Halamicek Bros. v. R & E Asphalt Service, Inc.

737 S.W.2d 193
CourtMissouri Court of Appeals
DecidedOctober 15, 1987
Docket50270
StatusPublished
Cited by6 cases

This text of 737 S.W.2d 193 (Halamicek Bros. v. R & E Asphalt Service, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Halamicek Bros. v. R & E Asphalt Service, Inc., 737 S.W.2d 193 (Mo. Ct. App. 1987).

Opinion

SMITH, Presiding Judge.

Defendant appeals from a judgment against it based upon a jury verdict in a breach of contract action.

Plaintiff is a general contractor engaged by Delsan Aluminum Products to construct a warehouse and parking lot. Defendant is a subcontractor employed by plaintiff to pave the parking lot. The paving was to be done according to blueprints and specifications prepared by plaintiff and Delsan. The specifications required defendant to guarantee its work against defects of materials or workmanship for one year from the date of acceptance. The subcontract required strict adherence to the plans and specifications. The subcontract also contained a specific indemnity provision which stated:

“The subcontractor shall indemnify and hold harmless the contractor from all liabilities, claims, or demands for injuries or damages to any persons or property which shall arise out of the work of the subcontractor under this agreement.”

Pursuant to the subcontract, defendant completed the paving and was paid. Plaintiff also completed its work and received the payment called for in its general contract. Within a few months (less than a year after completion), problems began to appear in the parking lot. The owner notified plaintiff which in turn notified defendant. Despite repeated requests that defendant correct the problem defendant refused. This suit followed. Plaintiff has not made the required corrections and owner has not instigated suit against plaintiff. At trial both owner and plaintiff indicated their concurrence that plaintiff was responsible under its general contract for providing a satisfactory parking lot and plaintiff recognized that it has not done so and has an obligation to do so.

The jury found a breach of contract by defendant and on appeal defendant does not challenge that finding. The jury assessed damages at $40,000, attorney’s fees at $8602, and expenses at $10,000. The last two categories were authorized recoveries under the terms of the subcontract. Defendant raises four claims of error. The first two, challenging standing and absence of damages to plaintiff, posit the legal question of plaintiffs right to recover where it has neither effectuated the repair nor been sued by the owner to recover the costs of repair. The next point deals with the testimony of an expert witness and the final point challenges the amount of the verdict.

Both parties are in agreement that the contract between the plaintiff and defendant was a third party beneficiary contract with Delsan as the third party beneficiary. Third party beneficiary is the nomenclature given to one who is not privy to a contract nor to its consideration but to whom the law gives a right to maintain a cause of action for breach of contract. Laclede Investment Corporation v. Kaiser, 596 S.W.2d 36 (Mo.App.1980) [6]. Third party beneficiaries fall into three categories — donee, creditor and incidental. The first two categories may recover, the third may not. Id. [7-10]. A creditor beneficiary is one who is not a donee beneficiary and for whom the performance of a promise by the promisor to the third party beneficiary contract will satisfy an actual or supposed or asserted duty of the promisee to the beneficiary. Id. Delsan clearly fits that definition. Defendant’s performance of its subcontract will satisfy in part the duty of plaintiff to Delsan under the general contract. Delsan could recover against defendant under the subcontract. From this defendant concludes that until plaintiff has been sued by Delsan or has in fact effectuated the repairs, only Delsan can seek recovery under the contract. We disagree.

*196 In Liberty Financial Management Corporation v. Beneficial Data Processing Corporation, 670 S.W.2d 40 (Mo.App.1984) we approved the bringing of the action by the promisee as representative of the third party beneficiaries. 1 In dicta we indicated our doubt that that representative capacity need be pleaded where all parties were aware of the rights being litigated and the victim of the breach of contract. In our case it is equally clear what breach is being litigated and who the ultimate victim is. An officer of Delsan testified at the trial as a witness for plaintiff.

Even without the authority of Liberty Financial, we have no hesitation in finding that plaintiff has standing to bring this action. Plaintiff and defendant were the contracting parties. Defendant’s breach of the contract was a breach of its promise to plaintiff and we know of no doctrine of law which would preclude plaintiff from suing for that breach. Plaintiff has also sustained damage from that breach. By its contract with Delsan it was required to provide a satisfactory parking lot. It did not do so. Its failure to do so was the result of defendant’s breach. Its damages are measured by the cost to it of complying with that portion of its contract with Del-san. Those are the damages it presented to the jury and which the jury awarded. It was unnecessary for plaintiff to first make the repairs and then sue for those costs in order for it to recover, just as such a course of action would be unnecessary had the contract been for paving of plaintiff’s premises. Plaintiff is not required to first repair and then rely upon the continued solvency of defendant to recoup its damages. Nor is there any reason for plaintiff to be forced to undergo suit by Delsan to establish a legal duty plaintiff admits it has. Plaintiff bargained for defendant’s performance, not for indemnity for a recovery by Delsan. Defendant contends that its relationship to plaintiff is that of a surety, therefore, it has no duty to reimburse plaintiff until plaintiff has been subjected to a judgment by Delsan. While the. contract contains an indemnity provision, it is not an indemnity contract. It is a performance contract and defendant is not being held for indemnity but for breach of performance.

Defendant also contends that it may be subject to multiple recoveries, as Del-san, as a third party beneficiary, also has the right to recover against it. If defendant has been injured, it is a self-inflicted wound. Both joinder and interpleader were available to it to prevent such a possibility. Rules 52.04, 52.07. Further, discharge of the defendant by plaintiff, as by satisfaction of judgment, can be effective against the credit beneficiary. See Restatement of Contracts § 143; Sears, Roebuck & Co. v. Jardel Co., 421 F.2d 1048 (3rd Cir.1970) [8, 9], We hold that plaintiff had standing to bring this action and that the court committed no error in submitting prospective cost of repairs as the measure of damages.

Defendant’s next point challenges the testimony of Henry Halamicek as to his opinion of the cost of repairing the parking lot. The matter is not preserved.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monarch Fire Protection v. Freedom Consulting
678 F. Supp. 2d 927 (E.D. Missouri, 2009)
Strain-Japan R-16 School District v. Landmark Systems, Inc.
965 S.W.2d 278 (Missouri Court of Appeals, 1998)
State Ex Rel. Chase Resorts, Inc. v. Campbell
913 S.W.2d 832 (Missouri Court of Appeals, 1995)
County Asphalt Paving Co. v. 1861 Group, Ltd.
851 S.W.2d 577 (Missouri Court of Appeals, 1993)
Community Title Co. v. Roosevelt Federal Savings & Loan Ass'n
796 S.W.2d 369 (Supreme Court of Missouri, 1990)
Kansas City NO Nelson Co. v. MID-WESTERN CONSTRUCTION CO. OF MO., INC.
782 S.W.2d 672 (Missouri Court of Appeals, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
737 S.W.2d 193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/halamicek-bros-v-r-e-asphalt-service-inc-moctapp-1987.