Hale & McClure v. Johnson & Wiggins
This text of 6 Kan. 137 (Hale & McClure v. Johnson & Wiggins) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
The opinion of the court was delivered by
No. 1. “ Under the written contract Johnson & Wiggins were to receive $3.75 per perch for performing the whole of the stone work. As they only finished a part of the work, the value of the part they did perform, can be ascertained by the cost of completing the remainder of the building.”
General charge: “ If the jury believe that when Johnson and Wiggins abandoned the work, they did so in consequence of Hale and McClure’s not furnishing material as required by Johnson and Wiggins, then plaintiffs, would be entitled to recover $3.75 per perch actually erected, and for such damages as may have been proven that Johnson and Wiggins suffered in consequence of the failure of Hale and McClure to comply with their part of the contract.”
We are of the opinion that thé court was right in refusing the first of these instructions. It is no doubt true, that the rule which it is quite plain was intended to be expressed therein, or at least one similar in principle, might be found to apply in some measure to a case substantially like the one stated in the pleadings in this record; but if so applicable, it would be necessary that it should be couched in such terms as would not be calculated to mislead the jury, when they should come to pass [143]*143upon the evidence in the light of such rule. Such was not the case here. The instruction as it stands — and especially when considered in connection with some of the facts which are stated to have been proven, is eminently unfair in the criterion it furnishes by which to estimate the value of that portion of the work which was performed by the plaintiff. The term or expression “cost of completing,”-etc., is used in an unrestricted sense, and under the evidence might have been held by ■the jury to include whatever the defendants below might have shown they had paid, or had seen fit to agree to pay, for the completion of the work, even to an amount much greater than the actual and reasonable value thereof. It hardly needs to be said, that the giving of an instruction which would have permitted the jury to go to the extent indicated, would have been improper.
As to the last instruction above set out, we think it was wrong, and for the reason that it is not in conformity with the rule laid down in the statute by which to estimate the amount which a party in a case of this kind is entitled to recover. This was an action brought under the provisions of the Mechanics’ Lien Act, ch. 137, Comp. L. 1862. Section 11 of said act provides as follows:
“ Sec. ll.-"When the owner of thé land shall have failed to perform his part of the contract, and by reason thereof the other party shall, without his own default, have been prevented from performing his part, he shall be entitled to a reasonable compensation for as much thereof as he has performed in proportion to the price stipulated for the whole; and the court shall adjust his claim accordingly.”
The difference between the rule here established and that expressed in the instruction given is apparent at a glance, and needs not to be enlarged upon. For the [144]*144error of the court below in giving tbis instruction tbe judgment must be reversed, and the cause sent back for a new trial.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
6 Kan. 137, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hale-mcclure-v-johnson-wiggins-kan-1870.