Hall Arts Ctr. Office, LLC v. Hanover Ins. Co.

327 F. Supp. 3d 979
CourtDistrict Court, N.D. Texas
DecidedAugust 27, 2018
DocketCivil Action No. 3:16-CV-3226-D
StatusPublished
Cited by14 cases

This text of 327 F. Supp. 3d 979 (Hall Arts Ctr. Office, LLC v. Hanover Ins. Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hall Arts Ctr. Office, LLC v. Hanover Ins. Co., 327 F. Supp. 3d 979 (N.D. Tex. 2018).

Opinion

SIDNEY A. FITZWATER, UNITED STATES DISTRICT JUDGE

*987In this removed action seeking recovery for a claim for lost rental income and soft costs under a builder's risk insurance policy, defendant Hanover Insurance Company ("Hanover") moves for summary judgment on all claims. Plaintiff Hall Arts Center Office, LLC ("Hall Arts"), a company engaged primarily in the business of commercial real estate, cross-moves for summary judgment. Hanover and Hall Arts both move to exclude expert witness testimony. For the reasons that follow, the court grants in part and denies in part Hanover's motion for summary judgment, denies Hall Arts's cross-motion for summary judgment, and denies Hanover's and Hall Arts's motions to exclude expert testimony.

I

This lawsuit arises from a dispute over Policy No. IHD-9935566, a builder's risk insurance policy (the "Policy"), issued to Hall Arts.1 The Policy covers the construction of an 18-story office building and adjoining retail space at 2323 Ross Avenue in Dallas (the "KPMG Plaza"). Hall Arts owns KPMG Plaza.

Turner Construction ("Turner") was the general contractor for the KPMG Plaza construction. The contract between Hall Arts and Turner set two progress milestones for the project: (1) a topping-out and dry-in date2 of November 1, 2014, and (2) a substantial completion date3 of April 1, 2015. Turner commenced construction on August 1, 2013. Over one year later, on October 13, 2014 rainwater leaked through openings in the temporary roof and damaged one of the high-voltage bus ducts ("Bus Duct B") (the "Weather Event"). Bus Duct B was intended to deliver electricity to mechanical equipment on various floors of the property. Bus Duct B was repaired and energized by November 25, 2014.

The relevant tenant of KPMG Plaza in this case is KPMG. KPMG's lease provides *988that it will lease about 150,000 square feet of the building, spanning from the third through seventh floors to part of the eighth floor. KPMG was originally scheduled to commence its tenant fit-out, or the process of preparing the interior space for KPMG's occupancy,4 on December 22, 2014, and, prior to the Weather Event, voluntarily delayed its tenant fit-out to January 1, 2015. KPMG did not actually commence the tenant fit-out process until January 14, 2015. On January 20, 2015 the Dallas Fire-Rescue Department ("DFRD") halted the fit-out, requiring Hall Arts to complete certain fire alarm and life safety items before resuming.5 DFRD, Hall Arts, and Turner agreed to a revised list of required items on January 30, 2015. KPMG commenced its actual occupancy of KPMG Plaza, and paying rent to Hall Arts, on July 27, 2015.

Section 3.1 of the KPMG lease specifies when KPMG is to begin paying rent:

Rent will accrue beginning on the date ('Commencement Date') which is the earlier to occur of: (i) the commencement of occupancy of the Premises by Tenant for the normal conduct of business; or (ii) the date that is nine (9) months following ['Construction Move-In Period'] the Delivery Date (but in no event prior to (1) Substantial Completion...of Landlord's Premises Work ..., (2) Substantial Completion of Landlord's Building Work ..., and (3) receipt of Certificates of Occupancy for the Core and Shell with respect to the Premises[.]

D. 3/30/18 App. 232. The lease requires the landlord to deliver the premises to the tenant with each floor of the premises dried in and sufficiently complete to allow the tenant to commence tenant's work (the "delivery date") by October 1, 2014. Id. at 234. The lease also states that the "Landlord shall Substantially Complete the Landlord's Building Work by June 30, 2015." Id. [redacted] Id. at 228.

Hall Arts sought compensation from Hanover under the Policy for costs arising from alleged delays resulting from the Weather Event. Pertinent to the dispute in this lawsuit, the Policy provides for coverage of "soft costs incurred during the delay period" so long as they "arise out of a 'delay' to a 'building or structure' at a 'jobsite' described on the Delay in Completion Schedule." P. 3/30/18 App. 50. "Soft costs" are defined as "the necessary and reasonable costs relating to the construction, erection, or fabrication of a covered 'building or structure' that are over and above those costs that would have been incurred had there been no 'delay period.' " Id. at 51. The Policy specifies that soft costs are limited to interest payments, realty taxes, lease expenses, and insurance premiums. Covered insurance premiums are the "[a]dditional cost of insurance premiums necessary to renew or extend insurance coverage." Id.

The Policy also covers "actual loss of rental income incurred during the 'delay period' " that "arises out of a 'delay' to a 'building or structure' at a 'jobsite' described on the Delay in Completion Schedule." Id. The Policy defines "delay period" as "the period of time the completion of the construction, erection, or fabrication of a covered 'building or structure' is 'delayed' as a result of direct physical loss or damage caused by a covered peril to property covered under the Builders' Risk Coverage *989form to which this coverage part is attached." Id. at 49. "Delay" is "an interruption in the construction, erection, or fabrication of a 'building or structure' caused by a covered peril." Id. "Buildings or Structures" are defined as: "a. buildings; b. structures; c. materials and supplies that will become a permanent part of the buildings or the structures; and d. foundations, excavations, grading, filling, attachments, permanent fencing, and other permanent fixtures." Id. at 44. The "Perils Covered" provision states that risks of direct physical loss or damage are covered unless the loss is limited or caused by an excluded peril, which includes, inter alia , seizure by civil authority, earth movement, fungus, nuclear hazard, flood, sewage backup, war, and delay in completion and increased construction costs . Id. at 34-37. The Policy states that "[i]f a waiting period is indicated on the Delay in Completion Schedule, we do not pay for: a. additional soft costs; b. loss of rental income; or c. loss of net income until after the number of days indicated on the schedule have passed." Id. at 56.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
327 F. Supp. 3d 979, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hall-arts-ctr-office-llc-v-hanover-ins-co-txnd-2018.