Haffler v. McKinney

157 S.W.2d 92, 288 Ky. 782, 1941 Ky. LEXIS 167
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedNovember 21, 1941
StatusPublished
Cited by9 cases

This text of 157 S.W.2d 92 (Haffler v. McKinney) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Haffler v. McKinney, 157 S.W.2d 92, 288 Ky. 782, 1941 Ky. LEXIS 167 (Ky. 1941).

Opinion

Opinion op the Court by

Judge Thomas

Nevers-

In August, 1935, appellee and the defendant below, A. B. McKinney, resided in Morehead, Nowan County, Kentucky, and was the owner of a lot in the business section of the city upon which was erected a brick business house with some dwelling apartments above the first story, the latter being used for business purposes. He concluded to not only remodel his present building, but to construct an additional store room on the adjoining vacant portion of his lot, and to make other improvements. Pursuant thereto he contacted appellant and plaintiff below, Whayne W. Haffler, who was then and for many years prior thereto had been a qualified architect located in the city of Lexington, Kentucky. Plaintiff first prepared sketches, and later he prepared specifications, blueprints and all necessary preliminary work required of him, and furnished a copy or copies to the defendant, and others to contractors for the obtention of bids to complete the job. The lowest bid was made by a contractor residing in Ashland, Kentucky, and it was above $17,000, without an alternative proposition to construct an extension to the old store room on the portion of the lot back of it, but the bidder named a price for such alternative work of above $3,000 or an aggregate sum for all of the contemplated alterations and additions of more than $20,000.

In the meantime plaintiff was negotiating with a local contractor in Morehead, a friend of his named L. H. Boggess, who estimated the cost of the entire work (apparently excluding the extension of the old building) at $16,694.54, but Boggess testified that up to the time of making that estimate he had not seen plaintiff’s plans and specifications, although, as we gather from the evidence, they had been sent to defendant before the witness Boggess finally submitted his estimate based upon information obtained from defendant. The latter retained the plans and never accepted any bid from any contractor and, therefore, never procured the contemplated work to be done.

*784 On February 8, 1937, plaintiff filed this action against defendant in tbe Rowan circuit court to recover judgment against bim for tbe sum of $676, wbicb he alleged was a reasonable fee for tbe work be bad done and tbe time devoted in tbe preparation of plans and specifications — all of wbicb be did (as averred) at tbe request of defendant. Tbe answer was a formal denial, followed by an affirmative separate paragraph alleging that “tbe plaintiff assured bim that be could draw up plans and specifications to do said repairing on said building and rooms to cost not exceeding $10,000, and tbe plaintiff assured bim that be could draw such plans and specifications to do tbe work of repairing said store bouse and rooms at a cost not exceeding said sum and this defendant advised bim at tbe time that be, defendant, could not do this work if it cost more than $10,000.” He then alleged that no bid was obtained for tbe completion of tbe entire contemplated work for less than $20,000, and that he abandoned tbe idea of making tbe improvements and declined to accept any of tbe tendered bids. A reply and following pleadings made tbe issues, and upon trial tbe jury, under tbe instructions of tbe court, returned a verdict for defendant, followed by a judgment dismissing plaintiff’s petition, to reverse which be prosecutes this appeal after his motion for a new trial was overruled.

A number of grounds were relied on in bis motion, but practically all of them are abandoned on this appeal, except tbe alleged error of tbe court in overruling bis motion for a peremptory instruction directing the return of a verdict in bis favor for tbe amount sued for, since no attack was made upon its reasonableness. We have concluded that tbe court should have sustained that motion, and because of wbicb we will devote no part of this opinion to a discussion of any other ground relied on, although it might be said that we exceedingly doubt if any of them, singly or in tbe aggregate, is sufficient to authorize a reversal of tbe judgment.

Tbe Court by its instruction No. 1 submitted to tbe jury only one factual issue, wbicb was, that a verdict should be returned for plaintiff for tbe amount claimed in bis petition, unless the jury should believe from the evidence “that at tbe time tbe plaintiff contracted with tbe defendant for tbe preparation of tbe plans and specifications mentioned in tbe evidence that it was mutually *785 understood and agreed between them that the costs of the improvements covered by said plans and specifications as finally completed was not to exceed $10,000.00, and if you further believe from the evidence that the costs of the improvements contemplated by said plans and specifications exceeded the sum of $10,000.00 and in which event you will find for the defendant.”

It will thus be seen that the whole case was made to turn on the sole defense of whether or not plaintiff recommended to defendant that the cost of the repairs and additions to defendant’s building — as finally settled and outlined in the blueprints and specifications furnished by plaintiff — would not exceed $10,000 when that figure was only about one-half of what the cost eventually proved to be. That issue, as will be seen, is exclusively a factual one to be determined by the evidence heard at the trial, and which embraces all circumstantial evidence as well as express and positive proof. In determining that question we will not encumber the opinion with a recitation of the testimony of each witness heard at the trial, nor will we refer to all of the twenty-five or thirty letters and telegrams passing between the parties, but only to those bearing upon the single issue submitted to the jury for its determination.

At the beginning of the negotiations between plaintiff and defendant with reference to the drawing of plans for the remodeling of plaintiff’s buildings and enlarging them, plaintiff as a result of his first visit to the premises made some sketches, but which called for much less work and less extensive remodeling than what was finally agreed on for his architectural submission to contractors for bids. Sometime following the first submitted sketches for the contemplated alterations, plaintiff expressed the belief that the work then under contemplation would probably cost between $7,000 or $8,000, and which estimate he communicated to defendant and testified to at the trial, but as time went on additional alterations and extensions were added to the first contemplated plans, and plaintiff’s finally submitted blueprints and specifications embraced not merely the first submitted plans, but also the additions and alterations ' that were later made. As we have hereinbefore stated, many letters passed between the parties, as well as some telegrams, and also inter partes meetings and conversations. On March 17, 1936, defendant wrote *786 plaintiff, saying: “Our (lot) line takes in all the walk •on Fairbank and Main St. So we have nothing to worry about there. We would like to hear from you in regard to the estimate cost of building as soon as possible.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Osborne v. Unigard Indemnity Co.
719 S.W.2d 737 (Court of Appeals of Kentucky, 1986)
Pence Mortgage Co. v. Stokes
559 S.W.2d 500 (Court of Appeals of Kentucky, 1977)
Goss v. Personnel Board
456 S.W.2d 824 (Court of Appeals of Kentucky, 1970)
Scott v. Patterson
400 S.W.2d 526 (Court of Appeals of Kentucky, 1966)
Jones v. Mathis
329 S.W.2d 55 (Court of Appeals of Kentucky, 1959)
Travelers Ins. Co. v. Wright
216 S.W.2d 909 (Court of Appeals of Kentucky (pre-1976), 1949)
Corbin's Ex'rs v. Corbin
194 S.W.2d 65 (Court of Appeals of Kentucky (pre-1976), 1946)
Minary v. Hammond
170 S.W.2d 873 (Court of Appeals of Kentucky (pre-1976), 1943)
Monson v. Commonwealth
161 S.W.2d 55 (Court of Appeals of Kentucky (pre-1976), 1942)

Cite This Page — Counsel Stack

Bluebook (online)
157 S.W.2d 92, 288 Ky. 782, 1941 Ky. LEXIS 167, Counsel Stack Legal Research, https://law.counselstack.com/opinion/haffler-v-mckinney-kyctapphigh-1941.