Hallicrafters Co. v. Moore

728 P.2d 441, 102 Nev. 526, 1986 Nev. LEXIS 1618
CourtNevada Supreme Court
DecidedDecember 4, 1986
Docket17387
StatusPublished
Cited by20 cases

This text of 728 P.2d 441 (Hallicrafters Co. v. Moore) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hallicrafters Co. v. Moore, 728 P.2d 441, 102 Nev. 526, 1986 Nev. LEXIS 1618 (Neb. 1986).

Opinion

OPINION

Per Curiam:

This is an appeal from a partial summary judgment certified as final pursuant to NRCP 54(b) by the district court. Appellant Hallicrafters Company has requested that we determine whether this court has jurisdiction to entertain this appeal. In essence, Hallicrafters moves this court to dismiss.

Hallicrafters contends that, because all of respondent’s causes of action arise out of a related series of transactions, respondent’s complaint alleges only one claim for relief. See Mid-Century Ins. Co. v. Cherubini, 95 Nev. 293, 593 P.2d 1068 (1979); Las Vegas Hacienda v. G.L.M.M. Corp., 93 Nev. 177, 561 P.2d 1334 (1977). Hallicrafters argues, therefore, that the partial summary judgment was not amenable to certification pursuant to NRCP 54(b).

Separate causes of action may frequently state only a single *528 claim for relief for purposes of NRCP 54(b) when they arise out of a single transaction, or a series of related transactions. Multiple claims for relief can arise, however, from a single transaction, or a series of related transactions, in some circumstances. In this case, all of respondent’s causes of action appear to have arisen out of the same transaction or series of related transactions. Respondent’s complaint, however, states more than one claim for relief for purposes of NRCP 54(b). Four of respondent’s causes of action are based on the alleged breach of a stock purchase agreement. An additional two causes of action allege the breach of a separate, but related, consulting agreement. The remaining causes of action sound in tort, alleging fraud and misrepresentation in inducing respondent to enter into the contracts referred to in the prior causes of action. Thus, respondent’s various causes of action present at least three separate claims for relief, each requiring proof of facts and elements not necessary to the proof of the other claims. Therefore, Hallicrafters’ contention that respondent’s complaint states only one claim for relief for purposes of NRCP 54(b) lacks merit.

Respondent’s complaint alleges more than one claim for relief. Further, the district court’s partial summary judgment arguably finally adjudicates one of respondent’s claims for relief. Nonetheless, we conclude that the district court improvidently certified its partial summary judgment as final. NRCP 54(b) provides that a judgment or order of the district court which completely removes a party or a claim from a pending action may be certified as final “only upon an express determination that there is no just reason for delay. ...” (Emphasis added.)

If the claims asserted in an action, albeit separate, are so closely related that this court must necessarily decide important issues pending below in order to decide the issues appealed, there can be no finding that there is no just reason for delay, and certification of an order deciding some but not all of those claims as final is an abuse of the district court’s discretion. See Mid-Century Ins. Co. v. Cherubini, 95 Nev. 293, 593 P.2d 1068 (1979); Las Vegas Hacienda v. G.L.M.M. Corp., 93 Nev. 177, 561 P.2d 1334 (1977). In this case, the claims alleged in respondent’s complaint are so closely related that this court would necessarily decide the law of the case on the claims still pending in the district court in the course of deciding the appeal. Although the contract claims and the tort claims are separate, and require proof of separate elements, the factual underpinnings and many of the issues related to the measure of damages to be awarded are the same. Therefore, consideration of this appeal would result in *529 piecemeal litigation, and would defeat the purpose of NRCP 54(b).

Accordingly, we grant Hallicrafters’ motion, and we dismiss this appeal without prejudice to the rights of the parties to pursue an appeal following a final judgment in the district court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vres, Llc v. Classic Landscapes, Llc
Nevada Supreme Court, 2022
Wiman Vs. Refaely
489 P.3d 917 (Nevada Supreme Court, 2021)
Life, M.D. Vs. Marquis Aurbach Coffing
479 P.3d 226 (Nevada Supreme Court, 2020)
Edwards Vs. Timeshare Liquidators, Llc
Nevada Supreme Court, 2019
Beierschmitt v. Smith, D.O.
Nevada Supreme Court, 2018
Wang v. U.S. Bank, Nat'l. Ass'n.
Nevada Supreme Court, 2016
Winston Products Co. v. DeBoer
134 P.3d 726 (Nevada Supreme Court, 2006)
Reno Hilton Resort Corp. v. Verderber
106 P.3d 134 (Nevada Supreme Court, 2005)
Moran v. Bonneville Square Associates
25 P.3d 898 (Nevada Supreme Court, 2001)
Lee v. GNLV CORP.
996 P.2d 416 (Nevada Supreme Court, 2000)
Sheriff v. Gillock
912 P.2d 274 (Nevada Supreme Court, 1996)
Valley Bank of Nevada v. Ginsburg
874 P.2d 729 (Nevada Supreme Court, 1994)
Fernandez v. Infusaid Corp.
871 P.2d 292 (Nevada Supreme Court, 1994)
Beets v. State
871 P.2d 357 (Nevada Supreme Court, 1994)
Hilton Hotels Corp. v. Butch Lewis Productions, Inc.
862 P.2d 1207 (Nevada Supreme Court, 1993)
State, Taxicab Authority v. Greenspun
862 P.2d 423 (Nevada Supreme Court, 1993)
KDI Sylvan Pools, Inc. v. Workman
810 P.2d 1217 (Nevada Supreme Court, 1991)
Mallin v. Farmers Insurance Exchange
797 P.2d 978 (Nevada Supreme Court, 1990)
Bernard v. Rockhill Development Co.
734 P.2d 1238 (Nevada Supreme Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
728 P.2d 441, 102 Nev. 526, 1986 Nev. LEXIS 1618, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hallicrafters-co-v-moore-nev-1986.