Hagar v. Elmslie

107 F. 511, 46 C.C.A. 446, 1901 U.S. App. LEXIS 3734
CourtCourt of Appeals for the Third Circuit
DecidedMarch 4, 1901
DocketNo. 34
StatusPublished
Cited by1 cases

This text of 107 F. 511 (Hagar v. Elmslie) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hagar v. Elmslie, 107 F. 511, 46 C.C.A. 446, 1901 U.S. App. LEXIS 3734 (3d Cir. 1901).

Opinion

GRAY, Circuit Judge.

This is an appeal from the district court of the United States for the Eastern district of Pennsylvania in a cause of contract, civil and maritime. 101 Fed. 840. The action arose out of a charter party of the bark Banklands, of -which the appellee was the managing owner, and the appellants were the charterers,, for a voyage from Philadelphia and New York to Rio de Janeiro. Under that charter party the vessel loaded a general cargo, consisting of locomotives, car materials, case oil, resin, lumber, etc. The provisions relevant to the present case are the following:

“It is agreed that the lay days shall be as follows (If not sooner dispatched), commencing from the time the vessel is ready to receive cargo: 65 running days, Sundays excepted, for loading and discharging;- * * * and that for each and every day’s detention by default of the said [charterers] or agent $05.85 United States gold dollars per day, day by day, shall be paid by said [charterers] or agent. * * * The cargo to- be received and delivered alongside, within reach of the vessel’s tackle, free of lighterage to vessel.’-' “Vessel to be consigned to charterers’ agents at Rio free of commission for doing- the vessel’s inward business.”

- The claim of the libelants embraced the following three items: (1) Customs agency fee at Rio; (2) lighterage of cargo at Rio; (3) demurrage- there incurred. In regard to the first two items, the court below said:

-. “The charge for lighterage is admitted, and need not be further considered. A credit, however, must be allowed thereon for the money received-by the master as a present from the owner of the lighters. The item for commission is too large. The sum paid to the broker by the master was for doing all the ship’s business at. Rio, and not merely for,doing her inward business. The respondents were only liable for one-half of this item.”

As thé’jüdgé, íú our opinion, was clearly right in the disposition made of these items, they need'not further occupy our attention. The principal question is that arising out of the claim for demur-rage. In addition to the provision as to lay days and demurrage, already quoted from the charter party, which was dated December 28, .1894,, a siibsequent agreement as to the same matters, was- en [513]*513tered into between the parties by the following lettér from the appellants to the appellee’s agent in New York, dated January 5, 1895, the date at which the charter party was signed:

“We sign inclosed c/p with understanding that the clause, ‘General average, if any, to he settled according to York-Antwerp rules of 1890,’ not binding in case shippers object to it. Also for discharging at Rio as agreed by captain regarding the days for car material and locomotives, viz. he to serve notice on each lot, and lay days to count as one lot.
Viz. 35 days locos. 6 to 10 “ car. to count as 35.”

On February 18, 1895, a second agreement was made by the shippers with the master of the Banklands in writing, as follows:

“We refer to your charter party, dated December 28th, 1894, in which it is stipulated that your vessel is to bo loaded and discharged in sixty-five running-days, Sundays excepted; and in consideration of your having indorsed on bills of lading a clause allowing the consignees thirty running days, Sundays excepted, with a letter allowing five more, if required, for discharging the locomotives, and six like days for discharging car material, — in all, forty-one days for these two lots of goods, — I agree that if the number of lay days left after completion of loading, over and above the forty-one, be not sufficient to discharge the other cargo, I will pay demurrage here as per charter party for any and all days used over and above the sixty-five days stipulated in chatter.”

On February 19, .1895, when the vessel was loaded, it was further agreed between the shipper and master as follows:

“We agree that twenty-three running days (23) have been used in loading Br. Bk. Banklands under charter dated December 28th, 1894, leaving forty-two (42) «running days, Sundays excepted, for discharging the vessel at Rio de Janeiro.”

In discussing these various stipulations, the learned judge of the court below says:

“But the parties have treated the agreement of January 5th, concerning notice, as modifying the apparently contradictory agreement of February 18th, so as to allow for discharge of the locomotives and car material 35 days instead of 41. Accepting this construction, the final result appears to be that the ship would have at least 7 days to unload the general cargo, and might have more. In fact, she had 5 days more, making 12 in all; for the consignees of the locomotives, who were themselves to unload this part of the cargo, used only 30 days in so doing. The single question, therefore, to be considered, is whether the libelants’ claim for an additional 13 days should be allowed. Only 8 of these days were actually occupied in unloading cargo, the charge for the remaining 3 arising under the following circumstances: The ship arrived at Rio on Saturday, March 23d, and on the morning- of that day the master called upon the respondents’ agents, in order to have his inward customs business attended to. This visit was in accordance with instructions received from the respondents before the ship sailed from New York, hut by some oversight the agents had not been notified of the instructions, and declined to act. They recommended the captain to apply to another firm of brokers, to whom he had also received a letter of introduction from the respondents. At the office of this firm he found that the principal was absent, and could not be seen before Tuesday; Monday being a holiday, when no business would be done. On Tuesday the firm refused to enter the vessel, and the captain thereupon employed another broker, who finally undertook the ship’s business. The vessel was entered at the custom house on the same day, and the next two days were employed by the master in making arrangements to unload the vessel by lighters; this course being necessary, owing to the regulations of the port that were then in force. On Wednesday the consignees of the general cargo were notified that the ship was prepared to deliver, but, as such consignees are allowed from one to" two days’ notice by the [514]*514custom of the port, actual delivery could not be begun before March 29th. These 5 days — March 23d to 28th, inclusive, Sunday excepted — form part of the libelant’s claim. I think 3 of them should be allowed. The respondents were at fault for‘failing to notify their agents at Rio of the instructions communicated to the captain at New York. If such instructions had been given, no reason is apparent why the ship could not have been entered on Saturday, and every aryahgement made to begin discharging on Tuesday. The lay days would then have begun on Tuesday, March 26th, and I think they should now be counted from that date.”

Agreeing with the learned judge in the view thus stated by him, we have only to consider the remaining question as to the allowance of the eight additional days for demurrage. As to these his •opinion is as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New Ruperra S. S. Co. v. 2,000 Tons of Coal
124 F. 937 (D. Massachusetts, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
107 F. 511, 46 C.C.A. 446, 1901 U.S. App. LEXIS 3734, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hagar-v-elmslie-ca3-1901.