Hale v. Bethlehem Steel Corp.

335 F. Supp. 559, 1971 U.S. Dist. LEXIS 10588
CourtDistrict Court, N.D. Illinois
DecidedNovember 30, 1971
DocketNo. 70 C 1967
StatusPublished

This text of 335 F. Supp. 559 (Hale v. Bethlehem Steel Corp.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hale v. Bethlehem Steel Corp., 335 F. Supp. 559, 1971 U.S. Dist. LEXIS 10588 (N.D. Ill. 1971).

Opinion

MEMORANDUM OPINION

DECKER, District Judge.

This is an action for damages arising out of an accident which occurred at a construction project in Burns Harbor, Indiana, when the plaintiff, Gerald A. Hale, fell from a platform upon which he was working and sustained serious injuries. Although a citizen of Indiana, plaintiff filed his complaint in the Circuit Court of Cook County, Illinois, against a number of defendants, one of whom was Bethlehem Steel Corporation, [560]*560which is neither incorporated nor maintains its principal place of business in either Illinois or Indiana. The suit was removed to this court, and I assumed jurisdiction based upon 28 U.S.C. §§ 1332 § 1441. A trial on the merits resulted in the dismissal as to all defendants other than Bethlehem and the finding of the following relevant facts.

In 1969 Bethlehem was engaged in the construction of an entire steel facility at Burns Harbor consisting of a number of buildings occupying an area of 25 to 30 acres. The accident occurred in one of these buildings called a “soaking pit”, which was a large structure, approximately 1000 feet long and 150 to 170 feet wide.

This “soaking pit” was being constructed under a so-called “turnkey” contract between Bethlehem and Surface Combustion Company. This contract provided, in effect, that Surface would be the prime contractor for the construction of the “soaking pit” and that it would deliver it to Bethlehem in “turnkey” (working) order. Morrison Construction Company (hereinafter “Morrison”), the corporation which was the plaintiff’s employer, was acting as the mechanical piping subcontractor under Surface.

Plaintiff was first employed as a pipe fitter on March 17, 1969, and on March 19, 1969, plaintiff and two other Morrison employees, Rogers and Dudy, were engaged in adjusting butterfly valves in the soaking pit area. During the morning of March 19, 1969, the three men were directed by Morrison’s foreman, Tiege, to cut out and take down a section of a four inch vertical pipe in order to enable another Morrison crew to lower some additional pipe into the basement of the soaking pit building.

Lying next to the pipe which was to be cut was a “pick”, a portable aluminum platform about 24 inches wide and 24 or 25 feet long, weighing about 90 to 100 pounds, and located approximately 25 feet above the floor of the soaking pit. One end of the “pick” was resting on a horizontal pipe, and the other end rested on the handrail of a catwalk or stairway. Although it was the customary practice to wire down picks of this type to the supporting structures, this had not been done.

Just prior to the accident, the plaintiff was directed by his foreman, Tiege, along with Rogers and Dudy, to use the “pick” in doing the pipe cutting. Rogers climbed from below onto the “pick” at about in the center. Plaintiff, carrying his cutting torch, followed Rogers and climbed onto the “pick” from the structural steel below. Plaintiff and Rogers sat down on the “pick” with their legs hanging over the north edge. As plaintiff lit his torch, Rogers moved to the east, or to his right. This shifting of his weight caused the “pick” to tilt to the north and caused plaintiff to fall to the basement of the soaking pit. Rogers grasped the handrail of the catwalk and saved himself from falling.

There is no dispute that the “pick” on which the accident occurred was owned by Bethlehem. There is an unresolved mystery as to how the “pick” arrived on the scene. One witness testified that it had been there for a week or two; another that it had been there two or three weeks prior to the accident. The plaintiff and another witness saw it for the first time that day.

During this period there were between 4,200 and 4,500 employees of various contractors and subcontractors engaged in construction. There was some vague evidence to the effect that the “pick” had been used at this location by some unidentified electricians. The superintendent of the electrical subcontractor, Fischbach & Moore, testified that they had done no work in this area within a period of five to six weeks prior to the accident.

