Opinion

Powell, J.

1. In June, 1909, Haag, the proprietor of a circus, as party of the first part, and Rogers, as party of the second part, made the following contract: “The said party of the second part hereby agrees to render services as workingman for the season commencing on or about July 20, and to continue for the show seasoii, or so long as mutually agreeable to both parties, under the following conditions: 1st. Party of the second part agrees to render services to Haag’s Mighty Shows, in a painstaking manner, and to be responsible for all property damaged by careless driving or willful carelessness of any kind. 2d. Party of the second part agrees to abide by all rules made by the party of the first part, and for any violation of said rules is liable to a fine of one week’s salary, or dismissal, and contract annulled. 3d. Party of the first part agrees to pay to the said party of the second part the sum of $10 per month, or if the said party of the second part remain in the employment of the party of the first part until close of season on December 31, 1909, party of second part is to be paid at the rate of $18 per month, but under no circumstances, if party of the second part fail to remain until said close of season, shall he be paid over the rate of $10 per month. 4th. ’ Party of the second part can in no way obtain settlement in full of the $10 per month rate unless party of the first part has been notified in written form two weeks previous to settlement. 5th. The party of the first part agrees that said party of the second part is to have a plenty to eat, always the best obtainable under circumstances and the place we are in; [652]*652also that party of the second part is to have the best of treatment if his duties are performed in a painstaking manner. 6th. The management reserves the right to temporarily close the season for cause, during which time no salaries shall be poáid. 7th. Be it clearly understood, by party of the second part that under no circumstances, during the life of this contract, is party of first part liable for any damages for any accident that may happen to party of the second part. 8th. Party of the second part furthermore agrees that no compensation other than board, transportation, and $1 in cash will be given him should he render less than one month’s service. 9th. $5 fine for each drank or fight on show-grounds. Witness whereof hereunto set our hands and seals.” On the back of the contract, which was duly signed by both parties, is the following: “Working Man’s contract. Haag’s Shows. E. Haag, Proprietor. For each drunk on or around show-grounds, $5 fine. For each fight on show-grounds, $5 fine. I agree to pay the above fines. [Signed] John Rogers.” On November 2 .Rogers had a fight on the show-grounds; Haag’s manager discharged him, and tenderd to him $2.25 in full settlement of the balance due him. It is undisputed that, if it is proper to compute the wages at the rate of $10 per month, the correct amount was tendered, and that if they should be computed at the rate of $18 per month, $30.25 would be due. Rogers sued out before a magistrate an attachment, which was levied on a gray horse, and the defendant replevied by giving a bond for the eventual condemnation money. On the trial of the case the magistrate gave judgment in the plaintiff’s favor for $30.25. From this judgment the defendant sought certiorari, but on the hearing in the superior court the judge overruled it, and to this judgment the writ of error now before us was sued out.

As the plaintiff in error (defendant in the original suit) sought certiorari directly from the decision of the magistrate without appealing to a jury, he is in the position where he must assume the burden of showing that there was nothing to submit to a jury, i. e., that the .evidence demanded as a matter of law a finding in his favor. Every issuable fact is to be taken against him. That the plaintiff fought on the show-grounds is undisputed; the circumstances of the fight do not appear; it is not shown whether the plaintiff was the aggressor in the fight or whether the fight was thrust upon him as a matter of self-defense or by other reasons of [653]*653justification. "Whether fighting, on the show-grounds (in the- absence of contractual stipulations on the subject) is sufficient cause for discharge would seem to be a jury question. So the judgment in the plaintiffs favor should stand, unless the contract itself is of such a nature as to forbid the recovery.

