clearly reveals extensive and concerted efforts by Hamilton to obtain clearance for the building permits from the city. The actions taken by Hamilton immediately following execution of the original agreement, and up to and after the signing of the addendum, demonstrate a sincere desire to complete the contract as agreed upon. This conclusion is further evidenced by Hamilton's repeated attempts, after expiration of agreed upon date, to go forward with the contract by attempting to secure clearances with state and county health and pollution authorities.

The general rule, recited in 17 Am.Jur.2d, Contracts § 361, provides:

"Where parties capable of contracting deliberately enter into a written contract by which there is created a condition precedent to a right of action, such condition must be performed or its requirements waived or excused."

Similarly, Florida law requires that performance of conditions precedent, or a valid excuse for nonperformance, be made to appear. Ballas v. Lake Weir Light & Water Co., 100 Fla. 913, 130 So. 421 (1930); Maryland Casualty Company v. Hallatt, 295 F.2d 64 (5th Cir.1961).

Although neither party has argued that the doctrine of impossibility of performance *572 is applicable to the instant case, and while we agree with that premise,[4] the moratorium passed subsequent to execution of the original contract, and continuing up to and past the allotted times for performance of the condition precedent, was sufficient to render Hamilton's nonperformance excused. This conclusion is strengthened by the language in the original contract, "[I]n the event such building permits are not secured ..." and the addendum, "In the event that the purchaser is unable to obtain the said permits... ." Both of these contract provisions clearly contemplate that the defendant assumed the risk of subsequent governmental interference.

Furthermore, no evidence suggests that the parties were informed of this moratorium prior to or at the time of contracting. Since neither party can be held to have foreseen this subsequent interference, then no reason exists for shifting the burden of this risk as allotted by the parties in their contract and the addendum.

We recognize that in cases tried without a jury a lower court's findings are entitled to the weight of a jury verdict and must not be disturbed unless there is a total lack of substantial evidence to support the trial judge's findings. Richards v. Dodge, 150 So.2d 477 (Fla.2d DCA 1963). However, misinterpretation of the legal effect of the facts so found can result in reversible error. Richards, supra. Here there was no substantial evidence to support the lower court's judgment that both parties were equally at fault.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dean v. Dean
665 So. 2d 244 (District Court of Appeal of Florida, 1996)
Porkolab v. Smithbay Homes, Inc.
640 So. 2d 195 (District Court of Appeal of Florida, 1994)
LaFaye v. Presser
554 So. 2d 610 (District Court of Appeal of Florida, 1989)
L.J. Clark Construction Co. v. Hardrives Co.
547 So. 2d 963 (District Court of Appeal of Florida, 1989)
In the Interest of R.D.D.
518 So. 2d 411 (District Court of Appeal of Florida, 1988)
In Interest of RDD
518 So. 2d 412 (District Court of Appeal of Florida, 1988)
Sirkin v. Hutchcraft
507 So. 2d 765 (District Court of Appeal of Florida, 1987)
Cohen-Ager, Inc. v. State
504 So. 2d 1332 (District Court of Appeal of Florida, 1987)
Petersen v. Powell
501 So. 2d 140 (District Court of Appeal of Florida, 1987)
Gulfside Supply, Inc. v. Fred Curtis, Inc.
464 So. 2d 585 (District Court of Appeal of Florida, 1985)
Greco v. Tampa Wholesale Co.
417 So. 2d 994 (District Court of Appeal of Florida, 1982)
Gruman v. State, Dept. of Revenue
379 So. 2d 1313 (District Court of Appeal of Florida, 1980)
Hunter v. City of Tampa
379 So. 2d 426 (District Court of Appeal of Florida, 1980)
Smith v. Department of Revenue
376 So. 2d 421 (District Court of Appeal of Florida, 1979)
Lee v. Bowlerama Enterprises, Inc.
368 So. 2d 913 (District Court of Appeal of Florida, 1979)
Kittay v. Weinkle
363 So. 2d 159 (District Court of Appeal of Florida, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
338 So. 2d 569, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hamilton-v-title-ins-agency-of-tampa-inc-fladistctapp-1976.