Hale Electric Co. v. West Virginia State Board of Education

6 Ct. Cl. 94
CourtWest Virginia Court of Claims
DecidedJune 27, 1952
DocketNo. 762
StatusPublished

This text of 6 Ct. Cl. 94 (Hale Electric Co. v. West Virginia State Board of Education) is published on Counsel Stack Legal Research, covering West Virginia Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hale Electric Co. v. West Virginia State Board of Education, 6 Ct. Cl. 94 (W. Va. Super. Ct. 1952).

Opinion

ROBERT L. BLAND, Judge.

Claimant Hale Electric Company, Inc., a Pennsylvania corporation, with principal office in the city of Pittsburgh, and duly qualified to hold property and transact business in the state of West Virginia, seeks an award against West Virginia state board of education for $9,659.02. Its claims is divided into two items, one for the sum of $3,274.36 and the other in the sum of $6,384.66.

The two and one-half million dollar project of the West Virginia state board of education for the construction and equipment of a science hall on the campus of Marshall college, a state-controlled educational institution located in the city of Huntington, was divided into seventeen different contracts, according to plans, specifications and drawings made by L. D. Schmidt, registered architect, of Fairmont. Pursuant to its duly published advertisement, inviting proposals for these various contracts, sealed bids were opened at the board’s office in the state capitol, in the city of Charleston, on the 4th day of December, 1947. Claimant had submitted two bids, one on contract No. 7, which according to the architect’s instructions to bidders includes the general electrical installation, not including the general experimental laboratory equipment, section 29, paragraphs 17 to 45, both inclusive, but all others as shown on drawings E-l to E-16 both inclusive, and specified under section No. 29; and the other on contract No. 10, which includes the electrical experimental laboratory equipment as shown on drawings E-l to E-16, both inclusive, of section No. 29. Its bid on contract No. 7 was in the [96]*96sum of $178,293.00. Its bid on contract No. 10 was in the sum of $49,475.00. On the two contracts combined claimant was the lowest bidder. Contract No. 7 was awarded to claimant for the said sum of $178,293.00. Contract No. 10 was not awarded on account of limitation of funds.

It is the position of claimant Hale Electric Company that contract No. 7 provides that the contractor shall perform in a workmanlike manner all of the work described under Contract No. 7, which includes section 29 of the specifications and drawings E-l to E-16, inclusive, in connection with the general installation, but not including the electrical experimental laboratory equipment as specified under section No. 29, paragraphs 17 to 45, inclusive; and that contract No. 10 is a contract covering the furnishing of all necessary tools, labor and equipment to complete in a workmanlike manner all work required for the furnishing and delivering to the building site electrical experimental laboratory equipment.

Claimant maintains that it was its understanding that both contracts 7 and 10 would be awarded to it and that it confidently expected that contract No. 10 would ultimately be awarded to it. It contends that the architect as the agent of the state represented to its president that both contracts 7 and 10 would be awarded to the lowest bidder on the two contracts combined. It also contends that the state board of education had advised it by letter that it would later be awarded contract No. 10. However, when proposals were again invited on contract No. 10 claimant again submitted a bid, but it was not the lowest bid, and the contract was awarded to the Standard Electric Time Company, of Huntington, West Virginia. With knowledge of this fact claimant admits that it started to do work, as it contends, required to be done under contract No. 10. While testifying in support of the claim claimant’s president was asked the following question:

“Q — After you were awarded Contract No. 7, did you have to make any preparations to perform the work, and what did you do?” and answered:
[97]*97“A — Yes, we did. To begin with, we had to buy conduit and fittings necessary for both contract No. 7 and contract No. 10, because the conduits had to be installed simultaneously. For one thing, slabs, and in masonry, before slabs could be poured, both sets of conduit had to be placed, therefore we estimated sufficient conduit and fittings to do the roughing-in work for both contracts as the building progressed.”

The record of the claim is voluminous. The transcript of evidence consists of two hundred and fifty-seven pages. In addition to such evidence claimant introduced as its exhibit No. 1, a large volume, containing approximately three hundred and forty-five pages, prepared by architect Schmidt, and embracing all of the documents pertaining to the science hall project, such as advertisement for bids, instructions to bidders, the form of proposal, form of contract, specification, etc.

It was admitted by claimant’s president that all of the work performed by it under what it contends was required to be done under contract No. 10 was done subsequent to the time that it had notice of the fact that contract No. 10 had been awarded to Standard Electric Time Company. After contract No. 10 had been awarded as aforesaid, claimant ceased to do any further work on the electrical project. Respondent thereafter contracted with Harry Goheen or Goheen Electric Company to complete the work of connecting the experimental laboratory equipment at a cost of $3,274.36. When claimant submitted its final estimate respondent, at the instance of the architect, deducted from said estimate the said sum of $3,274.36 which it had paid to Goheen for connecting the experimental laboratory equipment on the ground that such work was provided to be done under contract No. 7. Claimant also contends that it is entitled to be compensated on a quantum meruit basis the reasonable value, that is to say the sum of $6,384.66 for the labor and materials which it furnished for laying the conduit for installing the special experimental laboratory equipment which it maintains was originally called for by contract No. 10.

During the progress of the hearing of the claim a number of objections were made, and urged with insistence, to the admissi[98]*98bility of evidence. The court’s rule 9 relates to proof governing testimony. The Court of Claims is not a court of law. It is expressly provided in the act of the Legislature creating the Court of Claims that it shall not be invested with or exercise the judicial power of the state in the sense of article eight of the consttiution of the state. As a special instrumentality and arm of the legislature its peculiar function is to investigate the merit of claims asserted against the state, or any of its agencies, and recommend the disposition of such claims. The court is not bound by the usual common law or statutory rules of evidence. The court may accept and weigh, in accordance with its evidential value, any information that will assist the court in determining the factual basis of the claims. Judge Charles J. Schuck, a former member of the Court of Claims, an able and distinguished lawyer, was wont to say, when objections were made to evidence, that members of the court were lawyers, or, at least had license to practice law and would endeavor to separate the “wheat from the chaff.”

Claimant agrees that the sole issue in the case is whether or not contract No. 7 which was awarded to claimant required claimant to lay the conduit for and otherwise install the special laboratory equipment referred to in paragraphs 17 to 45, inclusive, of section No. 29 of the specifications. Claimant contends that such installation was not included in contract No. 7 but was intended to be included in contract No. 10.

To establish the merit of its claim claimant bears the laboring oar.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
6 Ct. Cl. 94, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hale-electric-co-v-west-virginia-state-board-of-education-wvctcl-1952.