Haddock v. McClendon

266 S.W.2d 74, 223 Ark. 396, 3 Oil & Gas Rep. 1219, 1954 Ark. LEXIS 678
CourtSupreme Court of Arkansas
DecidedMarch 29, 1954
Docket5-356
StatusPublished
Cited by4 cases

This text of 266 S.W.2d 74 (Haddock v. McClendon) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Haddock v. McClendon, 266 S.W.2d 74, 223 Ark. 396, 3 Oil & Gas Rep. 1219, 1954 Ark. LEXIS 678 (Ark. 1954).

Opinion

Ward, J.

This appeal raises this general question: What acts on the part of a lessee constitute a compliance with the provision to “commence drilling operations” before the expiration of an oil and gas lease?

On February 23, 1943 appellees, L. A. McClendon and Susie McClendon, executed a standard oil and gas “Commencement Form Lease,” form No. 88, on certain lands to appellants, Fred T. Haddock and W. S. Bellows. The principal term of the lease was 10 years from the date of execution and was to be kept in force by the payment of yearly rentals, which in this instance were all paid, thereby extending the term of*the lease to February 23, 1953. The lease also contained this paragraph:

“Notwithstanding anything in this lease contained to the contrary, it is expressly agreed and covenanted that if the lessee, his heirs, successors or assigns, shall commence drilling operations at any time while this lease is in force, this lease shall remain in force and effect, and the term and life shall continue as to the entire acreage described herein, so long as such operations are prosecuted, and if production results from such operations, then as long thereafter as such production continues.” (Emphasis supplied.)

Apparently due to the fact that appellants were waiting on the outcome of nearby oil developments, or at least it is a fact, they did not see fit and did not attempt to drill an oil well on said lands until the attempt, as hereafter discussed, was made shortly before the expiration date of the lease. While appellants were engaged in an attempt, begun February 18, 1953, to proceed with drilling operations they were notified by appellees, on March 4, 1953, that the lease had terminated, and on March 14th following appellants filed this suit against appellees asking to have their title to the oil and gas lease quieted in them. Appellees filed a general denial and also specifically denied that Haddock and Bellows, as lessees, had “commenced or caused to be commenced drilling operations on the above described land which would operate to continue said lease in force and effect beyond the expiration of the primary term, ’ ’ and they ask that the said oil and gas lease be canceled, set aside and held for naught. On final hearing the chancellor dismissed the complaint and canceled the lease, giving, in part, the following reasons: Nothing was done by appellants until the closing days of the lease; appellants did not do what was necessary under the terms of the lease to protect their interest and prolong the life of the lease; and, apparently the purpose of appellants in starting the operations was to see what the result of a nearby well would be. It was further noted by the chancellor that had appellants “in good faith, gone in on the last day and entered upon this property and commenced to drill for gas or oil they would have had their protection. ’ ’ From this decree appellants prosecute this appeal.

Although the testimony is in most part not in conflict we deem it necessary to set out portions of it hereafter in some detail.

Appellant Haddock is an oil producer who lives in Oklahoma and appellant Bellows is a general contractor who lives in Houston, Texas. Knowing that their lease from appellees would expire on February 23, 1953, and apparently being aware of the oil production near the leased land, they employed Mr. George Belt, a practical oil man in Oklahoma, early in January 1953, to come to Arkansas and drill a well 9,400 feet deep on the leased premises. Under instructions Belt offered to pay appellees a substantial sum of money if they would extend the expiration date of the lease for something like sixty days, but appellees refused to do this. Then Belt made inquiry with the view to obtaining a drilling rig which would he capable of drilling to a depth of 9,400 feet, which depth, it is conceded, will be necessary to drill in this instance with any hopes of striking oil or gas. Not being able to obtain such a rig readily Belt made arrangements with Warren and Hollyfield for a smaller drilling rig known as a “Cardwell Rig,” which uses a cable. It is conceded by appellants that this rig is not capable of drilling the desired depth, but Belt says that he secured it only for the purpose of putting down about 200 feet of soil pipe in preparation for a larger drilling operation. Before the expiration date Belt made application to and secured a permit from the Arkansas Gas Commission to drill the well to a depth of 9,400 feet, and a few days before drilling operations started on February 18th Belt built a road up to the drilling site. This road would take care of ordinary heavy traffic but was not in shape to take care of a heavy drilling rig such as would eventually have to be used. The Cardwell rig was moved on location on February 18th and after encountering many difficulties, including quicksand, they were able to drill about 30 feet by February 23rd and had drilled to the depth of 52 feet by March 12, 1953, but were not able to install all of the surface pipe.

For a reversal, the principal contention of appellants is stated in this way:

‘ ‘ The employment of a cable tool drilling rig for the purpose of setting surface casing on the lease, and the actual making of a hole with that equipment constituted drilling operations while this lease was in force.”

In support of this contention they cite the following authorities: Jackson v. Gilbert, 216 Ark. 501, 226 S. W. 2d 59; Winn v. Collins, 207 Ark. 946, 183 S. W. 2d 593; Allen v. Palmer, et al., 201 Okla. 673, 209 Pac. 2d 502; and McCallister, et al. v. Texas Company, (Tex. Civ. A.) 223 S. W. 859.

The Jackson case, supra, dealt with a coal mining lease where it was alleged that the lessee had violated a provision of the lease requiring him “to begin the establishment of a plant within the first year. ’ ’ The expiration date was January 1st and it was shown that appellee began stripping overburden with a bulldozer on the previous December 21st and removed 4 tons of coal on December 23rd; then, deciding the bulldozer was not suitable, he brought in a dragline on December 30th; and appellee had installed two boxes, dragline cover and shed. In denying cancellation of the lease we said:

“We think the requirement is met by the installation of such machinery and equipment as are appropriate to the development of the leasehold. The lease itself permits the lessee to remove the top vein of coal ‘by the steam shovel process or other equally good processes.’ ”

The Winn case, supra, deals with the expiration clause in a bauxite mining lease. The lessee there had until April 29, 1943 to begin active mining operations. The proof showed that on February 7th test mining began and that in the early part of April a shaft was being sunk to see if bauxite could be mined in that way and it was discovered that they could only mine by open pits. On April 28th a scraper and tractor were in use removing the overburden. Although no bauxite had been mined we held the above facts showed “that active mining operations began in due time.”

The Allen case, supra, involving an oil and gas lease, deals with a question similar to the one presented here. Apparently this case is cited by appellants to show that it is not necessary to have a complete drilling outfit on the ground before the expiration date. There the court posed the question this way:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Hess Corp.
649 F.3d 891 (Eighth Circuit, 2011)
Vickers v. Peaker
300 S.W.2d 29 (Supreme Court of Arkansas, 1957)
Moore Oil, Inc. v. Snakard
150 F. Supp. 250 (W.D. Oklahoma, 1957)
Hill v. Larcon Company
131 F. Supp. 469 (W.D. Arkansas, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
266 S.W.2d 74, 223 Ark. 396, 3 Oil & Gas Rep. 1219, 1954 Ark. LEXIS 678, Counsel Stack Legal Research, https://law.counselstack.com/opinion/haddock-v-mcclendon-ark-1954.