Hall v. United States Fidelity & Guaranty Co.

436 A.2d 863, 1981 Me. LEXIS 989
CourtSupreme Judicial Court of Maine
DecidedOctober 29, 1981
StatusPublished

This text of 436 A.2d 863 (Hall v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hall v. United States Fidelity & Guaranty Co., 436 A.2d 863, 1981 Me. LEXIS 989 (Me. 1981).

Opinion

CARTER, Justice.

The plaintiff-supplier, George C. Hall, brought this action against the contractor, Libby Construction Company, Inc. (Libby), and against Libby’s surety, United States Fidelity & Guaranty Company (Fidelity), alleging that he had not been paid for materials supplied to Libby, and that Fidelity was also liable pursuant to its Contract Payment Bond with Libby. The Superior Court (Cumberland County) awarded Hall judgment for $24,510.35 against Libby, but granted Fidelity’s motion for summary judgment on the grounds that Hall’s action was not commenced before the expiration of the applicable statute of limitations. Hall appeals from the entry of final judgment in favor of Fidelity. We affirm the decision below.

In 1974, Libby entered into a contract with the State Department of Transportation to construct part of a highway in Knox County. In that same year, Fidelity entered into a surety agreement with Libby, whereby Fidelity agreed to satisfy claims for labor and materials provided to Libby in case Libby should default. Hall, in turn, entered into a subcontract with Libby to furnish gravel and sand for the project.

Hall last worked on the highway project in 1975. The parties agree that on February 16, 1978, the State Department of Transportation determined the final quanti[864]*864ty estimates of materials supplied for the highway project, including final quantity estimates of materials supplied by Hall. Fidelity was notified of these estimates by letter dated February 16, 1978; Hall was notified by letter dated March 10, 1978. Hall filed with the Superior Court his complaint against Libby and Fidelity commencing this action on March 9, 1979.

The parties agree that Hall’s action against Fidelity on the Contract Payment Bond is governed by the Public Works Contractors’ Surety Bond Law of 1971, 14 M.R. S.A. § 871 (1980), and that the amount of Hall’s claim against Libby and Fidelity could not have been ascertained until final quantity estimates were determined. Section 871(4) states in part:

Any . . . claimant having a direct contractual relationship with a subcontractor of the contractor furnishing such payment bond but no contractual relationship, express or implied, with such contractor shall not have the right of action upon such payment bond unless he shall have given written notice to such contractor within 90 days from the date on which such claimant performed the last of the labor, or furnished or supplied the last of the material for which such claim is made ....
No ... action [on the payment bond] may be commenced after .. . one year from the date on which the last of the labor was performed or material was supplied .... Provided that in the case of a material supplier, where the amount of the claim is not ascertainable due to the unavailability of final quantity estimates, such action may be commenced before the expiration of one year from the date on which the final quantity estimates are determined. The notice of claim from the material supplier to the contractor furnishing the payment bond shall be filed before the expiration of 90 days following the determination by the contracting authority of the final quantity estimates.

(Emphasis added.) The issue that we must determine is when the one year statute of limitations began to run.

Relying on a claimed variance in the language used by the legislature in section 871(4) and emphasized above, Hall contends that different events must trigger the running of the ninety day notice provision and the one year statute of limitations. Because the ninety day period for providing notice to the contractor begins to run upon “the determination by the contracting authority of the final quantity estimates,” argues Hall, the one year limit must commence following a different event. It is indisputable that the notice provision, itself, does not apply to Hall in this case since he is a materialman having a direct contractual relationship with Libby, the contractor providing the payment bond. Hall suggests as possible triggering events either the date upon which final quantity estimates are determined by the material supplier, or the date upon which actual notice of the estimates made by the contracting authority is received by the material supplier. We disagree.

The fundamental rule in statutory construction is that words must be given their plain meaning. Of course, legislative intent is always of fundamental importance. Thus, the court has disregarded the strict wording of statutes to avoid absurd results, or to [avoid] inconsistent or unreasonable results.

Paradis v. Webber Hospital, Me., 409 A.2d 672, 675 (1979) (citations omitted). Giving the phrase “the date on which the final quantity estimates are determined” its plain meaning, the one year limitations period here would have commenced to run on February 16, 1978, when the Department of Transportation determined final quantity estimates.2 That result is not absurd, inconsistent or unreasonable.

[865]*865This construction of the statutory language is confirmed by the Legislature’s use of “determined” as the operative word identifying the event intended. The determination referred to is obviously that on the basis of which payments are to be made upon the contract. Because the contracting authority is responsible for establishing the factual foundation on which payments are to be made, its determination of the quantities of material for which payment is to be made should logically be made the controlling predicate for the commencement of the period of limitations. Such determinations are the ones contemplated by the legislative language precisely because of their controlling significance on the making of the payments.

Quantity estimates compiled by the mate-rialman, on the other hand, do not have any controlling effect upon payment until they are approved and adopted by the contracting authority as its own. They are merely submissions by the materialman for approval by the contracting authority after investigation and verification as to the amounts of materials for which payment is to be made. They may be “determinations” from the materialman’s personal perspective, but they are not controlling on payments until approved by the contracting authority. They are not, therefore, “determinations” within the meaning of the statutory language. Thus, Hall’s argument that the period of limitations commences from the ma-terialman’s making of such estimates is not in accord with the legislative intent expressed by the language of the statute.

We find further confirmation of our construction of this language in the fact that, even in a case where the notice provision is applicable, a material supplier (whose claim is ascertainable only after the determination of final quantity estimates) must act, in order to comply with the ninety day notice provision, within ninety days of the determination of final quantity estimates by the contracting authority or risk losing his cause of action on the payment bond.3 Thus, the supplier, in such a situation, must be diligent in inquiring as to when the contracting authority makes its final estimate determinations for purposes of complying with the notice requirement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Laurel Bank and Trust Co. v. Burns
398 A.2d 41 (Supreme Judicial Court of Maine, 1979)
Dougherty v. Oliviero
427 A.2d 487 (Supreme Judicial Court of Maine, 1981)
Paradis v. Webber Hospital
409 A.2d 672 (Supreme Judicial Court of Maine, 1979)
Brown v. State, Department of Manpower Affairs
426 A.2d 880 (Supreme Judicial Court of Maine, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
436 A.2d 863, 1981 Me. LEXIS 989, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hall-v-united-states-fidelity-guaranty-co-me-1981.