Halkias v. General Dynamics
Opinion
UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT
NO. 97-10334
JOHN HALKIAS, ET AL.,
Plaintiffs
DAWN DEE BRYANT; BARRY JACKSON, Plaintiffs-Appellants
VERSUS
GENERAL DYNAMICS CORPORATION, Defendant-Appellee
JAMES ANTHONY CUREINGTON, Plaintiff
VERSUS
GENERAL DYNAMICS CORPORATION, Defendant
Appeal from the United States District Court For the Northern District of Texas
April 1, 1998
Before JOLLY, DUHE’ and PARKER, Circuit Judges. ROBERT M. PARKER, Circuit Judge:
I.
FACTS & PROCEDURAL HISTORY On January 13, 1988, General Dynamics and McDonnell Douglas Corporation were awarded a contract by the United States Navy to
jointly develop a new generation of carrier-based, medium attack aircraft to be known as the A-12 “Avenger”. The contract contained several provisions reflecting a concern for the abusive cost overruns of the past. Costs between the target price of $4.4 billion and the ceiling price of $4.8 billion would be shared by the government and the contractors (60% by the government and 40% by the contractors). All costs over the ceiling price would be absorbed by the contractors.
By May, 1990, the A-12 contractors had incurred substantial unforeseen production difficulties and by its own estimate, General Dynamics concluded that the cost of completion would be $700 million more than planned. On June 13, 1990, the contractors notified the Navy that the costs of completion would overrun the contract ceiling by an amount that the contractors could not absorb. Throughout the remainder of 1990 production continued amidst various attempts to restructure the contract, which did result in a new delivery schedule. However, the Navy would not agree to change the contract ceiling price. Meanwhile, the threat of contract cancellation loomed overhead.
On December 14, 1990, the Secretary of Defense directed the Navy to show cause by January 4, 1991, why the A-12 contract should not be canceled. Later that same day, General Dynamics received informal notice of the Secretary’s show cause order. On December 17, 1990, the Navy gave the contractors notice that their performance on the A-12 contract was “unsatisfactory” and that unless specified conditions were met by January 2, 1991, the
contract might be terminated. On December 20, 1990, General Dynamics issued a special bulletin to all of its employees notifying them that the A-12 contract was in jeopardy and promising to provide notices the next day to each individual employee who might lose his or her job. As promised, on December 21, 1990, General Dynamic sent out individual notices to all potentially affected employees, providing official but conditional notification that they might be terminated in the event that the A-12 contract were canceled. On January 7, 1991, Secretary Cheney announced his decision to terminate the A-12 contract effective immediately. As a result General Dynamics immediately began laying off affected employees. Approximately 2000 non-union salaried employees were laid off from General Dynamics’ Fort Worth, Texas, and Tulsa, Oklahoma, facilities.
On November 24, 1992, Plaintiff John Halkias filed suit under the Worker Adjustment and Retraining Notification Act, 29 U.S.C. §§ 2101-2109 (1988)(the “WARN” act), claiming that General Dynamics had failed to comply with the Act’s sixty-day notice requirement. The district court certified a class of non-union salaried employees and designated John Halkias as class representative. On June 24, 1993, the district court granted General Dynamics’ Fed. R. Civ. P. 12(c) motion to dismiss holding that the six-month statute of limitations of the National Labor Relations Act, 29 U.S.C. § 160(b), was applicable to actions under the WARN Act, and Plaintiff appealed to this Court. On July 11, 1995, this Court reversed the district court and remanded the case following North Star Steel v.
Thomas, ___ U.S. ___, 115 S. Ct. 1927, 132 L. Ed. 2d 27 (1995), which held that state law rather than the NLRA provided the relevant statute of limitations for actions under the WARN Act. Halkias v. General Dynamics Corp., 56 F.3d 27 (5th Cir. 1995).1 On October 3, 1995, the district court determined that the Texas four-year statute of limitations for actions for debt, Tex. Civ. Prac. & Rem. Code Ann. § 16.004(a)(3)(Vernon 1986), was the most analogous to actions under the WARN Act and denied General Dynamics’ Rule 12(c) motion. Since this holding was at odds with a holding by the district court for the western district of Texas, the district court granted General Dynamics the right to take an interlocutory appeal on October 6, 1995, which invitation General Dynamics accepted. Over one year later, on October 22, 1996, following the decision in Staudt v. Glastron, Inc., 92 F.3d 312 (5th Cir. 1996), this Court affirmed the district court’s ruling concerning the statute of limitations and remanded the case. Halkias v. General Dynamics Corp., 101 F.3d 698 (5th Cir. 1996)(table).
On December 12, 1996, the district court issued a scheduling order establishing July 31, 1997, as the deadline for completion of discovery. On January 16, 1997, General Dynamics filed its motion for summary judgment, arguing that sixty-day advance written notice was not required in this case, because the layoffs were “caused by business circumstances that were not reasonably foreseeable as of
1 During the pendency of this appeal, Plaintiff John Halkias passed away, and on remand his widow, Billie Halkias, was substituted as Plaintiff and Appellant Dawn Dee Bryant was substituted as class representative.
the time that notice would have been required.” 29 U.S.C. § 2102(b)(2)(A). In response Appellants sought to have General Dynamics’ motion for summary judgment continued so that more discovery might be conducted in accordance with Fed. R. Civ. P. 56(f) . That motion was denied. The motion for summary judgment was fully briefed, and on March 5, 1997, the district court granted it. Plaintiffs-Appellants have taken this appeal raising the following issues: 1. Did the district court err by refusing to continue General Dynamics’ motion for summary judgment so that additional discovery might be conducted in accordance with Fed. R. Civ. P. 56(f)? 2. Did the district court err by granting General Dynamics’ motion for summary judgment?
II.
LAW & ANALYSIS
A.
The WARN Act
The WARN Act provides that:
“[a]n employer shall not order a plant closing or mass layoff until the end of a 60-day period after the employer serves written notice of such an order ... to each representative of the affected employees as of the time of the notice, or if there is no such representative at that time, to each affected employee....”
29 U.S.C. § 2102 (a)(1). However, the Act further provides that;
“[a]n employer may order a plant closing or mass layoff before the conclusion of the 60-day period if the closing or mass layoff is caused by business circumstances that were not reasonably foreseeable as of the time that notice would have been required ... An employer relying on this subsection shall give as much notice as is practicable and at that time shall give a brief statement
of the basis for reducing the notification period.”
29 U.S.C. § 2102 (b)(2)(A) & (b)(3)(emphasis added). This case centers around the proof in support of and against the proposition that General Dynamics should have reasonably foreseen the impending contract cancellation and therefore cannot avail itself of the exception in § 2102(b)(2)(A). This Court reviews a district court decision to grant summary judgment de novo, applying the same standard as the district court. Wynn v. Washington National Insurance Company, 122 F.3d 266, 268 (5th Cir. 1997), citing Bodenheimer v. PPG Indus., Inc., 5 F.3d 955, 956 (5th Cir. 1993).
Free access — add to your briefcase to read the full text and ask questions with AI
Halkias v. General Dynamics (Halkias v. General Dynamics) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.