The contract provided for wages at the rate of $10 per month, which were paid or tendered, but stipulated for an additional $8 per month to be paid if the plaintiff remained in the employment until the end of the season. Only this additional $8 per month A involved; and the defendant’s contention is that, as the plaintiff did not remain until the end of the season, but was sooner discharged, the language of the contract itself forbids a recovery. It is pointed out that there is an express provision in the contract that it was to continue only “so long as mutually agreeable to both parties,” and that, therefore, the defendant had the right to terminate the employment at his will, either with or without cause. “The law will not construe a contract so as to give the debtor the right to destroy it by a simple refusal to comply with it, unless the terms of the contract are so clear and unambiguous as to make irresistible the conclusion that no other result could possibly be reached, and that such was the intention of the parties. Civil Code, § 3675, par. 4 [Civil Code (1910), § 4268], Nor will a contract bo so construed as to authorize one of the parties to take advantage of his own wrong, unless it be plain and manifest that such was the intention of the parties.” Finlay v. Ludden, 105 Ga. 264 (31 S. E. 180); Milledgeville Cotton Co. v. Cary, ante, 391 (71 S. E. 503).

2. Applying the rule just quoted, we are of the opinion that ihe proper construction to give the contract before us is that either party might terminate it at will; that if the plaintiff terminated it prior to the close of the season, or caused it to be terminated by such conduct on his part as would ordinarily authorize a discharge, he forfeited all claim to compensation beyond $10 per month ; that rF the defendant terminated it voluntarily and without the plaintiff’s having first given adequate cause, he would be liable not only for the $10 per month, but for the additional $8 per month which was being held back as a guarantee against the plaintiff’s quitting the employment before the close of the season. It is frequently the case that an employer is willing to pay a higher rate of wages to a servant who will bind himself to remain in the employment for [654]*654a definite period, or so long as the employer may desire to keep him, than to one who may quit at a time when his services are most needed. It is entirely legitimate for an employer to contract that 'the employee shall have so much wages for his services generally, and so much additional if he does not quit prior to a named date. It is also legitimate (when the terms of the contract so permit) for the employer to hold back the extra pay until lapse of time has demonstrated that the employee has done his part. But in such a case, unless the language of the contract is too clear to admit of anjr other reasonable interpretation, the employer can not capriciously terminate the contract himself so as to avoid liability for the wages at the higher rate. Here the season was nearly over.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Milhollin v. Salomon Smith Barney, Inc.
612 S.E.2d 72 (Court of Appeals of Georgia, 2005)
Die & Mold, Inc. v. Western
448 N.E.2d 44 (Indiana Court of Appeals, 1983)
State Ex Rel. Roberts v. Public Finance Co.
662 P.2d 330 (Oregon Supreme Court, 1983)
Spickelmier Industries, Inc. v. Passander
359 N.E.2d 563 (Indiana Court of Appeals, 1977)
Avondale Mills v. Saddler
290 So. 2d 173 (Supreme Court of Alabama, 1974)
Thompson v. Burr
490 P.2d 157 (Oregon Supreme Court, 1971)
Darby v. McNelley
120 S.E.2d 153 (Court of Appeals of Georgia, 1961)
American Security Life Ins. Co. v. Moore
72 So. 2d 132 (Alabama Court of Appeals, 1954)
Coleman v. Graybar Electric Co., Inc
195 F.2d 374 (Fifth Circuit, 1952)
Watwood v. Potomac Chemical Co.
42 A.2d 728 (District of Columbia Court of Appeals, 1945)
C. v. Hill Company Inc. v. Weinberg
19 S.E.2d 430 (Court of Appeals of Georgia, 1942)
Webb v. Pullman Co.
196 S.E. 477 (Court of Appeals of Georgia, 1938)
Cotterill v. Hopkins
178 S.E. 444 (Supreme Court of Georgia, 1935)
Gilbert v. Norfolk & Western Railway Co.
171 S.E. 814 (West Virginia Supreme Court, 1933)
Estate of Hippe v. Gallet
228 N.W. 522 (Wisconsin Supreme Court, 1930)
Colonial Hill Co. v. Greenoe
134 S.E. 633 (Court of Appeals of Georgia, 1926)
Geer v. Grow
120 S.E. 426 (Court of Appeals of Georgia, 1923)
Superior Motor Co. v. Chevrolet Motor Co.
212 P. 100 (Supreme Court of Kansas, 1923)
Russell v. H. W. Johns-Manville Co.
200 P. 668 (California Court of Appeal, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
72 S.E. 46, 9 Ga. App. 650, 1911 Ga. App. LEXIS 277, Counsel Stack Legal Research, https://law.counselstack.com/opinion/haag-v-rogers-gactapp-1911.