Hall v. JFW, INC.

893 P.2d 837, 20 Kan. App. 2d 845, 1995 Kan. App. LEXIS 52
CourtCourt of Appeals of Kansas
DecidedApril 7, 1995
Docket71,832
StatusPublished
Cited by18 cases

This text of 893 P.2d 837 (Hall v. JFW, INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hall v. JFW, INC., 893 P.2d 837, 20 Kan. App. 2d 845, 1995 Kan. App. LEXIS 52 (kanctapp 1995).

Opinion

Shepherd, J.;

John Hall, lessor, and JFW, Inc., lessee, entered into an oil and gas lease on August 3, 1990. The lease provided in pertinent part:

“If no well be commenced on said land on or before August 3rd, 1991, this lease shall terminate as to both parties ....
“If the lessee shall commence to drill a well within the term of this lease . . . the lessee shall have the right to drill such well to completion with reasonable diligence and dispatch.”

The lease was altered after it was recorded. The altered lease stated it was entered into on August 13, 1990, and stated the well must be commenced on or before August 13, 1991.

The lease also contained a delay rental clause, but JFW did not timely tender payment.

JFW performed the following activities on the Hall lease:

10-22-90: Title opinion

3-30-91: Measured and staked location for well

4- 2-91: Surveyed elevation of site

6-25-91: Received KCC approval of intent to drill

*847 June/July 1991:

Talked with geologist

7-18-91: Received bid for drilling mud

7-20-91: Reached verbal agreement with Duke Drilling to drill well; tentative date set for late July or early August

7-24-91: Restaked location for well

More than three days before 8-6-91:

Told Duke Drilling to get rig on lease.

8-10-91: Signed written contract with Duke Drilling Agent of Duke Drilling dug drilling pits and leveled location

8-11-91: Drilled water supply well

8-12-91: Prepared rotary hold and run-around

8-12-91: Duke Drilling picked up surface casing

8-14-91: Duke Drilling moved drilling rig onto lease and spudded well

8-14-91 to 8-20-91:

Well dug to 3,000 feet; production casing installed and cemented

8-20-91 to 9-3-91:

Cement allowed to cure

9- 3-91: Ready to move completion rig onto lease.

Prior to completion of the well, Hall sought a determination that the lease had terminated and requested a temporary restraining order preventing JFW from entering the lease. On September 3, 1991, a temporary restraining order was issued. The trial court later denied a temporary injunction and determined the well had been commenced by August 3, 1991. This court reversed the judgment after finding the trial court prematurely had decided the merits of the case.

Upon remand, the parties completed discovery and filed motions for summary judgment. The trial court found JFW had a “firm commitment” from Duke Drilling prior to the commencement deadline and therefore determined JFW had commenced the well prior to expiration of the lease, and entered summary judgment for JFW.

*848 Hall argues the trial court erred in finding a well had been commenced prior to the lease termination date. He argues the preliminary steps taken in anticipation of drilling were not sufficient to constitute commencement of the well under the terms of the lease. We agree.

Summary judgment is proper when no genuine issue of material fact exists and the moving party is entitled to judgment as a matter of law. When considering a motion for summary judgment, the trial court is required to resolve all facts and inferences which may reasonably be drawn from the evidence in favor of the nonmoving party. The same standard is applied on appeal, and summary judgment must be denied where reasonable minds could differ as to the conclusions drawn from the evidence. See K.S.A. 60-256(c); C.J.W. v. State, 253 Kan. 1, 16, 853 P.2d 4 (1993).

This court is not bound by the trial court’s interpretation of the written contract. Simon v. National Farmers Organization, Inc., 250 Kan. 676, 680, 829 P.2d 884 (1992). The rules of construction for oil and gas leases are well established and mirror the rules for construction of contracts generally.

“[T]he intent of the parties is the primary question; meaning should be ascertained by examining the document from all four comers and by considering all of the pertinent provisions, rather than by critical analysis of a single or isolated provision; reasonable rather than unreasonable interpretations are favored; a practical and equitable construction must be given to ambiguous terms; and any ambiguities in a lease should be construed in favor of the lessor and against the lessee, since it is the lessee who usually provides the lease form or dictates the terms thereof.” Jackson v. Farmer, 225 Kan. 732, 739, 594 P.2d 177 (1979).

Unambiguous contracts are enforced according to their plain, general, and common meaning in order to ensure the intentions of the parties are enforced. See Wood River Pipeline Co. v. Willbros Energy Services Co., 241 Kan. 580, Syl. ¶ 3, 738 P.2d 866 (1987). The intent of the parties is determined from the four comers of an unambiguous instrument, harmonizing the language therein if possible. See Brown v. Lang, 234 Kan. 610, Syl. ¶¶ 1, 2, 675 P.2d 842 (1984); Wiles v. Wiles, 202 Kan. 613, 619, 452 P.2d 271 (1969). Ambiguity does not appear until the application of the pertinent mies of interpretation to the face of the instru *849 xnent leaves it genuinely uncertain which of two or more meanings is the proper meaning. Patrons Mut. Ins. Ass’n v. Harmon, 240 Kan. 707, 713, 732 P.2d 741 (1987).

When analyzing whether a lease has terminated because the lessee has not timely commenced a well, our Supreme Court has looked to the language of the controlling instrument, reading it as a whole, to determine the nature and extent of the lessee’s obligation. See Shoup v. First Nat’l Bank, 145 Kan. 971, 976, 67 P.2d 569 (1937) (an escrow agreement required not only timely commencement but continued operations with due diligence to completion).

Our courts have considered clauses which require the lessee to commence operations for drilling in a number of instances. Most recently in A & M Oil, Inc. v. Miller, 11 Kan. App. 2d 152, 154-55,

Related

Smith v. Anguiano
Court of Appeals of Kansas, 2021
Hess Bakken Investments II v. AgriBank
2020 ND 172 (North Dakota Supreme Court, 2020)
Hefner v. Deutscher
Court of Appeals of Kansas, 2020
Lincoln v. BNSF Railway Company
900 F.3d 1166 (Tenth Circuit, 2018)
Davis v. Key Gas Corp.
124 P.3d 96 (Court of Appeals of Kansas, 2005)
Ed Bozarth Chevrolet, Inc. v. Black
96 P.3d 272 (Court of Appeals of Kansas, 2003)
Bunnell Farms Co. v. Samuel Gary, Jr. & Associates
47 P.3d 804 (Court of Appeals of Kansas, 2002)
Nolde v. Hamm Asphalt, Inc.
202 F. Supp. 2d 1257 (D. Kansas, 2002)
Johnson County Bank v. Ross
13 P.3d 351 (Court of Appeals of Kansas, 2000)
Oakview Treatment Centers of Kansas, Inc. v. Garrett
53 F. Supp. 2d 1184 (D. Kansas, 1999)
Rinehart v. Northern Natural Gas Co.
967 P.2d 1090 (Court of Appeals of Kansas, 1998)
Neustrom v. Union Pacific
Tenth Circuit, 1998

Cite This Page — Counsel Stack

Bluebook (online)
893 P.2d 837, 20 Kan. App. 2d 845, 1995 Kan. App. LEXIS 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hall-v-jfw-inc-kanctapp-1995.