Bethlehem had an engineering and construction department to oversee the complete Burns Harbor project. In March of 1969 the department consisted of a superintendent, Kennard Champness, and 35 employees, broken down into several groups, including a cost group and a field group. The field [561]*561group consisted of 15 to 18 field foremen, who were assigned to different buildings under construction. One of the field foremen was assigned to the “soaking pit”, and his primary function was to see that the schedules were maintained and the job carried forward according to the plans and specifications.

It was the responsibility of each field foreman to call any contractor error or unsafe practice to the attention of the prime contractor’s superintendent. Unless some immediate hazard of injury or accident was involved, the field foremen would not go to a contractor’s foreman or general foreman. None of the field foremen gave any orders to contractors’ or subcontractors’ employees. In addition to this, Bethlehem held monthly meetings attended by representatives of the various contractors and subcontractors, which meetings were concerned with general safety practices.

Mr. Champness’ department had two safety engineers for the entire construction area and construction work force. One or the other of the safety engineers attempted to cover the area each day, and if he saw an unsafe work practice, the safety engineer would contact the prime contractor’s superintendent in the same manner as the field foremen.

There was no evidence that any Bethlehem employee used the “pick” at that location or of any work that had been performed by Bethlehem at that elevation in the three-week period before the accident or of any future work to be performed by Bethlehem at that location.

It is in this factual setting that plaintiff asserts that defendant is liable for his injuries. Plaintiff’s first contention is that Bethlehem, being the owner of the property under construction and by virtue of its supervisory activities over this project, is a person who was in “charge of, or responsible for,” the work in question within the purview of the Indiana Dangerous Occupations Act.1

So far as that Indiana statute is concerned, I am governed by the decisional law of Indiana, where the accident occurred. Ever since the adoption of the Indiana Dangerous Occupations Act in 1911, the Indiana courts have narrowly construed the language, “have charge of, or responsible for”, to apply to the particular person or entity in charge of or responsible for the work at hand when the accident occurred. Prest-O-Lite Co. v. Skeel, 182 Ind. 593, 106 N.E. 365 (1914); Leet v. Block, 182 Ind. 271, 106 N.E. 373 (1914); Wyler v. Lilly Varnish Co., 252 N.E.2d 824 (Ind. App.1969); Zainey v. Rieman, 81 Ind. App. 74, 142 N.E. 397 (1924).

. The viability of Leet v. Block, supra, is clearly recognized in a diversity case decided by our Circuit Court of Appeals in Bruemmer v. Clark Equipment Company, 341 F.2d 23 (1965). There, Chief Judge Hastings, speaking for the court, said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frederick H. Bruemmer v. The Clark Equipment Company
341 F.2d 23 (Seventh Circuit, 1965)
Tyler v. Nolen
248 N.E.2d 186 (Indiana Court of Appeals, 1969)
Wyler v. Lilly Varnish Co.
252 N.E.2d 824 (Indiana Court of Appeals, 1969)
Kilmer v. Galbreth
218 N.E.2d 361 (Indiana Court of Appeals, 1966)
Hunsberger v. Wyman
216 N.E.2d 345 (Indiana Supreme Court, 1966)
Forcum-James, Inc. v. Johnson
59 N.E.2d 730 (Indiana Court of Appeals, 1945)
Leet v. Block
106 N.E. 373 (Indiana Supreme Court, 1914)
Prest-O-Lite Co. v. Skeel
106 N.E. 365 (Indiana Supreme Court, 1914)
Bedford Stone & Construction Co. v. Hennigar
121 N.E. 277 (Indiana Supreme Court, 1918)
Zainey v. Rieman
142 N.E. 397 (Indiana Court of Appeals, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
335 F. Supp. 559, 1971 U.S. Dist. LEXIS 10588, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hale-v-bethlehem-steel-corp-ilnd-1971.