Hamilton Properties, Inc. v. Associated Grocers Inc.

925 P.2d 1237, 144 Or. App. 171, 1996 Ore. App. LEXIS 1471
CourtCourt of Appeals of Oregon
DecidedOctober 16, 1996
DocketC940838CV; CA A90081
StatusPublished
Cited by2 cases

This text of 925 P.2d 1237 (Hamilton Properties, Inc. v. Associated Grocers Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hamilton Properties, Inc. v. Associated Grocers Inc., 925 P.2d 1237, 144 Or. App. 171, 1996 Ore. App. LEXIS 1471 (Or. Ct. App. 1996).

Opinion

*173 EDMONDS, J.

Plaintiff moved for summary judgment in this breach of contract action on the issues of liability and damages, and defendant filed a cross-motion for summary judgment on the same grounds. The trial court granted plaintiffs motion, denied defendant’s motion, and entered judgment in favor of plaintiff. ORCP 47. Plaintiff then moved for entry of an amended judgment to include prejudgment interest. The trial court granted plaintiff’s motion and entered an amended judgment that included prejudgment interest. Defendant appeals, and we reverse.

The dispute in this case involves a proposed grocery store project that was to be built on a six-acre parcel of real property owned by plaintiff in the City of Tigard (City) just off of Interstate Highway 5 at the intersection of 72nd Avenue and Durham Road. Plaintiff, a real estate developer, and defendant, a wholesale grocery distributor, entered into a letter of intent in December 1992, contemplating that plaintiff would construct the development and lease it to defendant. The letter was preliminary and subject to the following conditions: (1) a mutual agreement on a site plan; and (2) satisfactory evidence that plaintiff could obtain City approval for the construction of a food store similar to a store that defendant had constructed in Roseburg. The letter of intent also provided that plaintiff would construct the grocery store in compliance with detailed plans and specifications that would be provided by defendant’s architect and that the parties would agree on those plans and specifications before the commencement of construction. The letter further provided that a final copy of the plans and specifications for defendant’s Roseburg store would be provided to plaintiff and would serve as a model for the final plans for the City project.

As a result of the letter of intent, plaintiff entered into a fee agreement in January 1993 with a real estate brokerage firm in which plaintiff agreed to pay the firm $187,500, once the lease had been executed between plaintiff and defendant. Apparently, the firm had procured defendant as the tenant for plaintiffs proposed development. Thereafter, plaintiff and defendant entered into an executory commercial lease and a construction agreement in August 1993. *174 In general terms, the construction agreement, which was incorporated into the lease agreement, provided that plaintiff would construct the store building, the parking lot, and the other on-site and off-site improvements according to defendant’s specifications. The agreement refers to an attachment, Exhibit B, which is a site plan for all on- and off-site improvements. Defendant, in turn, agreed to lease the property from plaintiff for 20 years.

The parties executed the lease and construction agreement before obtaining land use approval for the project. In September 1993, plaintiff applied to City for land use approval and site development review of the project. During the review process, plaintiff worked with its engineering consultants to address concerns expressed about the project by City and other parties affected by the proposed development. The parties anticipated that City would approve a site plan, because a grocery store was an approved use on the site and the site plans for the project were prepared by the architect and the engineer for the project to conform to applicable City standards. It is uncontradicted that plaintiff informed defendant of all proposed changes submitted to City, but defendant denies that it ever agreed to them.

In December 1993, City granted site development review approval subject to a number of conditions that differed from Exhibit B. City required that those conditions be satisfied before the issuance of a building permit. After the approval, defendant wrote a letter to Tri-Met (a third party affected by the development) stating that it had recently approved the site development review application and that it was committed to accomplishing the improvements to the intersection as recommended by the engineering traffic report for the project. However, defendant later determined that the approved plan would not yield a profitable store. In February 1994, defendant notified plaintiff that it intended to terminate the project. Plaintiff responded by demanding reimbursement under paragraph 2.3 of the construction agreement for its expenses and, subsequently, it filed this action.

Plaintiff moved for summary judgment in the litigation, arguing that “[p]laintiffs right to liquidated damages *175 from [d]efendant [under paragraph 2.3] * * * became absolute when defendant and its architect failed to supply approved plans and specifications for the site improvements to plaintiff.” Paragraph 2.3 of the construction agreement provides:

“Promptly (within 15 days after receipt of City of Tigard Preliminary Site Design approval) following mutual execution of the Lease and this Construction Agreement, [defendant] shall deliver to Architect information and drawings outlining in reasonable detail [defendant’s] requirements and specifications as to the Building and related improvements. Thereafter, Architect shall promptly (within 60 days after receipt of City of Tigard Preliminary Site Design approval) prepare the Building Plans and Specifications for the Building and related improvements based upon the information furnished by AG (revised to comply with City of Tigard Preliminary Site Design approval) and based upon the description of [plaintiffs] and [defendant’s] work in this Construction Agreement. [Plaintiff] and [defendant] recognize that time is of the essence of this Agreement and that [plaintiff] will suffer financial loss if [defendant] and/or its Architect do not deliver approved Plans and Specifications to [plaintiff] within the times specified herein. Accordingly, the parties agree that as liquidated damages for any such delay (but not as a penalty) [defendant] shall reimburse [plaintiff] for any costs incurred for this project by such time. * * * The following are estimates of the costs expected to be so incurred to be paid by [defendant] to [plaintiff]: one-half real estate broker fee, $190,000; Accounting, $5,000; Legal fees, $6,000; Engineering fees, $40,000; permit fees, $200,000. This provision only limits damages if such delay occurs prior to the time construction commences.” (Emphasis supplied.)

Defendant countered that the phrase “within 15 days after receipt of City of Tigard Preliminary Site Design approval” was a condition precedent to its obligations under the agreement that never occurred because City did not approve the site plan contained in Exhibit B. The trial court rejected defendant’s argument and granted summary judgment to plaintiff. After the court granted summary judgment, defendant filed its notice of appeal. Plaintiff then filed a motion for entry of an amended judgment to include prejudgment interest, which the court granted.

*176 First, we turn to the assignments of error pertaining to the summary judgment. Summary judgment is appropriate if the moving party can show that the pleadings, depositions and affidavits contain no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. ORCP 47C; Jones v. General Motors Corp., 139 Or App 244, 911 P2d 1243,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grady v. Cedar Side Inn, Inc.
963 P.2d 36 (Court of Appeals of Oregon, 1997)
Outdoor Media Dimensions Inc. v. State
945 P.2d 614 (Court of Appeals of Oregon, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
925 P.2d 1237, 144 Or. App. 171, 1996 Ore. App. LEXIS 1471, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hamilton-properties-inc-v-associated-grocers-inc-orctapp-1996.