Halkias v. General Dynamics

CourtCourt of Appeals for the Fifth Circuit
DecidedApril 1, 1998
Docket97-10334
StatusPublished

This text of Halkias v. General Dynamics (Halkias v. General Dynamics) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Halkias v. General Dynamics, (5th Cir. 1998).

Opinion

UNITED STATES COURT OF APPEALS

FOR THE FIFTH CIRCUIT

NO. 97-10334

JOHN HALKIAS, ET AL.,

Plaintiffs

DAWN DEE BRYANT; BARRY JACKSON,

Plaintiffs-Appellants

VERSUS

GENERAL DYNAMICS CORPORATION,

Defendant-Appellee

JAMES ANTHONY CUREINGTON,

Plaintiff

Defendant

Appeal from the United States District Court For the Northern District of Texas

April 1, 1998

Before JOLLY, DUHE’ and PARKER, Circuit Judges.

ROBERT M. PARKER, Circuit Judge:

I.

FACTS & PROCEDURAL HISTORY

On January 13, 1988, General Dynamics and McDonnell Douglas

Corporation were awarded a contract by the United States Navy to

1 jointly develop a new generation of carrier-based, medium attack

aircraft to be known as the A-12 “Avenger”. The contract contained

several provisions reflecting a concern for the abusive cost

overruns of the past. Costs between the target price of $4.4

billion and the ceiling price of $4.8 billion would be shared by

the government and the contractors (60% by the government and 40%

by the contractors). All costs over the ceiling price would be

absorbed by the contractors.

By May, 1990, the A-12 contractors had incurred substantial

unforeseen production difficulties and by its own estimate, General

Dynamics concluded that the cost of completion would be $700

million more than planned. On June 13, 1990, the contractors

notified the Navy that the costs of completion would overrun the

contract ceiling by an amount that the contractors could not

absorb. Throughout the remainder of 1990 production continued

amidst various attempts to restructure the contract, which did

result in a new delivery schedule. However, the Navy would not

agree to change the contract ceiling price. Meanwhile, the threat

of contract cancellation loomed overhead.

On December 14, 1990, the Secretary of Defense directed the

Navy to show cause by January 4, 1991, why the A-12 contract should

not be canceled. Later that same day, General Dynamics received

informal notice of the Secretary’s show cause order. On December

17, 1990, the Navy gave the contractors notice that their

performance on the A-12 contract was “unsatisfactory” and that

unless specified conditions were met by January 2, 1991, the

2 contract might be terminated. On December 20, 1990, General

Dynamics issued a special bulletin to all of its employees

notifying them that the A-12 contract was in jeopardy and promising

to provide notices the next day to each individual employee who

might lose his or her job. As promised, on December 21, 1990,

General Dynamic sent out individual notices to all potentially

affected employees, providing official but conditional notification

that they might be terminated in the event that the A-12 contract

were canceled. On January 7, 1991, Secretary Cheney announced his

decision to terminate the A-12 contract effective immediately. As

a result General Dynamics immediately began laying off affected

employees. Approximately 2000 non-union salaried employees were

laid off from General Dynamics’ Fort Worth, Texas, and Tulsa,

Oklahoma, facilities.

On November 24, 1992, Plaintiff John Halkias filed suit under

the Worker Adjustment and Retraining Notification Act, 29 U.S.C. §§

2101-2109 (1988)(the “WARN” act), claiming that General Dynamics

had failed to comply with the Act’s sixty-day notice requirement.

The district court certified a class of non-union salaried

employees and designated John Halkias as class representative. On

June 24, 1993, the district court granted General Dynamics’ Fed. R.

Civ. P. 12(c) motion to dismiss holding that the six-month statute

of limitations of the National Labor Relations Act, 29 U.S.C. §

160(b), was applicable to actions under the WARN Act, and Plaintiff

appealed to this Court. On July 11, 1995, this Court reversed the

district court and remanded the case following North Star Steel v.

3 Thomas, ___ U.S. ___, 115 S. Ct. 1927, 132 L. Ed. 2d 27 (1995),

which held that state law rather than the NLRA provided the

relevant statute of limitations for actions under the WARN Act.

Halkias v. General Dynamics Corp., 56 F.3d 27 (5th Cir. 1995).1

On October 3, 1995, the district court determined that the

Texas four-year statute of limitations for actions for debt, Tex.

Civ. Prac. & Rem. Code Ann. § 16.004(a)(3)(Vernon 1986), was the

most analogous to actions under the WARN Act and denied General

Dynamics’ Rule 12(c) motion. Since this holding was at odds with

a holding by the district court for the western district of Texas,

the district court granted General Dynamics the right to take an

interlocutory appeal on October 6, 1995, which invitation General

Dynamics accepted. Over one year later, on October 22, 1996,

following the decision in Staudt v. Glastron, Inc., 92 F.3d 312

(5th Cir. 1996), this Court affirmed the district court’s ruling

concerning the statute of limitations and remanded the case.

Halkias v. General Dynamics Corp., 101 F.3d 698 (5th Cir.

1996)(table).

On December 12, 1996, the district court issued a scheduling

order establishing July 31, 1997, as the deadline for completion of

discovery. On January 16, 1997, General Dynamics filed its motion

for summary judgment, arguing that sixty-day advance written notice

was not required in this case, because the layoffs were “caused by

business circumstances that were not reasonably foreseeable as of

1 During the pendency of this appeal, Plaintiff John Halkias passed away, and on remand his widow, Billie Halkias, was substituted as Plaintiff and Appellant Dawn Dee Bryant was substituted as class representative.

4 the time that notice would have been required.” 29 U.S.C. §

2102(b)(2)(A). In response Appellants sought to have General

Dynamics’ motion for summary judgment continued so that more

discovery might be conducted in accordance with Fed. R. Civ. P.

56(f) . That motion was denied. The motion for summary judgment

was fully briefed, and on March 5, 1997, the district court granted

it. Plaintiffs-Appellants have taken this appeal raising the

following issues:

1. Did the district court err by refusing to continue General

Dynamics’ motion for summary judgment so that additional discovery

might be conducted in accordance with Fed. R. Civ. P. 56(f)?

2. Did the district court err by granting General Dynamics’

motion for summary judgment?

II.

LAW & ANALYSIS

A.

The WARN Act

The WARN Act provides that:

“[a]n employer shall not order a plant closing or mass layoff until the end of a 60-day period after the employer serves written notice of such an order ... to each representative of the affected employees as of the time of the notice, or if there is no such representative at that time, to each affected employee....”

29 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bodenheimer v. PPG Industries, Inc.
5 F.3d 955 (Fifth Circuit, 1993)
North Star Steel Co. v. Thomas
515 U.S. 29 (Supreme Court, 1995)
Halkias v. General Dynamics
101 F.3d 698 (Fifth Circuit, 1996)
INTERN. ASS'N OF MACHINISTS v. General Dynamics
821 F. Supp. 1306 (E.D. Missouri, 1993)
Halkias v. General Dynamics Corp.
56 F.3d 27 (Fifth Circuit, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Halkias v. General Dynamics, Counsel Stack Legal Research, https://law.counselstack.com/opinion/halkias-v-general-dynamics-ca5-1998.