Habitat Education Center, Inc. v. United States Forest Service

603 F. Supp. 2d 1176, 2009 U.S. Dist. LEXIS 22340, 2009 WL 738868
District Court, E.D. Wisconsin·Decided March 19, 2009·No. Case 08-C-0043·Published·Cited by 4 cases

Opinion

DECISION AND ORDER

LYNN ADELMAN, District Judge.

Plaintiffs filed the present action pursuant to the Administrative Procedure Act (“APA”), 5 U.S.C. § 706, arguing that in approving a project (the “Fishbone” project) in the Chequamegon-Nieolet National Forest (“CNNF”), the Forest Service violated the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4821 et seq., and the National Forest Management Act (“NFMA”), 16 U.S.C. § 1600-1687. Before me are the parties’ cross-motions for summary judgment.

I. BACKGROUND

The CNNF covers approximately 1.5 million acres in northern Wisconsin, where between the mid-nineteenth century and the Great Depression timber barons and forest fires reduced Wisconsin’s old-growth forests to “brush fields, eroded fallow pastures, and burned-over stump patches.” See History of the Chequame-gon-Nicolet National Forests (“History of CNNF”) at 2-4. 1 After the timber barons denuded the forest, speculators sold what remained as farmland. The land was unproductive, however, and the farmers could not earn enough to pay their property taxes, causing them to abandon their lands or forfeit them to county governments. Id. at 8; Fishbone Record of Decision (“ROD”) at 2.

In the late 1920s, the federal government began purchasing the abandoned land from the counties and managing it as a national forest. During the Great Depression, the Civilian Conservation Corp planted thousands of acres of pine throughout the barren farmland. ROD at 2. In 1933, the government’s collective purchases were designated as the Nicolet National Forest. Because the national forest emerged from the government’s purchases of individual tracts of land and was not carved from large blocks of public land, it had a fragmented ownership pattern, characterized by a patchwork of public and private lands. History of CNNF at 4. In 1933, these lands were aggregated into two, noncontiguous units, the Nicolet East and Nicolet West. The Nicolet West eventually became the Chequamegon National Forest. For sixty years, the Forest Service managed the Nicolet and Chequame-gon units as separate national forests. Since 1993, however, the units have been managed as a single entity, now known as the Chequamegon-Nieolet National Forest. Id. Although the amount of national forest land has grown over the years, the Nicolet and Chequamegon units remain noncontiguous. The Nicolet unit is located on the eastern half of northern Wisconsin, east of Rhinelander, and the Chequamegon is located on the western half of northern Wisconsin, near Park Falls. 2

As a result of the Forest Service’s management of the CNNF, the land has returned to forest conditions, although it is now a young forest characterized by even-aged stands (i.e., trees that are roughly *1181 the same age). ROD at 2. While this is an improvement over the conditions left by the timber barons, a truly healthy forest contains trees of different ages, as well as a variety of tree species. Id. Thus, one of the Forest Service’s objectives in managing the forest is to encourage a diversity of tree species and a diversity of tree ages throughout the CNNF. Id. One of the tools that the Forest Service uses to further this objective is selective timber harvesting through restoration projects, such as the project at issue in this case. Id. When selected trees are harvested from an even-aged stand, the stand becomes more diverse over time, as younger trees replace the harvested trees and compliment the older trees that were left in the stand. 3 Id. Thus, restoration projects further not only the economic interests of those who benefit from forest commodities, but also the objective of forest diversity.

On June 18, 2007, Jeanne M. Higgins, the Forest Supervisor for the CNNF, issued a Record of Decision (“ROD”) in which she approved the Fishbone project, a restoration project located on the Che-quamegon side of the forest. Before deciding to implement the project, the Forest Service surveyed the project area and identified a number of project goals. Those goals were designed to bring the project area closer to the condition described by the Forest Plan for the CNNF, a document that the Forest Service created in 2004 to guide its overall management of the forest. The Forest Service identified five project goals, including the reduction of old-age oak and aspen trees (which are susceptible to pests and diseases) and the provision of timber to meet the demand for wood products. See, e.g., Environmental Impact Statement, at ii-iv (executive summary). The resulting project will involve a variety of activities, including various harvesting methods, some road building and some road closings. See, e.g., ROD at 9 (Table 3).

Because the Fishbone project is a “major Federal action[ ] significantly affecting the quality of the human environment,” NEPA required the Forest Service to prepare an Environmental Impact Statement (“EIS”) for the project, which is “a detañed analysis and study conducted to determine if, or the extent to which, a particular agency action wül impact the environment.” See Highway J Citizens Group v. Mineta, 349 F.3d 938, 953 (7th Cir.2003). The final version of the EIS for the Fishbone project was published in June 2007.

The plaintiffs, environmental advocates, challenged the ROD approving the Fish-bone project in administrative proceedings. After exhausting their administrative remedies, plaintiffs commenced this action, which is the fifth in a series of actions that plaintiffs have filed in this District against the Forest Service relating to their approval of restoration projects within the CNNF. In three of the previous three actions, I determined that the Forest Service did not fully comply with NEPA and enjoined the projects until such time as the Forest Service remedied their non-compliance. See Habitat Educ. Ctr. v. Bosworth, 381 F.Supp.2d 842 (E.D.Wis.2005) (“Habitat III ”); Habitat Educ. Ctr. v. Bosworth, 363 F.Supp.2d 1090 (E.D.Wis.2005) (“Habitat II ”); Habitat Educ. Ctr. v. Bosworth, 363 F.Supp.2d 1070 (E.D.Wis.2005) (“Habitat I ”). More recently, I found that the Forest Service’s decision to approve a project complied with NEPA and NFMA. See Habitat Educ. Ctr. v. U.S. Forest Service, 593 F.Supp.2d 1019 (E.D.Wis.2009) (“Hab *1182 itat IV”). Although the present action arises out of the same forest, involves some of the same species, and has some issues in common with the previous actions, the actions are otherwise unrelated.

Free access — add to your briefcase to read the full text and ask questions with AI

Habitat Education Center, Inc. v. United States Forest Service, 603 F. Supp. 2d 1176, 2009 U.S. Dist. LEXIS 22340, 2009 WL 738868 (E.D. Wis. 2009).

603 F. Supp. 2d 1176 (Habitat Education Center, Inc. v. United States Forest Service) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related