Halfmoon Bridge Co. v. Canal Board
This text of 163 A.D. 76 (Halfmoon Bridge Co. v. Canal Board) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
In 157 Appellate Division, 18B, the opinion of this court is reported, wherein this court reversed an order setting aside the temporary injunction herein. In that opinion are stated most [77]*77of the facts necessary for a determination of this appeal. Upon that appeal this court held in effect that the State had no power to condemn the plaintiff’s bridge and franchise, but that upon a reading of the entire act it was contemplated that all bridges, the destruction of which was rendered necessary by the building of the canal, should be rebuilt, presumptively for the benefit of the bridge owners. This construction of the statute if upheld assured the plaintiff of some relief in the action. Thereafter, and in September, 1913, an act was passed which purported to authorize the State to condemn this bridge and the franchise of the corporation owning the same.
First. The payment of all costs and an additional allowance of $1,500.
Second. The permission to either party to offer evidence.
Third. The denial of leave to serve the answer in case the costs and allowances are not paid.
Fourth. The waiver by defendants of all costs already accrued.
Fifth. The grant to the plaintiff of permission to discontinue without costs after a compliance with these conditions.
In my opinion, for the purposes of this argument, the constitutionality of the act of 1913 must be assumed. By such assumption the plaintiff is deprived of no material right. If the assumption should prove erroneous, the plaintiff has full remedy against the State for any damage suffered through any illegal act of the State. With this assumption then, and [78]*78with the fact established that the State has taken the necessary acts to appropriate the rights of the plaintiff in this bridge, there is no apparent reason why this injunction should continue, and the order should I think be modified so as to vacate the same.
The terms imposed on the granting of the permission to serve the supplemental answer should also be somewhat modified. The defendants should, of course, pay all the costs of the motion up to date. Such are the ordinary terms imposed upon the service of a supplemental answer, and I see no reason why this case should not come within the ordinary rule. If the case were one in which an extra allowance should be granted upon the granting of the judgment, it would be my opinion that a further condition might be made requiring the payment of such an extra allowance. The case had practically progressed to the point of a decision. The ruling of this court, as before indicated, assured the plaintiff of success. Large expenses had been incurred, and the case was undoubtedly a difficult and extraordinary one. Natural equity would require the court in exercising its discretion to grant the defendants permission to come in and change the entire issue by pleading an act passed since the commencement of the action, to indemnify the plaintiff by making it as a condition of such permission the payment of such costs as would probably follow the judgment if such permission were not granted. But what facts here shown would justify a substantial extra allowance even upon a judgment % The State must confessedly build a new bridge if the property cannot be condemned. The value of the bridge is not in controversy. If a new bridge be built and the State has no right of condemnation the plaintiff would own the bridge, which would be much to its advantage. If it should finally be determined that the State had a right of condemnation the plaintiff obtains the full value of its bridge from the Court of Claims. The only amount in fact in controversy here in the light most favorable to plaintiff is the value of the use of the franchise from the time of the destruction of the old bridge until the building of the new. This does not appear • to have been estimated in such a way that an extra allowance could be based upon it. Inasmuch as this is not a case in which a sub[79]*79stantial extra allowance could have been granted, it would seem that it was improper for the Special Term to have required as a condition of the permission to serve the amended answer the payment of any extra allowance.
The order should, therefore, be amended: First, so as to vacate the injunction; second, so as to authorize the defendant to serve an amended answer upon the payment of the costs of the action up to da be, within thirty days after the same should have been taxed by the clerk; third, with the right to plaintiff after such payment to discontinue, without costs, if so advised. As so amended the order should be affirmed, without costs to either party.
All concurred, except Howard, J., who voted for affirmance without modification.
Order modified as per opinion and as modified affirmed, without costs to either party.
See Laws of 1913, chap. 801, amdg. Laws of 1903, chap. 147, §§ 3, 4, as amd.— [Rep.
Free access — add to your briefcase to read the full text and ask questions with AI
Cite This Page — Counsel Stack
163 A.D. 76, 148 N.Y.S. 531, 1914 N.Y. App. Div. LEXIS 6938, Counsel Stack Legal Research, https://law.counselstack.com/opinion/halfmoon-bridge-co-v-canal-board-nyappdiv-1914.